Decision map of the work mode. On the left, a two-by-two grid crosses the coupling of work (loose or tight) with common ground (low or high). Tight coupling and low common ground: on site. Tight coupling and high common ground: hybrid with fixed days on site. Loose coupling and high common ground: remote. Loose coupling and low common ground: remote with an on-site kick-off meeting. A dashed outline surrounds the three hybrid and remote cells: collaboration readiness and collaboration technology readiness are required there. On the right, the setup of each mode. On site: team room; wall or board for the schedule. Hybrid: fixed days on site for coupled work. Remote: online team space with files, discussion threads and calendar; videoconferencing; messaging; at least one face-to-face meeting; team charter.

Virtual Teams and Colocation

Colocation and the virtual team are two ways a project team can work. Hybrid work combines them. Colocation places all or some of the most active members in the same physical location. A virtual team pursues a shared goal with little or no face-to-face contact. The project manager chooses on-site, hybrid or remote work for each work package and each phase. The decision rests on the coupling of the work and on the members' common ground. The project manager then sets the rules, tools and meetings that the mode requires.

Goal

The project manager fits the work mode to each package and each phase rather than to the whole project. The same developer can attend the workshops on site during scoping, then work from home during delivery.

The decision produces a work mode grid, a section of the team charter on ways of working and the list of collaboration tools chosen. For each package and each phase, the grid records the chosen mode and the reasons for it.

Usage

When to use it

  • Forming the project team: decide who works from where before signing the assignments and contracts.
  • Expertise missing at the project site: bring the specialist in remotely.
  • Team spread over several sites or language regions: set the language, the shared hours and the tools before the first deliverable.
  • Phase of ambiguous and interdependent work: scoping, requirements workshops, architecture; decide whether to bring the team together.
  • Move from one phase to the next: review the work mode when the coupling of the work changes.
  • Member or supplier joining the team remotely: plan time to get to know each other and a face-to-face meeting.
  • Reopened decisions or repeated misunderstandings between two sites: check whether the work given to remote members is too tightly coupled.
  • Travel or office costs that threaten the project: give the loosely coupled packages to remote members.

When not to use it

  • Whole team on one imposed site: no mode to choose and nothing to set up for remote work; settle the ways of working in the project ground rules.
  • Collaboration problem unrelated to distance: unclear roles or a team in the storming stage; address it with the RACI matrix or the Tuckman ladder.

Description

Two work modes

The PMBOK Guide defines both modes in its Section 5. It lists virtual teams among the tools of the Acquire Resources process (§2.6.2.3). It lists both among those of the Lead the Team process (§2.6.2.4).

ColocationVirtual team
DefinitionThe most active members work in the same physical location for the whole project or at strategically important times.The members pursue a shared goal with little or no time spent face to face.
What it bringsBetter communication, better working relationships and higher productivity.Distant specialists, employees working from home, staggered hours, people with reduced mobility, projects that travel costs would have stopped.
SetupA team room, a wall or board to post the schedule, spaces for informal conversation.An online team space that holds the team's files, discussion threads and calendar.
What it costsOffices, travel and sometimes relocation. A loss of privacy, of quiet and perhaps of concentration (Teasley et al.).More demanding communication planning. Time to set expectations, agree how to handle conflict, involve everyone in decisions, understand cultural differences and recognise each person's contribution.
Colocation and the virtual team according to the PMBOK Guide: definition, benefits, setup and costs. The colocation cost row comes from Teasley et al. and from the comparison with the virtual team.

The PMBOK Guide notes that some adaptive methods call for colocation and that remote work may improve the efficiency and focus of some individuals and teams (§4.3.3). The sixth principle of the Agile Manifesto names face-to-face conversation as the most efficient and effective way to convey information to and within a development team.

The conditions for remote work

Gary and Judith Olson conclude from their studies that a team has a chance of succeeding remotely when it has high common ground, when its work is loosely coupled and when it is ready both for collaboration and for collaboration technology. Each departure from these conditions creates strain. The title of their article sums up their conclusion: distance matters.

