Work order (SOW)
The work order (statement of work, SOW) is the document that describes the work a supplier or a staff member must perform: the tasks, their outcomes and their limits. In the procurement process of the PMBOK Guide, the buyer writes it before the bid documents. The US Department of Defense handbook MIL-HDBK-245D (1996) gives a method for it. The writer draws the tasks from the work breakdown structure (WBS) and sorts them into three sections: the scope, the applicable documents and the requirements. The writer states the expected results and leaves the method to the supplier. In Switzerland, HERMES uses the term work order for the document by which the project manager assigns a task internally or externally.
Goal
The work order is the document by which the buyer or the project manager describes the work assigned to a supplier under contract or to a staff member. The PMBOK Guide glossary defines the SOW as a narrative description of the products, services or results to be delivered. The MIL-HDBK-245D handbook asks the writer to define this work in specific, quantitative and performance-based terms (§3.1). Bidders learn from the work order what the buyer needs and write offers that respond to it. According to the PMBOK Guide, one selection criterion judges whether the proposed approach responds to the SOW (§X4.7). After the award, the buyer and the supplier look in it for their rights and obligations. The buyer measures the supplier's performance against it (MIL-HDBK-245D, §3.4).
The technique draws the line between the work that the buyer assigns to a supplier and the work it keeps. It delivers a document in three sections. Each task in this document corresponds to an element of the WBS.
The US Department of Defense published the handbook in 1996 for its solicitations and contracts (§1.1). Its vocabulary is that of US military procurement. Its method applies to any contract for work or services.
Usage
When to use it
- Work assigned to a supplier: describe the tasks before writing the bid documents.
- Several offers to compare: every bidder prices the same work.
- Fixed-budget selection: the PMBOK Guide allows this method only if the buyer defines the SOW precisely (§X4.6).
- Project split into lots: each contract receives a work order drawn from the WBS.
- HERMES project: the project manager delegates a task to a staff member or to a third party.
- Scope that the parties could dispute: before the award, the work order defines the tasks that the supplier must perform.
When not to use it
- Solution left to the bidders: each bidder writes its own work order from a statement of objectives (SOO, §1.3).
- Standard product with no work to perform: give the item number and the quantity in a request for quote (RFQ).
- Method to define for a repetitive workstation: standard work defines the method of a workstation, while the work order defines only results.
Description
The work order, the specification and the HERMES specifications
| Document | It defines | Example |
|---|---|---|
| Work order (SOW) | The work that the supplier performs and the outcomes it hands over | "The supplier shall establish, implement and control a reliability and maintainability programme." |
| Specification | The design and performance requirements of the product | The mean time between failures (MTBF) and the mean time to repair (MTTR) |
| Specifications (HERMES) | The requirements for the items to be procured and the procurement procedure | The contract deadlines |
The handbook separates the work order from the specification (§3.2). The work order cites the specification and does not repeat its values.
In HERMES, the specifications describe the requirements for the items to be procured (task 5.4.3.5), while the work order describes the supplier's work. The French version of HERMES calls the specifications cahier des charges. In French-speaking Switzerland, that term also means a job description. Neither sense refers to the SOW.
The three sections
The writer departs from the standard format (§3.6) when the project requires it.
1. Scope. A short text sets the breadth and the limits of the work. A background section may precede it. The background is limited to what the bidder must know to understand the purchase. The scope contains no direction to perform tasks, no data requirement and no description of the deliverables (§3.6.1).
2. Applicable documents. The section lists the standards, directives and other documents that the work order invokes. Each document carries its version: its date or its revision letter. The writer justifies each document from a zero base. The writer drafts this section after the first draft of section 3 (§3.6.2). Every document that section 3 invokes appears in section 2. Section 3 states which part of the document applies.
3. Requirements. The section carries the tasks that the supplier performs (§3.6.3). It is well written when:
- the buyer and the bidders can estimate the cost, the expertise, the staffing and the resources of the work;
- the supplier knows what the buyer requires and can complete each task;
- no task leaves doubt whether the supplier must perform it;
- the section invokes only the minimum of standards and specifications;
- the background and the suggested procedures stand apart from the supplier's obligations;
- each task states the expected result and leaves the method to the supplier.
