Work Breakdown Structure (WBS)
The work breakdown structure (WBS) is the hierarchical decomposition of all the work a project must carry out to produce its deliverables. ISO 21511 gives guidance on it for project and programme management. The first level is the project. Each level details the one above it down to the work packages. The team gives each work package a single owner, estimates it and checks it. The schedule, the budget and the risk register reuse the WBS codes. Work that is not in the WBS is not part of the project.
Goal
The WBS is a tree. Its root is the project, its branches the deliverables and its leaves the work packages.
The scope statement says in prose what the project delivers. It says neither who produces each part nor what it costs. The WBS breaks this scope into units that the team can assign, estimate and track.
The technique produces the coded WBS. A WBS dictionary often accompanies it. In a predictive approach, the scope baseline consists of the WBS, the scope statement and the dictionary. On this basis the sponsor approves the project's scope and budget.
For the business analyst, the WBS turns requirements into work. BABOK lists it under functional decomposition: it decomposes the work to be done. BABOK also cites it as a common way to describe the elements to estimate. The analyst adds a WBS column to the requirements traceability matrix. The analyst maps the requirements against the WBS elements in the cross-reference matrix and checks that each requirement finds its deliverable in the tree. Faced with a change request, the analyst uses the WBS codes that the request touches to bound its impact.
Usage
When to use it
- Validated scope without a plan: turn the scope statement into work packages that the team can assign.
- Effort and cost estimation: estimate each work package, then add up the estimates along the tree.
- Building the schedule: derive the activity list from the work packages before drawing the Gantt chart.
- Project with several teams or suppliers: give each work package a single owner and fix the boundaries between the packages.
- Subcontracting part of the project: the supplier details its part in a contract WBS attached to the project's WBS.
- Earned value management: the control accounts and the work packages carry the budget and the progress measure.
- Change request: locate the change in the tree and list the work packages, costs and risks it affects.
When not to use it
- Agile development with evolving scope: the deliverables emerge from one iteration to the next. Keep a prioritised backlog through backlog management.
- Small single-team project lasting a few weeks: the tree adds nothing to a task list. Use a task board.
Description
The components of the WBS
The project occupies level 1 and carries code 1. Each element takes its parent's code and appends its sequence number: 1.3, then 1.3.2, then 1.3.2.1. The code identifies the element in every other project document. These identifiers form a code of accounts. Costs, durations and resources add up by these codes along the tree.
The work package is the element at the lowest level. According to the NASA handbook, no other work package shares its content. A single organisational unit owns it. It has a start date, an end date and a budget or an effort. Either its duration stays short or intermediate milestones measure its progress. HERMES uses the same term.
The control account groups two or more work packages. Each work package belongs to a single account. The account is a management control point. Management integrates the scope, the budget and the schedule there and compares them with the earned value. Its code links the WBS to the organisation's accounting. An organisational unit owns each account.
The planning package sits under a control account. It holds work that lies far in the future. The team knows its content but has not yet detailed its activities. The team will break it down into work packages later.
For PMI and NASA, the WBS stops at the work package. Activities belong to the schedule. BABOK files phases, milestones, activities, tasks, work items and deliverables in the WBS. Its list mixes the WBS and the schedule. PMI's boundary becomes necessary once the schedule codes each activity by the work package it delivers. The WBS says what to produce. The schedule says in what order and when.
Naming deliverables
Work packages are verifiable products, services or results. The NASA handbook rejects elements such as Design, Engineering, Fabrication, Phase A or Direct labour. The first three are functions or organisations. Phase A is a period. Direct labour is a cost category. None of them names a thing that the project delivers.
The team therefore names each element with a noun: "Application form" rather than "Develop the form". The verb goes to the activities in the schedule. One question settles it: can the team observe that the element is finished? A deliverable finishes. A function never does. Project management is the exception. PMI includes it in the 100% rule. NASA makes it element 01 of its standard template. Its children remain deliverables: the project management plan and the status reports.
