Value breakdown structure of a health insurer's reimbursement portal. The root is worth CHF 5'980'000 over five years. Three mandatory deliverables each carry 100% of that value. Automatic invoice reading is optional and worth CHF 520'000. Under invoice submission, PDF upload is mandatory and the photo from a mobile phone is optional and worth CHF 260'000. Two elements on the critical path carry their drag cost. A dotted link runs from the upload to its work packages in the WBS.

Value breakdown structure

The value breakdown structure (VBS) is a tree of a project's deliverables in which each element carries an estimate of the value it adds. It takes the shape of the work breakdown structure (WBS). A mandatory element carries the whole value of the project, since removing it wipes that value out. An optional element carries the difference in value between the project with it and the project without it. The team uses it to separate mandatory from optional scope, to prioritise the deliverables and to put a figure on a week of delay on the critical path. Stephen Devaux published the method in 1999; the PMBOK Guide took it up in its 8th edition.

Goal

The PMBOK Guide defines the value breakdown structure as a hierarchical structure that links the project scope and its expected value to the product scope that generates that value (§2.2.1). Its Section 5 describes it as a WBS in which each element carries an estimate of value.

A WBS states what the project produces and what each part costs. It does not state what each part earns. Without that figure the team knows neither which deliverable to sacrifice when the budget runs short nor what a week saved is worth. This observation was the starting point of Stephen Devaux's method. For him a project is an investment. Traditional project management tracks the sum invested and leaves aside the value that this sum is meant to produce.

With the value breakdown structure, the sponsor and the team decide which elements are mandatory, which optional elements are worth their cost and what accelerating an element on the critical path earns. The technique produces a tree of deliverables in which each node carries a status (mandatory or optional) and an added value. According to the PMBOK Guide, the team decomposes each leaf of this tree through the WBS. The guide prescribes no form for this link. A traceability matrix documents it: it ties each leaf to the work packages that produce it.

Usage

When to use it

  • Benefits already quantified: the business case gives a value in francs or in measurable units that can be carried down to the deliverables.
  • A budget or deadline that forces cuts: sort the scope on the value of each element.
  • Value that depends on the date: put a figure on a week of delay when the project targets a seasonal launch, a regulatory deadline or savings that start at go-live.
  • A trade-off on the critical path: decide whether to pay to accelerate a critical activity or to remove it from scope.
  • A project that a programme depends on: each week of delay on this project delays the value of the whole programme.
  • A fixed-price supplier on the critical path: calculate the early-completion bonus to write into the contract.

When not to use it

  • No quantified value from the sponsor: values that the team estimates alone produce false precision; prioritise with MoSCoW (see prioritisation).
  • Scope entirely imposed: nothing to trade off; put a figure on time with critical path drag.
  • Adaptive approach without a WBS: the product backlog ordered by value plays this role at each iteration.

Description

The elements

The node is a deliverable or a sub-deliverable. It is named as an outcome ("Online invoice submission") rather than as an activity ("Develop the submission module"). The top level gathers the major deliverables that the stakeholders have discussed and agreed together (PMBOK Guide, §2.2.1).

The added value estimates what the element brings to the project. The PMBOK Guide allows two forms: a number in the project's unit of value or a percentage of its total expected value. A company counts in revenue or savings. The guide also cites children who learn to read and lives saved.

The status classifies the element. A mandatory element is one without which the project loses its purpose and its value. Devaux puts an element that the law or an internal rule imposes in the same class. Its added value equals that of the whole project, which the PMBOK Guide writes as 100%. An optional element adds value without being indispensable. Its value is the difference between what the project is worth with it and what it is worth without it.

Devaux shows this on a house. Without a bathroom the house gets no occupancy permit and is worth nothing: the first bathroom is mandatory and carries the house's 200'000 dollars (100%). The second bathroom is worth 40'000 dollars: the difference in sale price between a house with one bathroom and a house with two.

Devaux starts from the MoSCoW method. Must becomes mandatory. Should and Could become optional and receive a quantified value. Won't stays out of scope.

