Technical Performance Analysis
Technical performance analysis compares the value that a technical parameter of the product has reached with the value planned for the same date. The parameter is a measurable quantity: a weight, a response time, a number of delivered defects, a storage capacity. The PMBOK Guide lists the technique among the tools for monitoring risks. According to the guide, a variance can signal the impact of a threat or an opportunity. Systems engineering calls these parameters technical performance measures (TPM). It supplies the method: a planned profile, a tolerance band and a threshold.
Goal
Technical performance analysis projects the value of a technical parameter over the duration of the project, records its actual value at each milestone and compares the two to inform a decision.
The technique answers a question about the product itself: will it reach its technical target? A variance outside the planned limits shows a technical problem while there is still time to correct it. The Defense Acquisition University (DAU) of the US Department of Defense calls this function an early warning. The customer and the team base a decision on it: continue, correct the design, request a change or accept the risk.
The technical plan lists the parameters to track. For each parameter the technical team sets a planned profile with its tolerance band and its threshold. At each milestone the team delivers a chart and a commentary. The PMBOK Guide counts technical performance measures among the work performance data. The Monitor Risks process takes them as an input and produces work performance information as an output. This process tracks the identified risks, detects new ones and evaluates the effectiveness of the responses. The analysis also feeds the other outputs of the Monitor Risks process: change requests and updates to the risk register and the risk report.
Usage
When to use it
- A quantified and uncertain technical requirement: track a weight, a response time or a capacity that the design may miss.
- A parameter measurable only on the integrated product: track from the start the component parameters that determine it.
- A quantified acceptance criterion in a contract: know several milestones before acceptance whether the supplier will meet the threshold.
- A project on budget and on schedule: check that the product is also moving towards its technical target.
- A technical margin shared between subsystems: track the consumption of a mass, power or memory margin.
- A technical review or a phase review: present the status of the critical parameters and their current estimate.
When not to use it
- A result with no quantifiable technical parameter: track a process or an organisation with metrics and KPIs.
- A parameter that cannot be projected over time: verify it as an acceptance criterion through test and inspection planning.
Description
The elements
The definition of a TPM comes from NASA. The goal comes from the DAU's model chart. The other terms follow the DAU glossary.
- Technical performance measure (TPM): a physical or functional characteristic of the product that the project judges critical to a requirement.
- Planned value: the value expected for the parameter at a given date, in the parameter's unit. Earned value management uses the term planned value (PV) for an amount in francs.
- Planned profile: the series of planned values for each milestone.
- Tolerance band: the alert limits around the profile. The DAU bases them on the expected estimating error. An early estimate carries more error than a final measurement: the band narrows towards the end.
- Threshold: the limit value that is acceptable. The contract often sets it. The PMBOK Guide uses the word threshold for the value that triggers an action. The edge of the band plays that role.
- Goal: the value that the team aims for at completion. It lies on the right side of the threshold.
- Achieved to date: the value measured or estimated at the milestone.
- Variance: the planned value minus the value achieved to date. The sign reads one way when a lower value is better and the opposite way when a higher value is better. For a response time, a negative variance is unfavourable.
- Current estimate: the value expected for the parameter at completion.
From the need to the parameter
The team derives each parameter from the need in successive levels: MOE, MOP, TPM. The measure of effectiveness (MOE) states what the user must be able to do in operation. It may stay qualitative. The measure of performance (MOP) translates the MOE into a quantified characteristic of the system. Several MOPs often serve one MOE. The DAU and NASA draw the TPMs from the MOPs.
The DAU explains why a team tracks a component parameter rather than the MOP itself. The speed of a system is measurable only once the product is integrated, except by analysis or simulation. Its weight can be estimated at every level of the work breakdown structure (WBS) and tracked throughout development. Weight therefore gives early warning about speed. In a web portal, the load test of the integrated system measures the end-to-end response time. The duration of a call to a third-party service and the page weight are measurable from the first components onwards.
The business analyst formulates the MOE with the stakeholders. The analyst then writes the MOP as a measurable requirement through non-functional requirements analysis. The technical team derives the TPMs and estimates their profile.
Verified in operation
Measured at each milestone
Choosing the parameters
A project tracks few parameters. The DAU sets the selection criteria:
- Tied to a risk: the parameter covers an area of the design identified as risky.
- Traceable: it traces back to a user need.
- Predictable: its course over time can be forecast well enough to draw a profile.
- Measurable: an analysis, a test or a demonstration gives its value during the project.
- Well placed: it concerns a WBS element that carries much of the cost, lies on the critical path or concentrates the risk.
The team starts from the work breakdown structure. For each element it looks for the parameters that determine a MOP. The supplier usually tracks more parameters than it reports to the customer, because it works at a finer level of detail.
The sequence of the analysis
The steps combine the guidance of the PMBOK Guide, the DAU and NASA. Steps 1 to 3 happen once at the start of the project. Steps 4 to 7 repeat at each milestone.
- Derive the parameters from the need, from MOE to MOP and then to TPM.
