Two diagrams side by side. On the left, "With Nadia": four actors linked by lines to five payroll tasks. Nadia is linked to all five tasks. Luc is linked by a solid line to the monthly payroll run and to the staff questions. A dashed line links Luc to the OASI and occupational pension parameters. The HR department is linked to the staff questions. The software vendor is linked to the rejected payment file by a dashed line. On the right, "Without Nadia": Nadia is struck through and her lines disappear. The banking portal certificate is left with no line and carries the label "Gap". The rejected file and the OASI and occupational pension parameters carry the label "To verify". The monthly payroll run and the staff questions carry the label "Covered".

Slaying the Hero

Slaying the Hero is an exercise that checks whether a team keeps working when the person everything depends on is missing. The team imagines that this person disappears for a time and checks who takes over each of that person's tasks. George W. Anderson calls this person the hero. The hero can also be a team or a process. The team plays out the absence in a tabletop exercise and typically also in a live exercise. It then answers six questions about its backups and how its skills are spread. Anderson describes the technique in Design Thinking for Tech (2023) as a long-standing disaster recovery practice.

Goal

Slaying the Hero checks that a team can work without the person it depends on most. Anderson slays the hero in a figurative sense. He likens the exercise to "human prototyping and testing".

The hero is a single point of failure (SPOF). In systems engineering, the term means the component whose failure stops the system. Anderson applies it to a person. In the book's worked example, Faizel is the only technician on the team who can run the central network hub. Anderson asks for the same redundancy in people that cloud infrastructures build in for machines and sites.

The technique helps decide where to build this redundancy: whom to train, whom to pair and which partner to hire. Anderson links the technique to Buddy System Pairing, which teams a newer member with an experienced one. Our reading sets one deliverable: the list of the hero's tasks, each with a named backup or marked as a gap.

Usage

When to use

  • Only one person knows how: tickets wait for that person's return and their holidays are negotiated.
  • Deadline that rests on the hero: the book cites the monthly update and the annual disaster recovery exercise.
  • Planned absence of the hero: maternity or paternity leave, military refresher course or departure; play out the absence before it begins.
  • Pairing already in place: after a Buddy System Pairing, check that the trained member covers the tasks.
  • Single team or partner: a single provider or a single night shift; the book extends the hero beyond one person.
  • Hero assigned to a project or promoted: play out the absence before releasing the hero.
  • Hero outside IT: the only person who runs calls for tender or the annual closing of the accounts.

When not to use

  • Hero not yet identified in a large code base: the exercise tests a known person; first estimate from the code history how many departures would stall the project (bus factor).
  • Hero already gone: nobody is left to correct the team; reconstruct the hero's work through document analysis and observation.
  • Proving a system's recovery time: the exercise tests people; run a functional exercise of the recovery plan.

Description

What the book gives

Anderson describes the hero's absence: an unexpected holiday, a sick relative to care for, a sudden disappearance. In his view, the technique prepares the team for anything from a minor incident to a major disaster. The team plays out the absence mentally and typically also through a live exercise. It does so "on occasion" before reality forces it to. It then answers the book's questions.

  1. What are our workarounds?
  2. Who are our workarounds?
  3. Do we have a backup?
  4. Are we too dependent on a specific person or system or process?
  5. Do we have the right skills distributed across enough people?
  6. Do we have fallback people and partners we may lean on in an emergency?

The steps

The first four steps follow the order the book implies. The instructions in each step and the fifth step are our reading.

  1. Choose the hero. The team looks for the person it means when it says "we wouldn't know what to do without them". The facilitator lists the hero's tasks with the hero. For each task, the facilitator notes the access it requires and the partner the hero calls.
  2. Set the absence. The facilitator picks one of the book's three scenarios and gives it a duration: one day, two weeks or a departure with no return. The facilitator schedules the absence over a date when one of the hero's tasks falls due: a payment run or an update.
  3. Play out the scenario. For the tabletop exercise, the team meets around a table. The facilitator announces the absence and goes through the list task by task. For each task, the facilitator asks who acts and how. The hero listens without answering: the exercise measures what the team knows. At the end, the hero corrects what the team assumed. In the live exercise, the hero stays out of reach for one working day. The backup runs the real tasks. Our reading adds a safety rule. The team picks a date on which a failure can still be put right or keeps the hero on call for the facilitator alone. The facilitator records each call to the hero as a gap.
  4. Ask the book's questions. Once the team has gone through every task, the facilitator asks the six questions about all its answers together. The second and the sixth ask for names.
  5. Write the list. For each task, the team records the backup and a status: covered, to verify or gap. Each task marked "to verify" and each gap gets an action, an owner and a date.
The rule that assigns a status to each task. Our reading.
StatusCriterionWhat establishes itWhat follows
CoveredA named backup has already done the task alone with their own access. For an external partner: a contract and a response time that meets the task's deadline.The live exercise or a past run without the hero. The contract for a partner.No action.
To verifyThe named backup has never done the task alone. For an external partner: a response time that exceeds the task's deadline.The tabletop exercise.An action, an owner and a date: a pairing, a live exercise or a renegotiated response time.
GapNobody can take over the task or nobody has the access it requires.The tabletop exercise or a call to the hero during the live exercise.An action, an owner and a date before the task's deadline.

The book and our reading

What the book specifies and what our reading adds.
ElementIn the bookOur reading
HeroA person, a team or a processOne hero per session.
AbsenceUnexpected holiday, sick relative, disappearanceThe facilitator sets a duration and a date.
FormMentally and typically also through a live exerciseA tabletop exercise. The live exercise deprives the team of the hero for one day.
Frequency"On occasion"Before each annual disaster recovery exercise and after each departure from the team.
FacilitationNo facilitator namedSomeone other than the hero runs the session.
DurationNoneOne hour for the tabletop exercise.
DeliverableNoneThe list of tasks with their backup, their status and their action.