The writer numbers the paragraphs consecutively within each section. A period separates the levels: 3, 3.1, 3.1.1, 3.1.1.1. The numbering stops at the third sublevel where possible. Each paragraph carries a title and a single task (§3.6.6). The title page gives the title, the date of preparation, the request or contract number, the revision number with its date and the organisation that wrote the work order. When the work order exceeds five pages, a table of contents follows (§3.6.5).
Writing from the WBS
The handbook builds the work order from the WBS. The WBS orders the elements of the work order. The team uses it as a checklist to verify that the work order covers all the work. The drafting team follows these steps (§3.8.2):
- Keep the tasks that add value. A management task enters the work order on the same footing as a technical task when it adds value to the product.
- Research the market. The team looks for commercial products that meet the need.
- Review the documents that authorise the project. They set its objectives.
- Review the management and control requirements. The team checks what the organisation's directives impose on the management, the procurement and the control of the project.
- List the candidate documents. The team notes the exact parts of the directives and standards that the project must comply with. It keeps the minimum and drops any citation that dictates the method. This working list feeds section 2.
- Sort the work. The team splits the work of the WBS into in-house work and contracted work.
- Group the contracted work by contract. The procurement plan sets the calls for tenders, the contract type, the schedule, the estimated cost and the selection method. In a HERMES project, the procurement analysis contains this procurement plan (outcome 4.4.1.9). Each contract receives a work order that covers all its WBS elements.
- Name the writers. The team covers management, technical matters and the contract. Its leader has written work orders before (§3.6.4). The team sets each writer's share.
- Write the sections in the order 1, 3, 2 (§3.6.2). For each WBS element, section 3 states the tasks and the deliverables.
- Check the work order against the specification. Technical performance stays in the specification.
- Derive the other parts of the call for tenders from the work order. The buyer derives from it the list of data to deliver, the instructions to bidders and the evaluation criteria. In a HERMES call for tenders, the structure of the offer stands in for the instructions. The list of criteria carries the evaluation criteria. The list of data to deliver has no equivalent in HERMES.
A simple purchase does not always justify a full WBS. The handbook then applies the same logic in fewer steps (§3.8.1, §3.8.3). The team defines the deliverables and sets the requirements of each with the document list. It determines the services or data needed after delivery. It names the writers and then writes the work order.
Writing the requirements
The handbook asks for short sentences, simple wording and a logical or chronological order (§3.6.7). It reserves shall for an obligation and will for the buyer's intent. The supplier's obligation takes shall: "The supplier shall establish the migration plan." The buyer's intent takes will: "The office will review the plan within ten working days." The writer uses will only for a purpose or an intent that the buyer declares. The writer defines each acronym at its first use and keeps the same term for the same thing throughout the work order. The verbs name work: establish, analyse, develop, deliver, verify.
| Written | Wanted | Rule (§3.6.7 and Appendix C) |
|---|---|---|
| "A migration plan shall be established." | "The supplier shall establish the migration plan." | The active voice names who performs. |
| "The supplier shall deliver the reports and/or the logs." | "The supplier shall deliver the reports and the logs." | "And/or" leaves the choice to the supplier. |
| "It shall send them to the project manager." | "The supplier shall send the reports and the logs to the project manager." | The repeated noun replaces the pronoun. |
| "The supplier shall configure the solution in accordance with applicable published specifications." | "The supplier shall configure the solution according to chapter 3 of specification S-04." | A phrase with several meanings defines nothing. |
| "The supplier shall train the users to the satisfaction of the project manager." | "The supplier shall train the users according to the programme in annex 2 and hand over the attendance list." | One person's judgement does not measure a result. |
In a HERMES project
In HERMES 2022, the work order is outcome 4.4.1.7. When planning, managing, informing and controlling, the project manager delegates tasks to the project staff through this work order. The project manager issues it internally or externally. The project manager creates the work orders in the task Manage and control project (5.4.3.33) and coordinates their dependencies. Where applicable, the project manager and the user representative agree on the solution-specific work orders in advance. When the buyer issues a call for tenders, the writer can place part of the content of the HERMES work order in the three sections of the SOW. This placement is a reading of the two documents. Neither HERMES nor the handbook sets it.
