Scrum of Scrums
The Scrum of Scrums is a coordination meeting between several Scrum teams that deliver one product. Each team sends a delegate. The delegates raise the impediments and dependencies between teams, settle on the spot what they can and take the decisions back to their teams. Jeff Sutherland introduced the practice at IDX Systems in 1996 and published it in 2001. Organisations add it to Scrum when one product needs several teams.
Goal
The Scrum of Scrums coordinates the work of several Scrum teams that deliver one product. A Daily Scrum sees only its own team's work. When the Portal team waits for an interface that the Claims team must deliver, neither team's daily meeting tracks the shared deadline. The dependency stays invisible until the day it blocks. The Scrum of Scrums brings it to light while the teams can still react.
The meeting decides which team delivers what to whom and by when. It names who removes each impediment and which impediments lie beyond the teams' reach and go up a level. It keeps a backlog of open items.
Usage
When to use it
- Several teams on one product: they deliver one integrated increment and depend on each other's work.
- Four or five teams on the product: the size Scrum@Scale gives a Scrum of Scrums; beyond that, add a level.
- An interface delivered by another team: one team consumes an API, a component or data that another team builds in the same sprint.
- A shared release on a fixed date: each team must learn in time what threatens the date.
- Teams spread over several sites: the Scrum Masters of each site meet remotely and connect teams that never cross paths.
- An impediment that several teams run into: one meeting deals with it instead of one Daily Scrum per team.
When not to use it
- The same dependencies every sprint: component teams produce them; reorganise into teams that deliver features end to end.
- Joint planning and review needed: a meeting of delegates cannot hold them on its own; adopt Nexus, LeSS or Scrum@Scale, which add these joint events.
- Priorities to settle between independent products: the Scrum of Scrums settles dependencies within one product; decide between initiatives on a Portfolio Kanban.
Description
The participants
The sources differ on who the delegate should be. At IDX, the team leaders of every Scrum in a product line met. The Agile Alliance glossary speaks of an ambassador: depending on the context, a technical contributor, the team's Scrum Master or a manager. Mike Cohn leaves the choice to the team. He recommends a technical contributor rather than the Product Owner or the Scrum Master. The delegate changes over the course of the project: the team sends the person best placed for the current topics. Early on, the topics often concern technology or user experience. Later, when collaboration on testing dominates, the team tends to send a tester. With up to four teams, Cohn accepts two delegates per team: a technical contributor and the Scrum Master. The meeting then has eight people at most.
The Scrum@Scale Guide sets the optimal number at four or five teams per Scrum of Scrums. At IDX, most business units had fewer than 100 developers. According to Sutherland, one Scrum of Scrums was enough to coordinate a group of that size.
In the Scrum@Scale Guide, the term Scrum of Scrums names the group of teams itself. The daily meeting of their representatives is called the Scaled Daily Scrum. The group also holds joint planning, review and refinement. The Scrum of Scrums Master facilitates the meeting. The role goes to one of the teams' Scrum Masters or to a dedicated person. This person makes sure the meeting takes place and keeps to its planned length. They help the delegates rank impediments by priority and remove them by tracking the dependencies between teams closely.
Cadence and duration
The sources propose cadences that range from a fifteen-minute daily meeting to a weekly one.
| Source | Frequency | Duration | Participants |
|---|---|---|---|
| Sutherland, IDX (2001) | Once a week | Not stated | The team leaders of every Scrum in a product line |
| Sutherland, PatientKeeper (Scrum Papers) | Every day | 15 minutes | The whole development team; the team leaders report |
| Schwaber as reported by Cohn (2007) | Every day | 15 minutes at most | Not stated |
| Cohn (2007) | Two or three times a week | 30 to 60 minutes booked in the calendar | One technical contributor whom the team chooses |
| LeSS | Two or three times a week | Not stated | Not stated |
| Agile Alliance | Every day | Not stated | One ambassador whom each team appoints at the end of its Daily Scrum: technical contributor, Scrum Master or manager |
| Scrum@Scale (2022) | Every day | 15 minutes at most | At least one representative per team |
Cohn leaves the frequency to the teams. A common rule defers problem-solving until after the Daily Scrum. Cohn instead deals with problems during the Scrum of Scrums: a problem that rises that far can affect the work of a hundred people. He therefore books 30 to 60 minutes. The meeting often ends after fifteen. A daily cadence suits teams that integrate their work every day. Cohn's less frequent and longer meetings leave time to settle the items during the meeting.
How the meeting runs
Cohn splits the meeting into two parts. The first part is a round in which each delegate answers for their team:
- What has your team done since we last met?
- What will your team do before we meet again?
- Is anything slowing your team down or getting in its way?
- Are you about to put something in another team's way?
