Two-axis grid. On the horizontal axis, cooperativeness rises from low on the left to high on the right. On the vertical axis, assertiveness rises from low at the bottom to high at the top. Under each mode sits the closest PMBOK Guide technique. Competing sits top left with force/direct. Collaborating sits top right with collaborate/problem-solve. Compromising occupies the centre with compromise/reconcile. Avoiding sits bottom left with withdraw/avoid. Accommodating sits bottom right with smooth/accommodate.

Thomas-Kilmann Conflict Modes

The Thomas-Kilmann model describes how a person behaves in a conflict along two independent dimensions. Assertiveness is the degree to which they try to satisfy their own concerns. Cooperativeness is the degree to which they try to satisfy the other person's concerns. Combined, the two give the modes of competing, collaborating, compromising, avoiding and accommodating. Each mode has its place. The model works at two levels. A party chooses its own behaviour. The project manager who steps in as a third party steers the parties towards a mode or imposes one. The factors that the PMBOK Guide lists guide this choice.

Goal

The Thomas-Kilmann modes are ways of responding to a conflict. The technique answers one question: which mode should one adopt in this conflict? It gives a vocabulary to name what each person does, a grid to place the mode and factors to choose it. The PMBOK Guide files conflict management among the interpersonal skills of the Lead the Team process. This process influences team behaviour, manages conflict and resolves issues among team members.

The deliverable is a written decision: the chosen mode, its reason in light of the factors, the agreed course of action and the threshold that triggers escalation. The team records it in the issue log, which the PMBOK Guide counts among the inputs and outputs of Lead the Team. At team level, the conflict resolution procedure in the team charter is a second deliverable.

Usage

When to use it

  • A scarce resource in dispute: two members want the same environment, the same expert or the same week; name their concerns before deciding.
  • Incompatible scheduling priorities: place each party's demand on the grid and choose the mode on the basis of the factors.
  • A conflict that reaches the project manager: the members found no way out; the project manager steps in with a mode chosen on the basis of the factors.
  • Drafting the team charter: write the conflict resolution procedure and the level at which the project manager steps in.
  • A member who gives way at every disagreement: the project manager asks them for their concern in private.
  • A disagreement that flares up in a distributed team's chat thread: take it out of the thread and deal with it in a private call.
  • A complex and novel decision: set aside the time for collaborating.
  • A team review or retrospective: measure the styles with the TKI instrument and spot the mode that the team overuses.

When not to use it

  • Harassment, discrimination or misconduct: no mode applies; refer the matter to the designated confidential contact for harassment, the organisation's formal procedure or human resources.
  • A disagreement over a verifiable fact: establish the fact by a measurement or by document analysis.

Description

Conflict and concerns

Thomas defines conflict as the condition in which people's concerns appear to be incompatible. A concern is anything that matters to someone: a deadline, a resource, a quality requirement, recognition. The word "appear" matters. Two concerns that seem to exclude each other can sometimes be reconciled once they are stated. Collaborating rests on this gap.

The PMBOK Guide holds conflict to be inevitable in a project. It names the usual sources: scarce resources, scheduling priorities and personal work styles. The team's ground rules, group norms, communication planning and role definition reduce the number of conflicts. A RACI matrix writes down the roles. A communication plan sets who receives which information.

The two dimensions

Thomas holds the two dimensions to be independent. A person can aim high on both, low on both or high on one only. The grid carries cooperativeness on the horizontal axis and assertiveness on the vertical axis. Each mode occupies a position on it.

According to Kilmann and Thomas (1977), the five-mode classification comes from Blake and Mouton (1964). Thomas reinterpreted it in 1976 on these two dimensions.

HighAssertivenessLow
CompetingForce/direct
CollaboratingCollaborate/problem-solve
CompromisingCompromise/reconcile
AvoidingWithdraw/avoid
AccommodatingSmooth/accommodate
LowCooperativenessHigh
Each mode occupies a position on the two dimensions. Under each mode is the closest PMBOK Guide technique.

The modes

Competing

Competing combines high assertiveness with low cooperativeness. The person pursues their own concerns at the other's expense. The closest PMBOK Guide technique is "force/direct". The project manager who stops a production incident decides first and explains afterwards.