Anderson describes a practice that he attributes to disaster recovery and risk management. Disaster recovery prepares the return of systems to service after a major outage.

The NIST contingency planning guide (SP 800-34) recommends recovery teams large enough to work when some members are missing. The guide calls for a designated alternate for each team leader. If an outage makes members unavailable, staff from another site or contractors can form a replacement team. NIST also describes the tabletop exercise. A facilitator presents a scenario and puts questions to the participants without deploying any equipment. The tabletop exercise of Slaying the Hero follows this form. In the functional exercise, teams carry out their tasks on the systems in a simulated operational environment.

The bus factor puts a number on the same dependency. Avelino and his co-authors call it the truck factor. They define it as the minimum number of developers whose disappearance or departure would incapacitate a project. They estimate it from the code history. Slaying the Hero starts from a known person and looks for who replaces that person.

The pitfalls

The pitfalls that follow are our judgement.

Casting the hero as the problem. The hero is made to feel that they are a risk. They then defend their role or worry about their job. The facilitator talks about tasks and dependencies, never about the person's worth. The hero helps draw up the list. During a restructuring, the team reads the exercise as groundwork for someone's exit. The facilitator then waits until the restructuring is over.

Accepting a backup without a name. "Someone on the team" or "the vendor" without a contract covers no task. Each task gets a name or the gap status. An external partner counts if it has a contract and a response time that meets the task's deadline.

Taking a name for a skill. A backup who has never done the task alone stays at "to verify". The live exercise checks the skill.

Forgetting access. The backup knows the procedure but has no account, no password and no signing authority. For each task, the facilitator asks which access the backup acts with.

Leaving the list without follow-up. A gap with no owner and no date stays a gap. According to Anderson, the pairing builds the redundancy. Slaying the Hero checks that it holds.

AI considerations

Before the session, a language model summarises the hero's tickets, procedures and on-call log. It proposes a first list of tasks with the access each one requires. The facilitator reviews this list with the hero. The model sees only what is written. The exercise looks for the knowledge that the hero has never written down.

During the session, a model proposes complications to the scenario: a file rejected the day before a payment run, an expired certificate. The facilitator keeps those that affect the tasks on the list.

A model that reads the tickets proposes the person who appears in them most often as the backup. A comment on a ticket does not prove that its author can handle the task alone. The team and its management appoint the backups against the status criteria and bear the consequences.

Tickets and logs name employees. A workload analysis per person processes personal data under the Federal Act on Data Protection (FADP). The final list also shows which access depends on a single person. An attacker would find a target in it. The team keeps these documents out of external AI services or anonymises them before uploading them.

Examples

In this invented example, Nadia is the only person who runs a municipality's payroll software. The IT team plays out an unplanned absence from 17 to 30 November. The absence covers the salary payment of 25 November.

With Nadia
NadiaHero
Luc
HR department
Software vendor
Monthly payroll run
Rejected payment file
Banking portal certificate
January OASI and occupational pension parameters
Staff questions
Without Nadia
NadiaHero
Luc
HR department
Software vendor
Monthly payroll runCovered
Rejected payment fileTo verify
Banking portal certificateGap
January OASI and occupational pension parametersTo verify
Staff questionsCovered
Solid line: covered Dashed line: to verify
On the left, each line links a task to an actor who can take it over. Nadia is linked to all five tasks. On the right, the team removes Nadia. The banking portal certificate is left with no line and becomes a gap. Two tasks are left with only a line that is still to be verified. Invented example.
Nadia's task list after the session. Invented example.
TaskBackupStatusAction
Run the monthly payrollLucCovered: Luc ran it alone in July.None.
Correct a payment file rejected by the bankSoftware vendorTo verify: the contract sets a response time of two working days. The bank must receive the corrected file on the working day after the rejection.By 31 October, the head of department negotiates the response time down to one working day.
Renew the banking portal certificate before 30 NovemberNoneGap: only Nadia's account can access the portal.The head of department opens access in Luc's name before 31 October.
Import the January OASI and occupational pension parametersLucTo verify: Luc has never done it alone.Nadia pairs with Luc to prepare the import before 15 December.
Answer staff questions about payslipsHR department and LucCovered.None.

The session brought the third row to light: nobody knew that access to the portal ran through Nadia's account alone. The certificate expires on the last day of the absence in the scenario.

Visualisations

One table gives the rule that assigns a status to each task. Another separates what the book specifies from what our reading adds. A diagram shows Nadia's tasks before and after her removal. A final table shows the list that the session produces.

Cost

DimensionLevelJustification
PreparationLowOne hour with the hero to list their tasks, access rights and partners.
ExecutionLowOur estimate: one hour for the tabletop exercise. The live exercise deprives the team of the hero for one day.
DocumentationLowOne line per task. The team keeps the list until the actions are closed.

Tooling

A whiteboard or a spreadsheet is enough for the list. The ticketing tool (Jira, ServiceNow) shows the requests that only the hero has handled. The on-call rota shows the weeks when the hero is alone on duty. The directory (Active Directory), the access management tool and the password manager show the access rights that have only one holder. A remote team holds the session by video call with a shared document.

Sources

Anderson describes a practice that he attributes to disaster recovery planning. He gives it a name and a form. NIST describes alternates and the tabletop exercise. The steps, the deliverable, the facilitation, the duration and the pitfalls are our reading.