The fourth question looks ahead to the obstruction a team is about to cause. A team that will restructure the code repository announces it. The other teams prepare for it. The delegates raise problems during this round. Nobody looks for a solution until every delegate has answered. During the round Cohn also applies the rule that bans people's names. This rule keeps the round at team level and stops it from running long.
The Scrum@Scale Guide proposes a variant centred on impediments and dependencies:
- Which impediments will prevent a team from reaching its Sprint Goal or threaten the release plan?
- Is a team doing something that will prevent another team from reaching its Sprint Goal or threaten its release plan?
- Have the teams discovered a new dependency or a way to remove one?
LeSS rephrases the questions so that every answer concerns the other teams:
- What has my team done that is relevant to the other teams?
- What does my team plan to do that is relevant to them?
- Which of my team's impediments should the other teams know about or can they help remove?
The second part deals with the problems raised in the round and with the open items of the Scrum of Scrums backlog. When the right people are present, they settle the problem on the spot. The Agile Alliance gives examples: the delegates agree on an interface between two teams or negotiate where each team's responsibility ends.
At PatientKeeper, Sutherland describes a daily fifteen-minute Scrum of Scrums for six teams. The whole development team attends. The team leaders do most of the reporting. The rule there is stricter: anything that can be settled in sixty seconds is settled in the meeting. The person who runs the Scrum of Scrums records the other blockers and follows them up after the meeting. The same person sends the minutes to the whole company as soon as the meeting ends.
Each delegate reports the decisions to their team at the next Daily Scrum.
- each delegate answers the questions for their team
- problems raised without solutions
- no people's names
- problems from the round and open backlog items
- settled on the spot when the right people are present
- interfaces and responsibilities between teams agreed
- register updated
- minutes sent to the teams
- each delegate informs their team at the next Daily Scrum
The Scrum@Scale Guide adds a joint retrospective every sprint. In it, the teams' Scrum Masters review the improvement experiments they ran and their results.
The Scrum of Scrums backlog
Cohn and the Agile Alliance give the Scrum of Scrums its own backlog. For Cohn, the backlog lists the open problems that the delegates must settle or track. A large sheet of paper on the team-room wall is often enough. A spreadsheet or a wiki also does the job. For the Agile Alliance, each item improves coordination between teams.
A dependency register is one possible form of this backlog. Each row names a dependency, the team that delivers, the team that waits, the deadline, the owner and the status. The deadline column holds the sprint in which the waiting team needs the delivery. At each meeting the delegates read the register from the nearest deadline onwards.
Going up a level
When one Scrum of Scrums no longer suffices, the structure repeats. Cohn describes a higher-level meeting that coordinates several Scrum of Scrums meetings. The Scrum@Scale Guide calls it the Scrum of Scrum of Scrums. A Scrum of Scrum of Scrums Master facilitates it. The Executive Action Team removes the impediments that no Scrum of Scrums can remove. Its members have the political and financial power to do so.
Product decisions follow another path. Sutherland places a MetaScrum above the Scrum of Scrums meetings. The Chief Product Owner leads it. The MetaScrum reviews the release strategy and decides to start, stop or change a sprint. The Scrum@Scale Guide likewise gives the "how" to the Executive Action Team and the "what" to the Executive MetaScrum, which the Chief Product Owner facilitates. The Agile Alliance glossary gives "Meta Scrum" as a synonym for Scrum of Scrums. In Sutherland's work, the MetaScrum is a separate meeting that decides content. The Scrum of Scrums deals with impediments and dependencies.
release strategy and starting, stopping or changing a sprint
Scaling frameworks and neighbouring techniques
Nexus brings three to nine Scrum teams together on a single product. A Nexus Integration Team is accountable for the integrated increment every sprint. At the Nexus Daily Scrum, team representatives identify integration issues and new dependencies. The Nexus Sprint Backlog makes these dependencies visible.
In LeSS, teams talk to each other directly and coordinate in the code. Larman and Vodde also propose scouts. During a sprint, a scout may watch the interface with another team. The scout reports what they observe to their own team. Component communities, multi-team meetings and experts who move from team to team complete the set. According to LeSS, the need for a Scrum of Scrums can signal component teams or single-function teams. LeSS still asks teams for whom the practice works to keep it.
Portfolio Kanban decides which initiatives in a portfolio move forward. The Scrum of Scrums coordinates teams already committed to one product. The Sprint Review and the retrospective remain each team's own events. Scrum@Scale adds joint versions of them. A shared Kanban board can carry the dependency register.
Pitfalls
The round drifts into a status report when each delegate details the work of every team member. Cohn's rule on names prevents this drift. The LeSS questions focus the round more tightly on the other teams.
A delegate who reports nothing back leaves the decisions in the room: the team discovers the dependency when it blocks. The written minutes that the person who runs the Scrum of Scrums sends after each meeting guard against this failure.