Collaborating

Collaborating combines high assertiveness with high cooperativeness. The parties solve the problem together until they reach a solution that fully satisfies the concerns of each. The closest PMI technique is "collaborate/problem-solve".

Compromising

Compromising sits halfway up both dimensions. The parties look for an acceptable settlement that partly satisfies each of them. The closest PMI technique is "compromise/reconcile".

Avoiding

Avoiding combines low assertiveness with low cooperativeness. The person sidesteps the conflict or postpones it. For the moment, they satisfy nobody's concerns. The closest PMI technique is "withdraw/avoid".

Accommodating

Accommodating combines low assertiveness with high cooperativeness. The person sacrifices their own concerns to those of the other. The closest PMI technique is "smooth/accommodate".

The PMBOK Guide techniques and the modes

The two sources describe two actors. Thomas describes the behaviour of a party facing its own concerns and those of the other. The PMBOK Guide describes the technique of the project manager who resolves a conflict between other people. So a party chooses its mode. The project manager steps in as a third party: they steer the parties towards a mode or impose one. This change of actor explains the position of power attached to force/direct.

The PMBOK Guide's conflict resolution techniques overlap closely with the modes. This mapping is our own reading. The technique names are PMI's own terms.

Thomas-Kilmann modePMBOK Guide techniqueWhat differs
CompetingForce/directThe PMBOK Guide adds the position of power and urgency. Thomas defines the mode by the two dimensions alone.
CollaboratingCollaborate/problem-solveThe PMBOK Guide describes combining viewpoints and reaching consensus. Thomas aims at the full satisfaction of both parties.
CompromisingCompromise/reconcileThe PMBOK Guide calls the solution temporary or partial and allows for a lose-lose result. Thomas places the mode in the middle of both dimensions.
AvoidingWithdraw/avoidThe PMBOK Guide adds the reasons for postponing: to prepare better or to let others settle the question.
AccommodatingSmooth/accommodateThe PMBOK Guide adds the emphasis on points of agreement.
Mapping between the Thomas-Kilmann modes and the conflict resolution techniques of the PMBOK Guide.

The labels win-win, win-lose and lose-lose belong to the PMBOK Guide. Thomas defines the modes by the satisfaction of concerns. A definition that mixes the two vocabularies attributes to one source what the other says.

Concerns and positions

A position is the solution that a party demands: "the test environment frozen for two weeks". A concern is what the position protects: "the business testers are only available in those two weeks". Thomas derives a condition for collaborating from this. As long as the parties discuss positions, one wins, one gives way or both split the difference: competing, accommodating or compromising. Collaborating starts from the concerns and looks for a solution that satisfies them all.

Thomas borrows "firm flexibility" from the researcher Dean G. Pruitt. The party stays firm on its concern and flexible on its position. You will find the same distinction between positions and interests in negotiation.

HighAssertivenessLow
Competing
Collaborating
Compromising
Avoiding
Accommodating
Discussion of positions
Discussion of concerns
LowCooperativenessHigh
When the parties discuss positions, one wins, one gives way or both split the difference. They stay on the diagonal that links competing to accommodating. Collaborating requires a discussion of concerns.

The procedure

The order of the steps combines the guidance of the PMBOK Guide and of Thomas.

1. Name the concerns

For each party, the project manager writes down its position and then the concern that the position protects. They ask "what does this solution guarantee you?" until they obtain a concern that the other party can satisfy another way. Each concern fits in one sentence.

2. Assess the situation

The PMBOK Guide lists the factors that guide the choice of method:

  • the importance and intensity of the conflict;
  • the time pressure to resolve it;
  • the relative power of the people involved;
  • the importance of keeping a good relationship;
  • the motivation to resolve the conflict in the long term or in the short term.

The project manager notes each factor in one word or a date. The written note keeps the mode from following the mood of the moment.

3. Choose the mode

The factors noted at step 2 point to a region of the grid. The choice holds when the cost of the mode remains acceptable against the same factors.