The NASA rule targets aerospace products. An IT or administrative project keeps the rule's focus on deliverables: a report, an interface or trained staff. The PMBOK Guide is more flexible: its sample WBS contains elements such as "Needs assessment".
Deliverables or phases at level 2
The PMBOK Guide places either the major deliverables or the life cycle phases at level 2. In the phase form the deliverables move down to level 3. The NASA handbook judges the phase-based WBS unsuitable.
In a phase-based WBS, one deliverable is spread over several branches. The application form appears under Concept and under Implementation. Nobody owns the whole form. No element shows its cost.
In a deliverable-based WBS, each deliverable has its own branch, owner and total. The schedule then marks the phases with milestones. This form suits a committee that tracks deliverables and their cost. The phase form suits an organisation that releases the budget phase by phase and wants to read it in the WBS.
The PMBOK Guide describes a third form for subcontracted work. The supplier develops a contract WBS for its part. This contract WBS attaches to an element of the project WBS.
Building the WBS
The team starts from the scope statement, the project charter and the validated requirements. Without a validated scope statement the tree freezes assumptions. The team first frames the scope through scope modelling.
Top-down construction starts from the project and works down to the work packages. Bottom-up construction groups work items that the team already knows under common parents. It helps when the team knows the work but not its structure. An organisation sometimes provides WBS guidelines or templates per project type. PMI's Practice Standard for Work Breakdown Structures contains templates per application area. The first five steps follow those of the PMBOK Guide.
- Identify the deliverables and the related work. Each requirement leads to at least one deliverable. The team adds the deliverables that nobody asks for: project management, data migration, training, documentation and user acceptance testing (UAT).
- Choose the structure. The team decides what level 2 carries: the deliverables, the phases or the subcontracted parts.
- Decompose. The team breaks each element into its components, branch by branch, down to the work package. One branch can stop at level 3 while its neighbour goes down to level 4.
- Code. Each element receives its hierarchical code. The team freezes the codes before the schedule and the budget reuse them.
- Verify the decomposition. The team checks that each level is complete and that the depth fits.
- Describe each work package in the dictionary. Each work package receives its entry: description of work, owner, effort and acceptance criteria.
- Have the sponsor or the steering committee approve the WBS. It then enters the scope baseline.
The people who will do the work take part in the decomposition workshop. According to the NASA handbook, a hierarchy goes wrong when the competent people accountable for the work are missing. A template taken from an earlier project saves time. It also carries over that project's errors. The team reviews it element by element before adopting it.
How far to decompose
An element becomes a work package when a single owner can take it on and the team can estimate it and observe its completion. Each branch goes only as deep as management, visibility and control require. The number of levels depends on the size of the project, on its technical uncertainty and on the organisation.
Decomposing too finely wastes management effort and resources. It also makes the data harder to roll up from one level to the next.
HERMES states that a work package typically lasts two to six weeks. The 8/80 rule is common in practice. It says that a work package takes between 8 and 80 hours of work. The team can adopt it as a convention for its project.
A deliverable that lies far in the future sometimes cannot be decomposed yet. According to the PMBOK Guide, the team then waits until it is agreed before detailing it. It remains a planning package with an order-of-magnitude estimate. PMI calls this practice rolling wave planning. You will find the resulting estimate under rolling wave estimation.
Verifying the decomposition
The 100% rule is the first check. According to the PMBOK Guide, the WBS includes all the product work and all the project work. Project management is part of it. The work at the lower levels rolls up to the higher levels. The team omits nothing and does no extra work. The NASA handbook adds that a WBS never contains unauthorised work.
At each parent, the team checks that the children are necessary and sufficient to produce it.