Value does not add up

In a WBS the cost of a parent equals the sum of its children's costs. Value does not follow this rule. The two wings of a small aircraft that sells for 100'000 dollars are both mandatory and each is worth 100'000 dollars. The pair of wings is still not worth 200'000 dollars. Two elements can also overlap: the value of the two together then stays below the sum of the two. They can instead reinforce each other and exceed it.

A health insurer builds an online reimbursement portal. The portal's business case puts the savings at CHF 23'000 per week of operation: CHF 5'980'000 over five years.

Cost and added value in the Invoice submission branch of the example portal. Amounts in CHF. Illustrative values.
ElementStatusCostAdded value
2 Invoice submissionMandatory300'0005'980'000 (100%)
2.1 PDF invoice uploadMandatory220'0005'980'000 (100%)
2.2 Photo from a mobile phoneOptional80'000260'000 (4%)

The children's costs make up the parent's CHF 300'000. Their values total CHF 6'240'000 and exceed the parent's value. A value total calculated by rolling up the tree is therefore wrong. The team estimates the value of the parent itself with the sponsor.

Building the structure

  1. Gather the major deliverables. The stakeholders discuss them and agree them together. They form the top level (PMBOK Guide, §2.2.1). They come from the business case, the project charter or the scope statement.
  2. Classify each deliverable with the sponsor. Section 5 of the PMBOK Guide gives the test: an element is mandatory if removing it wipes out the project's value.
  3. Estimate the added value. A mandatory element receives 100%. An optional element receives the difference in value with and without it. The sponsor, the customer or the investor supplies these figures. The analyst attaches them to the deliverables.
  4. Decompose. The team divides each deliverable into sub-deliverables and gives them a status and a value under the same rules. Decomposition stops when each optional element forms a separate decision. In the kitchen of his house, Devaux separates a mandatory sink from an optional dishwasher.
  5. Link to the work packages. Each leaf decomposes through the WBS into work packages and activities (PMBOK Guide, §2.2.1). Functional decomposition describes this WBS and its rules.
  6. Weigh value against cost. An optional element stays in scope if its value exceeds its cost. The team judges the mandatory scope as a block. The total expected value already counts all the options. If the cost of the mandatory scope exceeds it, no choice of options makes the project pay.
  7. Price the critical path. For each element on the critical path, estimate its drag cost and compare it with the cost of accelerating or removing the element.
  8. Revise. Rework the values when the business case changes or when the go-live date slips.

Drag cost on the critical path

A project's value often depends on its date. Devaux takes the example of a remote-controlled snow blower. If it is in the shops three days before the first storm of the winter, it is expected to earn 25 million dollars. Each week of delay takes 10% off those sales.

Section 5 of the PMBOK Guide defines two terms that put a figure on this sensitivity. Critical path drag is the time that a critical activity adds to the project's duration. It is read from the network of the critical path method. Drag cost is the drop in the project's expected return that this drag causes. The team estimates this cost for each element on the critical path from the added values in the structure (§2.2.1).

For an element on the critical path, Section 5 suggests checking whether another plan earns more: accelerating or removing the element can earn more than the acceleration or the removal costs.

Two trade-offs on the critical path of the example portal. Assumption: the project is worth CHF 23'000 per week of operation. Automatic invoice reading contributes 2'000 of that (520'000 over 260 weeks); without it a week is worth 21'000. Each week of delay loses one week of operation. Each row reads on its own. Amounts in CHF. Illustrative values.
Critical elementDragDrag costOption studiedWhat the option costsWhat the option earnsDecision
3 Interface with the claims management system (mandatory)3 weeks69'000Add an integration specialist. The specialist saves 2 weeks; the 3-week drag caps the gain.30'000 in resources46'000 (2 × 23'000)Accelerate
4 Automatic invoice reading (optional)4 weeks92'000Remove the element520'000 in lost value84'000 (4 × 21'000) plus 180'000 in avoided cost: 264'000Keep

Drag cost alone decides nothing. Removing automatic reading brings go-live forward by four weeks but loses more value than it gains.