- Select a few parameters that meet the selection criteria.
- Plan each parameter: measurement method, profile, tolerance band, threshold, goal and milestones.
- Measure or estimate the parameter at each milestone.
- Calculate the variance and compare it with the band and the threshold.
- Decide and report with a chart and a commentary.
- Carry the result into risk monitoring.
Plan the parameter
The team plans the parameters as early as the functional specification of the system. The technical plan sets for each parameter the estimating method, a dated profile, a tolerance band and a threshold. It also names the reviews and tests that meeting the profile depends on.
The profile follows the expected maturity of the design. A response time falls as the team optimises the code and the infrastructure. NASA also treats margins as tracked parameters. A mass, power or memory margin covers uncertainties. The project consumes it over the life cycle. NASA requires every hardware project to track its mass margin. It requires every project whose product draws power to track its power margin.
The band reflects the expected estimating error. It depends on the measurement method and on the share of the design that can still change. An estimate on a mock-up justifies a wide band. A load test on the final environment justifies a narrow band. The project decides for each parameter whether it uses a band. The threshold comes from the requirement or the contract. The goal keeps a margin from the threshold. The measurement milestones follow the reviews, tests and increment deliveries already planned.
Measure at each milestone
The team compares the achieved value with the value planned for the date. Without a test result it takes the best estimate available. The method changes during the project: calculation, then simulation, then test. The team records the method with each value so that the reader of the report knows how much weight the value carries.
Calculate the variance and check where it falls
The team compares the variance with the tolerance band, the threshold and the goal, then projects the trend to completion. The projection extends the slope of the latest measurements taken by the same method. The report names the points it uses and its assumption. This projection gives the current estimate, which the team compares with the threshold. A value outside the band calls for an evaluation.
| Situation | Interpretation | Decision |
|---|---|---|
| Value inside the band | The design is progressing as planned | Continue. Watch the slope of the latest milestones. |
| Value outside the band on the unfavourable side | Threat to the requirement | Find the cause and correct the design. Update the risk register. |
| Value outside the band on the favourable side | Opportunity or measurement error | Check the measurement. Reallocate the margin or revise the profile through a change request. |
| Current estimate beyond the threshold | The requirement will not be met without action | The customer chooses among a correction, a change to the requirement and acceptance of the risk. |
Decide and report
The DAU describes the report as a chart with a commentary. The chart shows the planned profile and the observed values. The commentary explains the causes of the variance, assesses its seriousness, describes the actions under way and projects future performance.
Feed risk monitoring
A variance outside the band enters the risk register as a new risk or raises the probability of an existing risk. A correction that affects the design, the scope or the contract goes through a change request. The risk report presents the status of the critical parameters to the steering committee. The risk owner then chooses the response through risk analysis and management.
Related techniques
The Monitor Risks process in the PMBOK Guide also uses reserve analysis.
| Technique | Question | Unit | Basis of comparison |
|---|---|---|---|
| Technical performance analysis | Will the product reach its technical target? | The unit of the parameter: s, kg, GB | The planned profile of the parameter |
| Earned value management | Is the work costing and progressing as planned? | CHF, days | The cost baseline and the schedule baseline |
| Reserve analysis | Does the reserve cover the remaining risk? | CHF, days | The contingency reserve and the management reserve |
According to the DAU, earned value combined with product measures helps to detect and understand development problems. The PMBOK Guide makes the same link for the to-complete performance index (TCPI). The project manager judges whether the index is achievable in light of the risk, the time remaining and the technical performance. The guide's variance analysis examines cost, schedule, resource and technical performance variances together.
Metrics and KPIs track the performance of a solution in operation. A TPM is a leading indicator: it concerns the product under development.
Pitfalls
Too many parameters
A committee cannot read a table of thirty parameters. The minor variances hide the one that matters. The number of parameters depends on the means of measurement and on the people available to track them. The team keeps the parameters tied to a risk and leaves the others to the internal tracking of the technical team.
The flat profile
A profile set at the goal from the first milestone ignores the maturity of the design. Every early measurement then falls outside the band. The team grows used to the alert and stops reading it.
The profile redrawn after each measurement
A team that resets the profile to the latest measurement has no variance left. The profile is part of the plan. The team changes it only through a change request that states the reason.
The ignored trend
A value that stays near the edge of the band for two milestones in a row signals that it is about to leave the band. The team reads the slope of the latest points as well as their position.
Measurements that cannot be compared
A response time measured under 500 users and then under 3'000 gives two unrelated numbers. The plan sets the method and the measurement conditions for each milestone. The report flags every change of method.
A project green on cost and schedule
A project can hold its cost and schedule while its product drifts away from the target. Earned value counts the work accomplished. It says nothing about whether the product will meet its technical target. A committee that reads only the cost and schedule indices discovers the problem at the acceptance test.
AI considerations
A language model proposes candidate MOPs and TPMs from a requirements specification. The analyst tests each candidate against the selection criteria and discards those that cannot be measured during the project. The model also proposes plausible parameters with no link to a written need: the analyst discards them.