| HERMES content (4.4.1.7) | Proposed place |
|---|---|
| Work objectives | Section 1 (Scope) |
| Boundaries | Section 1 (Scope) |
| Prerequisites and dependencies | The prerequisites go in the background of section 1. The dependencies between work orders have no clear place. |
| Outcomes | Section 3: each task states the expected result (§3.6.3). |
| Activities and their reference to the outcomes | Section 3: one numbered paragraph per task |
| Those responsible/involved | Outside the SOW: the supplier sets its staffing (§3.6.3). |
| Plan hours | Outside the SOW: the bidder estimates the effort (§3.6.3). |
| Deadlines | Outside the SOW: only significant milestones appear in it (§3.6.4). |
| Status | Outside the SOW: it belongs to monitoring the execution. |
| Resource requirements | Outside the SOW: the bidder estimates them (§3.6.3). |
| Presentation of outcomes | Outside the SOW: the handbook excludes data format instructions from it (§3.6.4). |
| Quality assurance | Section 3: a supplier task. The standard it invokes goes in section 2. |
The execution order (4.4.1.13) is a binding agreement between the project sponsor and the project manager for solution development. The project initiation order (4.4.1.33) is an agreement between the project sponsor and the project manager for the initiation phase. Neither describes the work of a supplier.
The handbook and the HERMES work order put the deadlines in different places. The handbook excludes the delivery schedule from the SOW and allows only significant milestones (§3.6.4). The HERMES work order carries the deadlines and the plan hours of each activity, because the project manager plans and controls with it. In a public call for tenders, the HERMES specifications set the contract deadlines (outcome 4.4.1.8). HERMES does not say whether the work order repeats them. The work order should not repeat them: two documents that carry deadlines diverge at the first change. When the project manager assigns a task to a staff member or to a supplier already under contract, the work order keeps the deadlines and all the HERMES content. The quote request (4.4.1.25) obtains offers for internal and external services. HERMES ties it to no procedure. It suits a service bought outside a call for tenders. It gives the subject of the order, the deadlines, the conditions and the quote specifications.
Pitfalls
Prescribing the method. The handbook excludes "how to" requirements (§3.3, §3.6.4). The supplier must be able to deliver in the most economical way. An imposed method takes that choice away. The work order asks: "The supplier shall migrate the case files and hand over the migration record." The migration tool remains the supplier's choice.
Citing a whole document. A document listed in section 2 with no limit in section 3 binds the supplier to comply with all of it. The supplier then prices requirements that the project does not need. This blanket reference has often weighed heavily on cost (§3.6.2).
Writing the product requirements into the work order. A performance value or a design parameter belongs in the specification or in the HERMES specifications. The handbook also forbids using the work order to establish or amend a specification (§3.6.4). The product would then have two definitions that diverge at the first change.
Slipping a task into the scope. A direction written in the scope escapes the numbering of section 3. The supplier does not price it. The buyer cannot cite it (§3.6.1).
Mixing background and obligations. A suggested procedure written as a task becomes an obligation. The bidder then prices what the buyer only meant to advise (§3.6.3).
Putting the evaluation criteria in the work order. The handbook excludes them from the SOW (§3.6.4). In a HERMES call for tenders, they go in the list of criteria of the tender documentation. The vendor assessment builds them.
Putting several tasks in one paragraph. The buyer can no longer price, cite, adapt or withdraw one task without touching the others (§3.6.6).
AI considerations
A language model drafts a first version of section 3 from the WBS elements: one numbered and titled paragraph per task. It checks the reciprocity of sections 2 and 3. It lists each document that section 3 invokes and section 2 does not list. It then lists each document in section 2 that section 3 does not invoke. It flags the passive without an actor, the pronouns, "and/or" and the phrases of the handbook's Appendix C such as "in accordance with applicable published specifications". It flags a performance value that belongs in the specification. It spots a work direction in the scope. It translates the work order into a second official language for review.
