Task board
The task board is a three-column board that shows the state of each task in an iteration: to do, in progress or done. The team breaks each item selected for the iteration into tasks and writes each task on a card. The card moves from one column to the next as the work advances. The team reads the board at its daily meeting and clears it at the start of the next iteration. The PMBOK Guide files it among the visual controls. The board carries no work-in-progress limit (WIP limit): the cap per column belongs to the kanban board.
Goal
The task board displays the plan of an iteration as cards spread over three columns by state. The PMBOK Guide treats it as a visual representation of the planned work that shows everyone the state of the tasks. Anyone sees at a glance how many tasks sit at each stage. Lean calls the displays that compare actual work with planned work visual controls.
Every day the team reads off the board where each task of the plan stands. The board supports the decisions of the daily meeting: who takes which task, which card has stopped moving, which obstacle to handle after the meeting. The Monitor and Control Schedule process (§2.3.2.3) counts this daily coordination meeting, velocity and the burndown among its tools.
The deliverable is the up-to-date board. At the end of the iteration, the items whose cards are all done count toward the velocity. The burndown tracks what remains.
Usage
When to use it
- A planned iteration: display the Sprint Backlog or the iteration plan as soon as planning ends.
- The daily meeting: give the team a shared surface it can read in fifteen minutes.
- Items that break down into tasks of a day or less: each card changes column between two daily meetings. A card that stays put stands out.
- A distributed team: a shared board replaces the wall if everyone moves their own card during the day.
- A team new to agile: a first tool with no flow rules to learn before a possible move to kanban.
When not to use it
- Continuous flow without iterations: support or requests as they arrive leave nothing to reset; prefer the kanban board and its WIP limits.
- Tracking initiatives across a portfolio: the cards would be whole projects; prefer Portfolio Kanban.
- Forecasting the end date for the sponsor: the board shows today's state; draw a burndown or burnup chart for the trend.
Description
To do, in progress, done
The Agile Alliance glossary describes the board in three columns: "To Do", "In Progress" and "Done". At the start of the iteration every card sits in "To Do". A card moves to "In Progress" when someone starts the task. It moves to "Done" when the task is finished.
The columns describe the state of a task. They name no activity. A development, writing or test task crosses the same three columns. According to the PMBOK Guide, the colour of the card shows the type of work. A dot added each day counts the time the card has spent in its column.
One card per task, never per item
A task is a piece of work that one person carries through to the end. The backlog item labels a row of the board. It is often a user story that the team breaks into tasks during iteration planning. The Scrum Guide describes the Sprint Backlog as the Sprint Goal, the selected items and an actionable plan for delivering the Increment. The tasks on the board are that plan. The task board is the common form this plan takes in practice.
One row per item groups its tasks. The item is done when all its tasks are in "Done" and it meets the Definition of Done. The Scrum Guide observes that Developers often break an item into units of one day or less. Such a task changes column at least once between two daily meetings. A two-week task stays "In Progress" for the whole sprint and tells the team nothing.
What separates it from the kanban board
The PMBOK Guide cross-references the two terms in its glossary. Its Figure 5-25 puts both boards under one title and shows a capped column. Yet the two tools differ in what the columns carry and in what moves.
On a kanban board the columns are the steps of the workflow, for example analysis, build and test. The item itself crosses these steps. The Kanban Guide defines the board as the visualisation of the definition of workflow. It requires control of work in progress. Most often the team sets a limit on each step. On the task board the item stays put. The team breaks it into tasks and tracks the progress of each task: to do, in progress, done. No column carries a WIP limit. The cap, the pull rule and the blocked card belong to the kanban board and WIP limits.
| Task board | Kanban board | |
|---|---|---|
| Columns | The state of a task: to do, in progress, done | The steps of the workflow |
| What moves | The tasks of a decomposed item | The item itself, from step to step |
| What the team tracks | The progress of each task | The flow of items, their age and their queues |
| WIP limit | None | Usually one per step |
| Scope | One team, one iteration | A continuous flow, for a team or a service |
| Reset | Every iteration | Never: the board is permanent |
Portfolio Kanban in the Agile Extension to the BABOK Guide applies the kanban logic one level higher. Its cards are strategic initiatives. Its columns are the steps the initiatives pass through, each with an exit criterion and a limit.
Setting up the board
- Start from the iteration plan: the items selected at planning, in order of priority.
- Break each item into tasks, including the tests and documentation that the Definition of Done requires.
- Write one card per task with a verb, an object and the identifier of the item. Place every card in "To Do" on the row of its item.
- Put the board where the team walks past it every day. A remote team keeps the tool open during the day and moves the card when the work changes state.
- When someone starts a task, they move the card to "In Progress" and write their name on it.
- When the task is finished, the same person moves the card to "Done".
- At the end of the iteration, note the cards not in "Done". Then clear the board for the next plan. An item with a card not in "Done" returns to the Product Backlog. The next planning decides whether to take it up again.
The Developers choose their own tasks. The Scrum Guide states that they decide among themselves who does what, when and how. It makes the Sprint Backlog a plan "by and for the Developers". A project manager who assigns every card at planning turns the board into a list of assignments. The team then stops reading it as its own plan.
Reading the board at the daily meeting
The Agile Alliance makes the board the anchor of the daily meeting. The Scrum Guide limits the Daily Scrum to fifteen minutes. The Developers inspect progress toward the Sprint Goal and adapt the Sprint Backlog. The Guide leaves the structure to them. The board supplies one: the team reads the cards instead of going round the table.