The NASA handbook's cross-reference matrix checks that the WBS covers the scope. One axis lists the paragraphs of the documents that define the scope: the requirements, the scope statement, the project charter or the statement of work. The other axis lists the WBS elements. An X marks each element that serves a paragraph. A paragraph without an X shows a gap in the scope. An element without an X shows work outside the scope. The team removes that element or has the requirement added through the formal channel.
| Requirement | 1.2.1 Application form | 1.2.2 Plan submission | 1.2.3 Fee payment | 1.3.2 Consultation interfaces | 1.3.3 Decision and notification | 1.3.4 Monthly statistics |
|---|---|---|---|---|---|---|
| R1 The applicant submits the application online | X | |||||
| R2 The applicant attaches the plans as PDF files | X | |||||
| R3 The applicant pays the fee online | X | |||||
| R4 The department consults the cantonal offices involved in the case | X | |||||
| R5 The department notifies the decision electronically | X | |||||
| R6 The applicant follows the status of the application |
Project management and the migration of pending cases take their X from the scope statement.
An element shared by two parents appears only once. If the team counts it under both parents, its cost doubles and no total shows it. Functional decomposition shows you where to place it.
The WBS dictionary
The WBS dictionary describes each element of the tree. The PMBOK Guide lists its content: the code, the description of work, the assumptions and constraints, the responsible unit, the milestones, the associated activities, the resources, the cost estimates, the quality requirements and the acceptance criteria. Most of this information comes from other processes. The team adds it as planning proceeds.
The description of work sets the boundary of the work package: what it includes and what it excludes. With the dictionary the team identifies all the work and assigns none of it twice.
| Field | Content |
|---|---|
| Code | 1.3.2.1 |
| Element | Interface with the environment department |
| Description of work | Send the case file to the environment department and receive its opinion in the portal. Includes the exchange format, the development and the integration tests. Excludes any change to the environment department's software. |
| Assumptions and constraints | The environment department provides a document exchange interface before 31 March. |
| Owner | Integration team of the cantonal IT directorate |
| Milestones | Exchange format validated on 15 February. Interface delivered for testing on 30 April. |
| Estimated effort | 18 person-days |
| Acceptance criteria | A test case file makes the round trip without manual entry. The opinion appears on the dashboard of the building department. |
The PMBOK Guide calls for a dictionary on projects with complex or interdependent deliverables. When a single team owns all the work packages, the WBS alone is enough. Once several teams or suppliers share the work packages, the descriptions of work set what falls to each.
Keeping the WBS up to date
Once approved, the WBS changes only through change control. The NASA handbook asks that each revision carry its justification and the project manager's approval. The WBS and the dictionary change in the same revision.
A published code stays attached to its element. If the team renumbers a branch, the schedule, the budget and the risk register point to other elements. A deleted element leaves its code vacant. An added element takes the next sequence number.
What the WBS feeds
| Document | What it takes from the WBS |
|---|---|
| Activity list and Gantt chart | Each activity carries the code of the work package it delivers. |
| Bottom-up estimation | The team estimates each work package, then adds up the estimates to the project. |
| Budget and earned value | The costs of the work packages add up by control account. The team measures earned value per work package and per account. |
| RACI matrix | The rows are the work packages. The columns are the roles or the people. |
| Risk register | Each risk carries the code of the element it affects. |
| Requirements traceability matrix | Each requirement points to the WBS deliverable that satisfies it. |
The risk register can carry two codes. The WBS code says which part of the project the risk affects. The risk breakdown structure says where it comes from. The value breakdown structure assigns an estimated value to each WBS element.
The WBS, the schedule and the organisation chart
A tree that the team reads from left to right as a timeline mixes the WBS with the schedule. Dependencies and dates belong to the Gantt chart and the critical path method.
The organizational breakdown structure (OBS) divides the project organisation into units. The WBS divides the work. According to the NASA handbook, the structure of the organisation must not dictate the structure of the WBS. The content of the work dictates it. A WBS modelled on the departments gives each head of department a branch. Deliverables that cut across several departments have no owner in it.