A project on which a whole programme depends carries that programme's value. In one of Devaux's examples, a bridge gives the only access to the building site of a hotel complex expected to earn 3.5 million dollars a week. Each week saved on the bridge is worth that amount. If a contractor builds the bridge at a fixed price, Devaux recommends writing a substantial bonus for each week of early completion into the contract.

Pitfalls

Adding up the values. The sum of the nodes soon exceeds the project's value and can reach several times that value. A spreadsheet that rolls values up like costs produces a total that nobody should read. The check: no sum formula in the value column.

Letting the team invent the values. Devaux observes that the expected value almost never reaches the project manager and the team, even when management or the sponsor has quantified it. A team that fills this gap builds the tree on its own assumptions. The figures come from the sponsor, the customer or the investor. A value that does not come from them carries its author's name and the label "assumption".

Declaring everything mandatory. Each stakeholder defends their own deliverable. A tree with no optional element adds nothing to the WBS. The Section 5 test settles it: if the project keeps its value without the element, the element is optional.

Confusing value with cost. A team that takes an element's cost as its value can no longer tell the options apart: each one is worth exactly what it costs. Value is measured from the point of view of the user or the sponsor: revenue, savings, risk avoided.

Stopping above the WBS. A structure that does not reach the work packages does not steer the work. A work package that no valued leaf justifies adds cost without adding value. The traceability matrix exposes this gold plating.

AI considerations

A language model drafts a first tree from a WBS, a charter or a business case. It rewrites activities as deliverables. It compares the structure with the WBS to list the work packages that have no valued leaf. It finds the spreadsheet formulas that add up values. It writes the formulas that recalculate the drag costs and the trade-offs; the spreadsheet does the calculation. For each optional element it prepares the questions to put to the sponsor.

The values remain the sponsor's business. A model produces plausible figures that nobody has taken responsibility for supplying. Mandatory status belongs to the same decision. The business case figures are confidential. At a health insurer the claims data concern health: the revised Federal Act on Data Protection (nFADP) classes them as sensitive personal data (Art. 5 let. c). These figures and data go to a hosted service only within the framework that the organisation has set.

Examples

In the health insurer's portal, the policyholder submits medical invoices online.

Three mandatory elements each carry CHF 5'980'000. Automatic invoice reading carries only its increment. Adding up the first-level nodes would give CHF 18'460'000 for a CHF 5'980'000 project.

Visualisations

The traceability matrix ties each leaf of the structure to the work packages in the WBS. The last row shows a package that no leaf justifies.

Traceability matrix between the leaves of the value breakdown structure and the work packages of the WBS in the example portal. Illustrative values.
LeafStatusAdded valueWBS work packages
1 Policyholder authenticationMandatory100%1.1 Connection to the identity provider; 1.2 Security tests
2.1 PDF invoice uploadMandatory100%2.1.1 Submission form; 2.1.2 Document archiving
2.2 Photo from a mobile phoneOptionalCHF 260'0002.2.1 Capture and cropping
3 Interface with the claims management systemMandatory100%3.1 Interface specification; 3.2 Development; 3.3 Integration tests
4 Automatic invoice readingOptionalCHF 520'0004.1 Recognition set-up; 4.2 Reading quality control
NoneNo statusNone5.1 Separate visual theme for each canton

Cost

PhaseLevelJustification
PreparationMediumObtain a quantified business case from the sponsor and have a first-level WBS.
ExecutionMediumOne or two workshops with the sponsor to classify the deliverables and estimate their value; a schedule network for the drag costs.
DocumentationLowThe tree and the traceability matrix. The team reviews them when the business case or the go-live date changes.

Tooling

A spreadsheet is enough for most projects. Each row holds one element with its code, its parent, its status, its added value, its cost and the codes of its work packages. A check column flags any formula that adds up values.

Scheduling software such as MS Project or Primavera P6 holds the value in a custom task field. It calculates the network and the float. It does not calculate drag. The team derives drag by hand from the network (see critical path drag). A diagramming or mind-mapping tool draws the tree for the workshop with the sponsor.

Sources

Stephen Devaux designed the value breakdown structure and remains its only detailed source. The PMBOK Guide covers it in two paragraphs.