The split between in-house and contracted work stays with the team, because it commits the budget and the organisation. A model asked to complete a work order adds plausible tasks. Each added task becomes a cost that the bidder prices. A model trained on US SOWs imports their military acronyms and their references to federal regulations. The estimated cost and the budget do not go to an AI service that the organisation has not authorised.
Examples
In a fictitious case, a federal office buys the migration of the data from its old case management system.
| No. | Title | Requirement | WBS element |
|---|---|---|---|
| 3.1 | Migration plan | The supplier shall establish the migration plan for the 180'000 case files and the 2.5 TB of attachments. The plan shall set the migration order of the case file types and the rollback procedure. | 1.4.1 Migration preparation |
| 3.2 | Trial migration | The supplier shall migrate 5'000 case files into the test environment and hand over the trial migration report. | 1.4.2 Trial migration |
| 3.3 | Final migration | The supplier shall migrate all case files and their attachments into the production environment. | 1.4.3 Final migration |
| 3.4 | Completeness check | The supplier shall compare the number of case files and attachments in the old and the new system. The supplier shall hand over the migration record. | 1.4.4 Migration check |
| 3.5 | Data protection | During the migration, the supplier shall apply the measures in chapter 4 of document 2.1. | 1.4 Data migration |
Section 2 of the same work order lists a single document, because only requirement 3.5 invokes one: "2.1 ISDP concept of the Case Management project (version 1.2)". The ISDP concept is the HERMES outcome that covers information security and data protection.
Visualisations
A diagram shows the path from the WBS to the work order. It separates in-house work from contracted work, gives each contract a work order and numbers the drafting order of the three sections. It links section 2 to section 3 and leaves the specification outside the work order. The tables set out the boundary between the three documents, the writing rules, the placement of the HERMES work order and the extract of section 3.
Cost
| Dimension | Level | Rationale |
|---|---|---|
| Preparation | Medium | The team reviews the project documents, researches the market and sorts the work of the WBS. |
| Execution | High | For a complex purchase, one task per paragraph, verifiable results and a section 2 justified document by document require several reviews. |
| Documentation | Medium | The work order follows the WBS. A change of scope modifies both. |
Tooling
HERMES publishes a work order template on hermes.admin.ch. When the procurement unit provides its own templates, those take precedence.
A word processor with hierarchical numbering and version tracking holds the work order. A planning tool holds the WBS and exports its elements. A spreadsheet links each WBS element to the section 3 paragraph that covers it and to the section 2 document that this paragraph invokes. The table shows an element without a paragraph or a document without a requirement.
Sources
- US Department of Defense, Department of Defense Handbook for Preparation of Statement of Work (SOW), MIL-HDBK-245D, 3 April 1996: §1.1 for what the handbook covers; §1.3 for the statement of objectives; §3.1 to §3.4 for the purpose of the SOW and its boundary with the specification and the contract; §3.6 for the three sections, the numbering, the title page, the language rules and the list of dos and don'ts; §3.8 for writing from the WBS; Appendix C for the phrases having multiple meanings.
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., Appendix X4: §X4.5 Bid Process and Documents and Figure X4-1 for the place of the SOW in the procurement process; §X4.6 for the fixed-budget method; §X4.7 for the selection criterion that judges the proposed approach against the SOW; glossary, entry statement of work.
- Swiss Confederation, Federal Chancellery, HERMES 2022, outcome Work order: the description and the content.
- Swiss Confederation, Federal Chancellery, HERMES 2022, outcome Tender documentation: the specifications and their deadlines.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management reference manual: tasks 5.4.3.5 Prepare call for tenders and 5.4.3.33 Manage and control project; outcomes 4.4.1.9 Procurement analysis, 4.4.1.13 Execution order, 4.4.1.25 Quote request and 4.4.1.33 Project initiation order.