The organisation enters the WBS at the control account. The NASA handbook places this account where a WBS element crosses an organisational unit. The responsibility assignment matrix shows this crossing. Its rows are the WBS elements and its columns the OBS units. An element that two units carry out keeps its single branch and opens one account in each unit.
| Level 2 element | Project leadership | Portal team | Integration team | Building department |
|---|---|---|---|---|
| 1.1 Project management | CA1: work packages 1.1.1 and 1.1.2 (30 days) | |||
| 1.2 Applicant counter | CA2: work packages 1.2.1 to 1.2.4 and planning package 1.2.5 (115 days) | |||
| 1.3 Case processing module | CA3: work packages 1.3.1 and 1.3.3 (45 days) | CA4: work packages 1.3.2.1 and 1.3.2.2 (30 days) | ||
| 1.4 Migration of pending cases | CA5: work packages 1.4.1 and 1.4.2 (30 days) | |||
| 1.5 Go-live | CA6: work packages 1.5.1 to 1.5.3 (40 days) |
In HERMES
HERMES 2022 has no WBS. Its execution structure plan is a tree of phases, tasks and outcomes. The project manager exports it from a scenario in HERMES online. This plan sequences the project phase by phase. The WBS structures the deliverables.
The project manager plans the classical phases in detail by work packages. A HERMES task yields one or more work packages. Each work package leads to one or more outcomes. It has one owner. Several people can work on it alongside its owner. HERMES plans on a rolling basis: the project manager plans the next phase in detail at the end of the current one. A project manager who also keeps a WBS files each HERMES work package in it under the deliverable that its outcomes produce.
On agile projects
According to the PMBOK Guide, the WBS corresponds to the product backlog in an agile project. The backlog items break down into epics and then into user stories. The backlog plays the same role as the WBS: it structures the work to be done. The backlog is a prioritised list of the known items. It does not apply the 100% rule. Story decomposition and story mapping break this work down.
AI considerations
A language model proposes a first draft of the WBS from the scope statement. It flags the elements named by a verb or by a phase. It codes the tree, converts it into an indented list for the planning tool and drafts a first dictionary entry for each work package. It maps a list of requirements against the WBS elements and builds the cross-reference matrix.
A model does not know the agreed scope. It adds plausible deliverables that nobody has authorised. It forgets the deliverables specific to the Swiss context: the public procurement procedure, the translation into a second national language and compliance with the Federal Act on Data Protection. It does not know which unit owns which work package. The 100% check stays with the team and the sponsor. The WBS carries budgets and supplier names. The team processes it in an AI tool that its organisation has authorised.
The Drafting the WBS and the schedule page gives you more detail.
Examples
A canton replaces the paper filing of building permit applications with an online portal. Its WBS is oriented towards deliverables. Each work package carries its estimated effort in person-days. Each parent carries the sum of its children.
The total includes planning package 1.2.5 with its order-of-magnitude estimate. The 100% rule also applies to work that the team has not yet decomposed. Without this package the total would fall to 250 days. The electronic signature would then leave the scope without a decision.
Visualisations
The team draws the WBS as a tree: the project at the top and each element under its parent with its code. The tree is used in workshops and before the steering committee, for which it often stops at level 2 or 3. The working copy is an indented list with codes in the spreadsheet or in the planning tool. Both forms carry the same WBS. The team keeps the dictionary as a table with one row per element and one column per field.