ModeSituation that calls for itWhat it costsHow to reduce the cost
CompetingAn emergency to resolve in the short term. One person holds the power to decide.The relationship wears down.The project manager who imposes a decision gives the reason and how long the decision lasts.
CollaboratingAn important, complex and novel issue that leaves time. Long horizon: the PMBOK Guide links collaborating to consensus and commitment. According to Thomas, it yields better decisions on such issues.Hours of meetings.The project manager keeps it for the issues that matter.
CompromisingA partial solution is enough to move forward. There is no time to collaborate. Short horizon: the PMBOK Guide describes a temporary or partial settlement.Each party obtains part of its concern. The conflict can return.The parties name their concerns at step 1 before they split the difference.
AvoidingA minor issue. A dangerous issue (a personality conflict). A postponement that gives the missing information time to arrive.The problem stays open.The party that postpones a question sets the date when the question comes back.
AccommodatingThe point matters little to the party. The relationship matters a lot.The party gives up its concern.The party that gives way says so to make the concession visible to the other party.
The situation that calls for each mode, its cost and how to reduce that cost.

4. Act early and in private

According to the PMBOK Guide, the project manager addresses the conflict early and usually in private. They approach it directly and in a collaborative spirit. A conflict discussed in front of the team forces each party to defend its position. The party loses the room that let it drop its position and keep its concern.

5. Lead a collaborating session

The project manager first has the parties state their concerns. They then collect the options. They select an option that satisfies each concern and check with each party that the option works for it.

6. Reduce the cost of the mode

According to Thomas, the way a mode is used reduces its cost. One can compete without antagonising, avoid without being evasive and accommodate without looking weak.

7. Escalate the conflict if it persists

The PMBOK Guide describes levels. Team members first resolve their differences themselves. If the conflict escalates, the project manager steps in to reach a satisfactory resolution. If the conflict keeps disrupting the work, the organisation applies its formal procedures. These can extend to disciplinary action.

The decision at step 3 sets the threshold for the next level: a date, a number of meetings or an observable fact.

8. Measure the style (optional)

A team that wants to know its habits takes the TKI instrument. The profile opens the discussion at step 3.

Style and the TKI instrument

Thomas defines style as a person's tendency to rely on some modes more than on others. A team also has its style. According to Kilmann Diagnostics, everyone can use all five modes and no one can be reduced to a single style. Behaviour arises from personal predisposition and from the demands of the situation.

The Thomas-Kilmann Conflict Mode Instrument (TKI) measures this style. It presents 30 pairs of statements. For each pair, the person chooses the statement that describes them best. Kilmann and Thomas adopted this forced choice to reduce social desirability bias. This bias pushes respondents towards the answer that shows them in a favourable light. The earlier instruments by Blake and Mouton, by Lawrence and Lorsch and by Hall were exposed to it. The 1977 paper judges the evidence of validity encouraging and calls for further research.

The score for each mode is read against percentile norms. A high score places the person in the top quarter of respondents. A medium score places them in the middle half. A low score places them in the bottom quarter. According to Kilmann Diagnostics, the 2007 norms rest on a sample of 8'000 people. A high score signals a mode that the person relies on readily. A low score signals a mode that they use little. Sometimes they avoid it when it would have helped them.

The statements and the scoring key belong to the publisher. A home-made questionnaire that imitates them lacks the norms.

Pitfalls

The mode out of habit

A person applies their habitual mode to every conflict without going through the factors. The TKI profile makes this habit visible. The written note from step 2 corrects it.

Collaborating on everything

According to Thomas, the party that collaborates too much over-analyses and seeks consensus when consensus does not come or time is short. A team that collaborates on the choice of a minutes template spends hours that it owes to the complex issues.

Avoiding that drags on

According to Thomas, the party that avoids too much misses meetings and withholds information. An issue postponed without a date comes back bigger. Each postponement carries a return date.

Competing without urgency

According to Thomas, the party that relies too much on competing monopolises the discussion, does not listen and blocks. Outside an emergency and a position of power, the imposed decision produces a victory that the other party then contests.

Compromising too early

Parties who discuss positions split the difference before they have stated their concerns. The compromise gives them half of each position. It sometimes misses the solution that would have satisfied every concern.

The profile read as a label

"Nadia is an accommodator" turns a score into a character trait. The TKI measures reliance on modes. Nadia uses all five and chooses accommodating more often than average.

AI considerations

A language model rephrases a position as possible concerns. The analyst gives it each party's demand without names or identifiable context and asks it what the demand protects. The party concerned confirms its own concern during the interview. The model also generates options that satisfy two given concerns. These options feed step 5.