ConditionWhat it meansSign in favour of remote workSign against
Coupling of workHow much the tasks depend on one another and how often the people doing them must consult each other.Work that is routine or split into parts that one person finishes alone.Ambiguous and non-routine work that needs rapid back-and-forth between people.
Common groundWhat the members know and know they share: domain, vocabulary, method, language.Members who have worked together before in a domain they know.A new team, several languages, professions that do not know each other.
Collaboration readinessThe willingness to share work and information.Sharing that the organisation's incentives reward.Collaboration imposed while the incentives reward individual work.
Collaboration technology readinessThe tools in place and the habit of using them.A team that already shares documents and boards online.Tools introduced with the project without training.
The Olson and Olson conditions for remote work. The definition of each condition comes from Olson and Olson; the signs for and against come from practice.

Coupling is the main lever that the project manager controls. Tightly coupled work is ambiguous, non-routine and highly interdependent. Olson and Olson report the case of an organisation that judged such work too difficult to do remotely. It assigned this work to people on a single site and so fitted the division of work to the geography.

Members build common ground by working together. A new team has little of it. In Switzerland, language plays a part: a team that spans Lausanne and Zurich often works in two languages or in English. For a newly formed virtual team, the PMBOK Guide suggests time to get to know each other and at least one face-to-face meeting (§2.6.3.1).

Olson and Olson observe that a mandate to collaborate fails when the organisation's incentives reward individual work. A collaboration tool does not correct this mismatch. The project manager settles it with the line managers before equipping the team.

Time zones and shared hours

Each added time zone reduces the hours that the team shares.

A team in Lausanne works from 8:00 to 17:00. Its Indian supplier works in Pune from 9:00 to 18:00 local time. The two share six and a half hours in summer. In winter they share only five and a half. Switzerland moves to winter time and India keeps the same time all year.

Lausanne
8:00 to 17:00
Pune, summer
6.5 hours shared
9:00 to 18:00 in Pune
Pune, winter
5.5 hours shared
9:00 to 18:00 in Pune
Swiss time
4:005:006:007:008:009:0010:0011:0012:0013:0014:0015:0016:0017:0018:00
The shared hours of a Lausanne team and a Pune supplier in Swiss time. The team shares six and a half hours in summer and five and a half hours in winter.

According to Olson and Olson, a team hands its work to the next time zone at the end of the day only if that work is loosely coupled and if the team first writes down where the work stands. A batch of regression tests described by written test cases tolerates the time difference. A requirements workshop does not.

Choosing the work mode

The sequence of steps for this choice comes from practice. It applies the Olson and Olson conditions and takes up the PMBOK Guide's suggestions for a newly formed virtual team (§2.6.3.1).