| Code | Element | Type | Effort (person-days) |
|---|---|---|---|
| 1 | Building permit portal | parent | 290 |
| 1.1 | Project management | parent | 30 |
| 1.1.1 | Project management plan | work package | 8 |
| 1.1.2 | Status reports | work package | 22 |
| 1.2 | Applicant counter | parent | 115 |
| 1.2.1 | Application form | work package | 30 |
| 1.2.2 | Plan submission | work package | 20 |
| 1.2.3 | Fee payment | work package | 15 |
| 1.2.4 | Application tracking | work package | 10 |
| 1.2.5 | Electronic signature | planning package | ≈ 40 |
| 1.3 | Case processing module | parent | 75 |
| 1.3.1 | Department dashboard | work package | 20 |
| 1.3.2 | Consultation interfaces | parent | 30 |
| 1.3.2.1 | Environment interface | work package | 18 |
| 1.3.2.2 | Fire safety interface | work package | 12 |
| 1.3.3 | Decision and notification | work package | 25 |
| 1.4 | Migration of pending cases | parent | 30 |
| 1.4.1 | Migration rules | work package | 10 |
| 1.4.2 | Migrated and checked cases | work package | 20 |
| 1.5 | Go-live | parent | 40 |
| 1.5.1 | Acceptance report | work package | 20 |
| 1.5.2 | Training materials | work package | 12 |
| 1.5.3 | Applicant guide | work package | 8 |
Cost
| Phase | Level | Rationale |
|---|---|---|
| Preparation | Medium | A validated scope statement and validated requirements as input. Gather the people who will do the work in a workshop. |
| Execution | Medium | One or two decomposition workshops, then the check with the cross-reference matrix. High on a project with several suppliers. |
| Documentation | High | One dictionary entry per work package. The team keeps it under change control with the WBS. Medium without a dictionary. |
Tools
A whiteboard and sticky notes are enough for the decomposition workshop. Mind mapping software (XMind, MindManager) draws the tree during the session and exports it as a list. A spreadsheet holds the indented list, the codes and the sums per level. MS Project and Primavera P6 manage WBS codes and add up effort and costs along the tree. A specialised tool such as WBS Schedule Pro draws the tree from the plan. In agile work, Jira and Azure DevOps hold the hierarchy of epics, features and user stories.
Sources
- Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., PMI: the Develop Scope Structure process, the dictionary and the correspondence with the product backlog (§2.2.2.4); the WBS, the work package, the control account, the planning package and the content of the dictionary (Section 4, entry Scope baseline); the control account linked to accounting (Section 4, entry Financial management plan); the WBS code of the activities (Section 4, entry Activity attributes); the WBS in the traceability matrix (Section 4, entry Requirements traceability matrix); the decomposition activities, top-down or bottom-up construction, the forms of WBS, the necessary-and-sufficient test, excessive decomposition, rolling wave planning and the 100% rule (Section 5, entry Decomposition, figures 5-6 to 5-8); bottom-up estimating, cost aggregation, the OBS, the responsibility assignment matrix and risk categorization by affected part (Section 5).
- Project Management Institute, Practice Standard for Work Breakdown Structures, 3rd ed., 2019: the detailed WBS reference that the PMBOK Guide points to.
- NASA, NASA Work Breakdown Structure (WBS) Handbook, NASA/SP-2010-3404, January 2010: the product-oriented WBS and the project boundary (§2.1); the cross-reference matrix (§3.3.3); the number of levels (§3.3.4); completeness and unauthorised work (§3.3.5); change control (§3.3.6); the control account where a WBS element crosses an organisational unit (§3.4, glossary); the unique code of each element for the life of the project (§3.4.2); the dictionary (§3.4.4); common errors (§3.5); the WBS and the organisation (§4.2); the characteristics of the work package (appendix B, glossary); project management as element 01 of the standard level 2 template (appendix C).
- ISO, ISO 21511:2018, Work breakdown structures for project and programme management: the international standard devoted to the WBS.
- Federal Chancellery, HERMES 2022, Project Management Reference Manual: the execution structure plan (7.4.5.2), rolling planning and planning by work packages (7.4.5.3).
- IIBA, A Guide to the Business Analysis Body of Knowledge (BABOK Guide) v3: the WBS as a decomposition of the work to be done (§10.22) and as a common description of the elements to estimate (§10.19).