The model fills in the decision table from a description of the conflict and proposes a mode. Its proposal remains a hypothesis. It knows nothing of the actual power of the people, the history of their relationship or what they leave unsaid. The mode remains the choice of the project manager or of the party concerned.

Notes from an interview about a conflict are personal data within the meaning of the Federal Act on Data Protection (FADP). They stay out of online services whose terms of use the organisation does not control. A model that reads the team's messages to detect conflicts or to classify each person's style monitors the employees. Article 26 of Ordinance 3 to the Employment Act (OLT 3) prohibits systems intended to monitor the behaviour of workers at their workplace. A style questionnaire generated by a model has neither the validated statements nor the norms of the TKI.

Examples

The team that is replacing a cantonal office's permit software handles three conflicts in the week of 23 February. The project manager fills in one decision table per conflict. The same project uses three modes depending on the factors. Names and dates are illustrative.

 Test environmentFormat of the test case IDsIncident on the legacy system
PartiesNadia (test lead) and Luca (development lead)Nadia and LucaThe supplier and the project manager
First party's positionFreeze the user acceptance testing (UAT) environment from 2 to 13 MarchPrefix the IDs with the business processAnalyse the cause before any intervention
Second party's positionDeploy the performance fix on 5 MarchPrefix the IDs with the requirement numberRestart the service immediately
First party's concernThe office's six testers are only available in these two weeks and test on a stable version with stable dataKeep the naming convention of the previous test campaignKeep the traces that explain the outage
Second party's concernMeasure the fix on a realistic volume before go-live on 30 MarchThe traceability tool links the cases to the requirements by this numberGive the online service back to its users
Importance and intensityHighLowHigh
Time pressureAcceptance testing from 2 to 13 March. Go-live on 30 MarchTest case writing from Thursday 26 FebruaryOnline service down for 40 minutes
Relative powerEqualEqualThe project manager decides
RelationshipBoth work together on the next phaseBoth work together on the next phaseFour-year maintenance contract
HorizonLong termShort termShort term
Chosen modeCollaboratingAccommodating: Nadia gives wayCompeting: the project manager imposes
Agreed course of actionDeployment on Thursday 5 March at 18:00. Measurement overnight. Fix removed and data restored before 07:00Prefix by requirement number. Nadia gives up the old conventionImmediate restart. The analysis starts from the logs available
Cost reductionA 90-minute meeting on Wednesday 25 FebruaryNadia announces her concession to the teamThe project manager explains her decision to the supplier on the same day
Escalation thresholdVersion or data not restored by 07:00: the project manager arbitratesNoneNew outage within the week: steering committee
Decision table for three conflicts in the week of 23 February. The factors lead to collaborating for the test environment, to accommodating for the ID format and to competing for the incident on the legacy system.

Avoiding was ruled out for the ID format because the team was writing the test cases from 26 February.

Visualisations

On the grid, the three decisions of the week occupy three corners. The positions of compromising and avoiding stay empty.

HighAssertivenessLow
CompetingIncident on the legacy systemProject manager
CollaboratingTest environmentNadia and Luca
Compromising
Avoiding
AccommodatingID formatNadia
LowCooperativenessHigh
The same project uses collaborating for the test environment, accommodating for the ID format and competing for the incident on the legacy system.

Cost

PhaseLevelJustification
PreparationLowOne interview with each party to name its position and its concern. One note per factor.
ExecutionMediumA few minutes for an imposed decision, one or more meetings for a collaboration.
DocumentationLowOne entry in the issue log. The TKI adds one report per person.

Tooling

A whiteboard or a sheet of paper is enough to write positions and concerns side by side and to place the mode on the grid.

The issue log holds the decision and the escalation threshold. A spreadsheet is enough. Jira or Azure DevOps carry it when the team already tracks its work there.

The team charter records the conflict resolution procedure, which the PMBOK Guide counts among its headings. A page in the team's wiki (Confluence, SharePoint) keeps it within everyone's reach.

The TKI instrument is taken online. Kilmann Diagnostics distributes it with the profile report and sells it per respondent. For a distributed team, a private video call replaces the one-to-one meeting.