An "In Progress" card that collects dots signals an obstacle. A row whose cards all stay in "To Do" in the middle of the iteration signals an item at risk. A task discovered along the way becomes a card in "To Do": the Sprint Backlog adapts while the Sprint Goal stays. The people concerned handle the obstacle after the meeting.
The board shows the whole team who is stuck. It only works if a person can say "I'm stuck" without being punished. In a team where it costs dearly to admit being behind, cards move to "Done" too early.
The fourth-column trap
The Agile Alliance glossary notes that teams often add further columns. It cites "In Test". The task board keeps its three columns.
In an "In Test" column, cards pile up while new tasks start. The team usually responds with a WIP limit on that column. This limit does not work on a task board. A WIP limit regulates a step of the flow. "In Test" names an activity: the column brings a step of the flow into a board whose other columns name states. A limit on "In Test" holds cards back in "In Progress". The pressure then backs up into "To Do", where no limit makes sense: by definition, that column holds the whole plan of the iteration. A team that wants limits moves to the kanban board.
The test column also signals a team split in two. Some build and others test. Nobody carries the whole item to "Done". Some developers regard testing as beneath them. Decomposition corrects this flaw: the test is a task of the item and gets its own card. Whoever is free takes it, even if they wrote the code.
The card that carries a whole item
A team that puts its user stories on the board without breaking them down gets a kanban board without steps. Each card stays "In Progress" for days and the daily meeting has nothing to read. The fix belongs to planning: break the item down before placing the first card.
The board nobody looks at
The PMBOK Guide describes information radiators as displays placed where everyone sees them. The team updates them often and by hand. A board kept in a tool that the team opens only at the meeting loses this property. A board updated the day before a review describes the past. The card moves when the work changes state.
AI considerations
A language model breaks a user story into tasks from its acceptance criteria. The team reviews the proposal at planning. A model often splits by phase across the whole item: analyse US-41, develop US-41, test US-41. Each card then lasts several days. Testing waits for development to finish. On review, the team re-splits by outcome: each task produces one thing that one person finishes alone in a day or less. Each outcome gets its own test task. The model can also read the board export before the daily meeting and list the cards that have been "In Progress" for more than a day.
The model moves no card. The state of a task comes from the person doing it: a status inferred from commit messages or a chat tool describes what the tool saw. Only the person knows what remains to be done. Cards often contain client names, case numbers or extracts of production data. At a health insurer they also carry the health data of insured persons, which the FADP classes as sensitive personal data. A request sent to a hosted service carries them outside the organisation.
Examples
This is the board of a team at a health insurer on day four of a two-week sprint.
After the meeting, the team works with Nora on the obstacle that the three dots on card T6 signal. On row US-42, three cards out of four are still in "To Do" six working days before the end: the next meeting checks that this row moves.
Marc, who wrote the upload API on card T2, is working on test task T4. Nobody waits for someone else to test their work.
Visualisations
Draw the board as three columns of equal width with one row per item. The label of the item opens its row. Each card carries an identifier, a verb and an object. An "In Progress" card also carries the name of the person. A coloured strip on the edge of the card shows the type of work. The dots count the days spent in the column. No number appears at the head of a column.
Cost
| Phase | Level | Justification |
|---|---|---|
| Preparation | Low | Break the items into tasks at iteration planning and write the cards. |
| Execution | Low | Move a card when its state changes and read the board during the daily meeting. |
| Documentation | Low | The board is the document. A photo or an export at the end of the iteration is enough to keep a record. |
Tooling
A wall or a whiteboard, coloured sticky notes and a marker are enough for a team on one site. The PMBOK Guide describes these displays as kept by hand rather than generated by a tool.
A remote team uses a shared tool. A project created with the default template (Jira Software) or the default process (Azure Boards) offers a sprint board whose initial columns are the three states. By default the Jira sprint board moves the whole story and reproduces the trap of the card that carries a whole item. It becomes a task board when the team creates subtasks and groups the swimlanes by story. The sprint Taskboard in Azure Boards has this layout out of the box: one row per backlog item, one card per task. Trello, GitHub Projects, Miro or MURAL also work with three columns created by hand. Jira Software and GitHub Projects offer a limit per column. On a task board that field stays empty.
Sources
- Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., PMI: the definition of the task board among the visual controls; its three states; the colours; the dots that count the days in the column; Figure 5-25 (Section 5, pp. 212-213); information radiators (Section 5); the daily coordination meeting, velocity and the burndown among the tools of the Monitor and Control Schedule process (§2.3.2.3); the definitions of the task board and the kanban board (Glossary).
- Agile Alliance, Glossary: Task Board: the three columns, one card per task, the update during the daily meeting, the reset at each iteration and the frequent addition of columns such as "In Test".
- Ken Schwaber and Jeff Sutherland, The Scrum Guide, November 2020, sections "Scrum Team", "Sprint Planning", "Sprint Backlog", "Daily Scrum" and "Increment": the Developers who decide among themselves who does what, when and how; the breakdown into units of one day or less; the Sprint Backlog as goal, selected items and plan of the Developers; the fifteen-minute Daily Scrum and its free structure; the Definition of Done and the return of an unfinished item to the Product Backlog.
- The Kanban Guide, Orderly Disruption Limited and Daniel S. Vacanti, May 2025: the kanban board as the visualisation of the definition of workflow and the control of work in progress, for the comparison only.