A model fits a trend to the achieved values and calculates the current estimate. Two or three comparable measurements give a fragile projection. The team checks the calculation and presents the projection with its assumption.
Application performance monitoring tools detect anomalies through machine learning. They flag a drift in response time between two milestones. These tools produce a value at every release. The team names the measurement of record for each milestone.
The model drafts the report commentary from the table of values and the team's notes. The cause of the variance and its seriousness remain an engineering judgement. The model copies the profile, the band and the threshold from the technical plan unchanged. A supplier's test results and the contract clauses stay out of online services whose terms of use the organisation does not control.
Examples
A canton renews its online tax return portal. The contract with the supplier sets an acceptance criterion: a response time of at most 2.0 s at the 95th percentile under 3'000 concurrent users. The team aims for 1.5 s. The report at milestone M3 holds a chart and a commentary.
| Milestone | Method | Planned (s) | Band (s) | Achieved (s) | Variance (s) | Position |
|---|---|---|---|---|---|---|
| M1 | Estimate on prototype | 3.0 | 2.5 to 3.5 | 3.2 | −0.2 | Inside the band |
| M2 | Load test | 2.6 | 2.2 to 3.0 | 2.9 | −0.3 | Inside the band, near the edge |
| M3 | Load test | 2.2 | 1.9 to 2.5 | 2.8 | −0.6 | Outside the band |
| M4 | Load test | 1.9 | 1.7 to 2.1 | |||
| M5 | Load test | 1.7 | 1.5 to 1.9 | |||
| M6 (acceptance) | Load test | 1.5 | 1.4 to 1.6 | |||
| Cause | Each page queries the taxpayer register. The call takes 0.9 s at the 95th percentile against 0.3 s planned. | |||||
| Seriousness | The trend excludes the prototype estimate at M1 because that value comes from another method. The two load tests show a fall of 0.1 s per milestone. At that pace the response time would reach 2.5 s at M6. The threshold is 2.0 s. | |||||
| Action | The supplier loads the taxpayer's data once per session. It estimates the gain at 0.8 s per page. The team checks the gain at M4. | |||||
| Current estimate | 1.7 s at M6 with the correction: below the threshold of 2.0 s but outside the M6 band (1.4 to 1.6). Risk R7 stays open. | |||||
| Risk register | Risk R7 "Response time threshold missed at acceptance": probability raised from low to high until the M4 measurement. | |||||
With the correction the estimate meets the threshold but stays outside the M6 band: the committee keeps risk R7 open until the M4 measurement. The alert comes three milestones before acceptance. The supplier corrects the design instead of failing the acceptance test.
Visualisations
The profile chart brings together on one time axis the planned profile, the band, the threshold, the goal and the achieved values. When a project tracks several parameters, a dashboard brings them together at the same milestone. A component parameter on the dashboard points to the cause of a variance. The dashboard also separates the parameters reported to the customer from those that the supplier tracks for itself.
| Parameter | Level | Planned | Band | Achieved | Position |
|---|---|---|---|---|---|
| 95th percentile response time (s) | Reported to the customer | 2.2 | 1.9 to 2.5 | 2.8 | Outside the band |
| Call to the taxpayer register (s) | Supplier's internal tracking | 0.3 | 0.2 to 0.4 | 0.9 | Outside the band |
| Average page weight (KB) | Supplier's internal tracking | 900 | 800 to 1'000 | 850 | Inside the band |
| Error rate under load (%) | Reported to the customer | Threshold 1.0 | No band | 0.4 | Below the threshold |
Cost
| Phase | Level | Rationale |
|---|---|---|
| Preparation | High | Derive the parameters from the need, estimate a profile and a band for each parameter and set the measurement methods with the technical team. |
| Execution | Medium | One measurement per parameter and per milestone. A load test or a weighing needs an environment that is ready. |
| Documentation | Low | One chart and one commentary per parameter and per milestone. Updates to the risk register. |
Tools
A spreadsheet is enough to hold the profile, the band, the achieved values and the chart for a few parameters.
Load testing tools (Apache JMeter, Gatling, k6) and application performance monitoring tools (Dynatrace, Datadog) produce the measurements of a software parameter. For a hardware product, CAD software calculates the mass from the digital mock-up.
Requirements management tools (IBM DOORS, Jama Connect, Siemens Polarion) link each TPM to the MOP and to the need that it derives from. This traceability shows which requirement a variance threatens.
Sources
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., §2.7.2.6 and figure 2-53, Section 4 (entry Work performance data), Section 5 (entries Technical performance analysis, p. 205, Variance analysis and To-complete performance index), glossary (technical performance measures).
- Defense Acquisition University Press, Systems Engineering Fundamentals, January 2001, chapter 14 (Metrics) and supplement 14-A (Technical Performance Measurement), pp. 124 to 132.
- NASA, NASA Systems Engineering Handbook, NASA/SP-2016-6105 Rev2, §4.2.1.2.5 (Define MOPs and TPMs), appendix J §7.4 and glossary (Margin, Technical Performance Measures).