  1. Split the work into packages, by phase. The packages of the work breakdown structure or the epics of the backlog will do.
  2. Classify each package by its coupling. The project manager asks how many times a day the people involved must consult each other to make progress. A package is tightly coupled when its questions remain open and the team takes its decisions in discussion. A package is loosely coupled when stable specifications describe it and one person can finish each of its parts alone.
  3. Assess the common ground of the people assigned to the package. The project manager notes what they share: the domain, the vocabulary, the method, the language, the projects they have already carried out together.
  4. Check collaboration readiness and collaboration technology readiness. Do the incentives reward sharing? Are the tools already in use in the organisation? The project manager weighs their ease of use and the training they will need.
  5. Choose the work mode of each package. A tightly coupled package runs on site when its members have low common ground. It runs hybrid when their common ground is high: the coupled work keeps fixed days on site and the common ground allows remote work on the other days. A loosely coupled package runs remotely when common ground is high. When common ground is low, it also runs remotely after an on-site kick-off meeting. This meeting builds the common ground that work without daily contact requires. Hybrid and remote work also require collaboration readiness and collaboration technology readiness. If a tightly coupled package cannot bring its members together, the project manager splits it differently. A project manager who sends the whole project to the office or the whole project home applies the wrong mode to some packages.
  6. Write the working rules into the team charter. The charter sets the shared hours, the expected response time on each channel, the language of meetings and of documents, the procedure for conflicts, the way absent members take part in decisions and the recognition of contributions. According to the PMBOK Guide, a virtual team needs extra time for these points.
  7. Choose the tools. The PMBOK Guide suggests shared workspaces, a team site that holds all the project information, audio and video conferencing and messaging for ongoing contact. It bases the choice on the urgency of the information, the availability and reliability of the technology, its ease of use, the project environment and the sensitivity and confidentiality of the information. The project environment covers whether the work is face to face or remote, how many time zones and languages it spans and its cultural constraints. Olson and Olson's conditions concern the work and the people: a tool does not make them unnecessary.
  8. Plan the meetings. The time to get to know each other and at least one face-to-face meeting go into the schedule and the budget. A project manager who cuts this meeting to save travel costs deprives a new team of its first common ground. The team uses temporary colocation for the strategically important moments: the kick-off, the end of a phase, a replanning.
  9. Review the work mode at the end of each phase. Coupling changes from one phase to the next and common ground grows. Retrospectives flag a mode that no longer holds.

What the studies support

Teasley and her co-authors followed six software development teams that worked in team rooms. Their productivity doubled. Each team had six to eight people and ran a project of about four months under tight deadlines. The authors acknowledge that their study does not separate the effect of the room from that of the deadlines.

Bloom, Han and Liang ran a six-month randomised trial with 1'612 graduate employees of a Chinese technology company. The employees on the hybrid arrangement spent two days a week at home. Resignations fell by a third. Performance reviews and promotions showed no difference.

These studies show what a work mode produced under specific conditions. The project manager compares those conditions with the conditions of the package before relying on a result.

AI considerations

A meeting assistant transcribes and summarises a meeting for members who are absent or in another time zone. The summary is the starting point of the written handover that work spread over several time zones requires. A translation tool makes a message or a document readable in the other language of a bilingual team. Videoconferencing can display translated subtitles. A language model reads the package descriptions and proposes an initial classification by coupling. It drafts a "ways of working" section for the team charter from the work mode grid.

The classification of the packages stays with the project manager and the package leads. A model reads the description of a package. It knows neither who knows whom nor what the team has already done together: it cannot see common ground. A summary erases the disagreements and hesitations that a meeting left open. A translation can shift the meaning of a requirement. A bilingual member therefore reviews the translated requirements before they become the reference. A recorded meeting holds the words of colleagues and sometimes confidential information. The team agrees in advance what it records and where it stores the recordings. The team chooses these tools according to the sensitivity and confidentiality of the information.

Examples

A health insurer is rebuilding its customer portal with nine people based in Lausanne and Zurich. An external specialist works from Bern.

PackageWeeksCouplingCommon groundTools and readinessChosen mode
Scoping and requirements workshops1 to 6Tight: ambiguous requirements, daily trade-offs with the businessLow: new team, French and German speakersReady: collaboration suite in use at the insurerOn site in Lausanne: workshops and writing
Solution architecture5 to 8Tight: interdependent technical choicesHigh: the three architects have worked together beforeReadyHybrid: Tuesday and Wednesday on site in Zurich; remote on the other days
Screen development9 to 30Loose: one developer builds each ready story aloneHigh by the end of scopingReady: team board, discussion threads, videoconferencingRemote; iteration review on site every four weeks
Migration of data from the old system12 to 24Loose: mapping rules written and approvedLow: external specialist based in BernReady once remote access to the test environment is openRemote; weekly videoconference check-in; one day in Lausanne at the package kick-off
Shared rules (team charter): online from 9:00 to 16:00; reply to team messages within the day; everyone speaks their own language in meetings; documents in French.
Work mode review: end of scoping in week 6, then at each retrospective.
Work mode grid of the customer portal project. Scoping is tightly coupled and brings together a new team: it runs on site. Architecture is tightly coupled and its three architects have worked together before: it runs hybrid. Development and data migration are loosely coupled: they run remotely with planned meetings.

Data migration runs remotely despite low common ground: the kick-off day in Lausanne gives the specialist from Bern and the team their first common ground.

Visualisations

The decision map links the Olson and Olson conditions to the work mode, then each mode to its setup.

highCommon groundlow
Remote
Hybridfixed days on site
Remoteon-site kick-off meeting
On site
looseCoupling of worktight
Collaboration readiness · Collaboration technology readiness: required in the outlined cells
On site
  • Team room
  • Wall or board for the schedule
Hybrid
  • Fixed days on site for coupled work
Remote
  • Online team space: files, discussion threads, calendar
  • Videoconferencing
  • Messaging
  • At least one face-to-face meeting
  • Team charter
Decision map of the work mode. Tight coupling and low common ground point to on-site work. Tight coupling and high common ground point to hybrid work. Loose coupling points to remote work. When common ground is low, an on-site kick-off meeting comes first. Hybrid and remote work also require collaboration readiness and collaboration technology readiness. Olson and Olson set the conditions. The PMBOK Guide describes the setup of colocation and of the virtual team. The allocation of the cells comes from practice.

Cost

PhaseLevelJustification
PreparationMediumSplit the work and assess the conditions of each package with its leads: half a day to a day.
ExecutionMediumTravel and accommodation for the on-site periods; licences and tool training for remote work.
DocumentationLowA one-page grid and a section of the team charter. The team reviews them at the end of each phase.

Tooling

Colocation needs a team room reserved for the on-site period, with walls or boards to post the schedule and the task board. A spreadsheet is enough to keep the work mode grid.

A virtual team needs an online team space (SharePoint, Confluence) for files, decisions and the calendar. A collaboration suite (Microsoft 365, Google Workspace) lets several people edit one document in real time. Videoconferencing (Microsoft Teams, Zoom, Webex) hosts remote meetings and workshops. Team messaging (Teams, Slack) handles ongoing contact. A digital whiteboard (Miro, Mural) replaces the wall of the team room. Before setting a recurring meeting, the team reads the shared hours from a time zone converter.

The organisation often imposes some of these tools. The project manager uses the factors in step 7 to choose the others. The project manager records in the communication plan which channel serves which purpose.

Sources

  • Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., PMI: virtual teams among the tools of the Acquire Resources process (§2.6.2.3, Figure 2-43); colocation, virtual teams and virtual collaboration tools among the tools of the Lead the Team process (§2.6.2.4); the suggestions for a newly formed virtual team (§2.6.3.1); colocation called for by some adaptive methods (§4.3.3); the definitions of colocation, virtual teams and virtual collaboration tools, the factors for choosing a communication technology (Section 5).
  • Gary M. Olson and Judith S. Olson, "Distance Matters", Human-Computer Interaction, 15(2-3), 2000, pp. 139-178: the conditions for remote work (common ground, coupling of work, collaboration readiness, collaboration technology readiness), work reorganised to fit the geography, time zones.
  • Stephanie Teasley, Lisa Covi, M. S. Krishnan and Judith S. Olson, "How Does Radical Collocation Help a Team Succeed?", Proceedings of CSCW 2000, ACM, pp. 339-346: the doubled productivity of six teams in team rooms, the effect confounded with that of tight deadlines, the loss of privacy and quiet.
  • Nicholas Bloom, Ruobing Han and James Liang, "Hybrid working from home improves retention without damaging performance", Nature, 630, 2024, pp. 920-925: the randomised trial on hybrid work, the fall in resignations by a third, the absence of effect on performance reviews and promotions.
  • "Principles behind the Agile Manifesto", 2001: face-to-face conversation in the sixth principle.