A dependency recorded without a deadline or an owner does not move. The register makes both columns mandatory. An impediment beyond the teams' reach stays in the backlog sprint after sprint until someone escalates it. The Scrum of Scrums Master does so and writes down the name of the level that handles it.
AI considerations
Before the meeting, an assistant connected to the backlog tool reads each team's Sprint Backlog. It flags the items that mention another team's API, component or data without a dependency link. It lists the register rows whose deadline falls in the current sprint or has passed. After the meeting, it drafts the register update and the minutes for the teams from the notes. The Scrum of Scrums Master reviews both before they go out.
The assistant does not decide which team gives way when two Sprint Goals conflict. The Product Owner and the Chief Product Owner decide that. Nor does the assistant judge whether a recurring dependency calls for reorganising the teams: that decision belongs to the organisation. A meeting transcript contains names and sometimes known vulnerabilities of the system. The Scrum of Scrums Master puts the transcript only into a tool the organisation has approved and announces the recording to the participants. Cohn's rule on names also reduces the personal data in the notes.
Examples
The dependency register shows what a meeting leaves behind. A health insurer builds its policyholder app with four teams. Sprint 14 is under way.
| No. | Dependency | Delivering team | Waiting team | For sprint | Owner | Status |
|---|---|---|---|---|---|---|
| 1 | Claim status API | Claims | Portal | 14 | Claims delegate | In progress: API contract approved by both teams |
| 2 | Reading the QR-bills that policyholders upload in the app | Documents | Claims | 15 | Documents delegate | Open: file format to be set by the next meeting |
| 3 | Validation of the IBAN entered in the profile | Portal | Payments | 14 | Portal delegate | Delivered in sprint 13 |
| 4 | Access to the bank's test environment for transfers | Partner bank | Payments | 15 | Scrum of Scrums Master | Escalated to IT management: beyond the teams' reach |
Row 4 depends on an actor outside the teams. The Scrum of Scrums escalates it and keeps it on the register until delivery.
Visualisations
The star diagram places the teams around the meeting: the delegates bring it the dependencies and impediments and leave with the decisions. The meeting itself is drawn in three stages. The levels of coordination are drawn in two columns: impediments rise towards the Executive Action Team and product decisions towards the MetaScrum. The cadences that the sources propose and the dependency register are tables.
Cost
| Phase | Level | Justification |
|---|---|---|
| Preparation | Low | Name the delegates and the facilitator, set the cadence, open the register. |
| Execution | Medium | Four delegates and one facilitator meet three times a week for 30 minutes: 7.5 hours of attendance a week. Following up the open items comes on top. |
| Documentation | Low | The register is kept during the meeting. The minutes take a few lines. |
Tooling
A large sheet on the wall or a whiteboard is enough when the delegates meet in the same room. A shared spreadsheet holds the register for distributed teams. Jira links two issues with the "blocks" link type and shows these links in its planning views. Azure Boards traces dependencies between work items in its Delivery Plans. For a remote meeting, the delegates work on an online whiteboard such as Miro or Mural.
Sources
- Jeff Sutherland, "Agile Can Scale: Inventing and Reinventing SCRUM in Five Companies", Cutter IT Journal 14(12), December 2001: the first publication of the practice and the weekly Scrum of Scrums of the team leaders at IDX.
- Jeff Sutherland, The Scrum Papers: Nut, Bolts, and Origins of an Agile Framework, 30 March 2021, sections "First Scrum Scaling at IDX Systems 1996-2000", "Distributed Scrum of Scrums" and "Type C Scrum Solution": the origin at IDX in 1996, the size of the business units, the Chief Product Owner's MetaScrum, the distributed model, the sixty-second rule and the minutes sent after the meeting.
- Jeff Sutherland and Scrum Inc., The Scrum@Scale Guide, version 2.1, February 2022: four or five teams per Scrum of Scrums, the fifteen-minute Scaled Daily Scrum and its questions, the group's joint events, the Scrum of Scrums Master, the joint retrospective, the Scrum of Scrum of Scrums, the Executive Action Team and the Executive MetaScrum.
- Mike Cohn, "Advice on Conducting the Scrum of Scrums Meeting", Mountain Goat Software, first published by the Scrum Alliance on 7 May 2007: the delegate whom the team chooses and rotates, the cadence of two or three meetings a week, Schwaber's recommendation, the two-part meeting, the question about getting in another team's way, the ban on people's names, the Scrum of Scrums backlog and the higher level.
- Craig Larman and Bas Vodde, LeSS Framework, "Coordination and Integration": the practice that LeSS advises against, its questions, the need for it as a sign of component teams and the other means of coordination.
- Ken Schwaber, The Nexus Guide, Scrum.org, January 2021: three to nine teams on one product, the Nexus Integration Team, the Nexus Daily Scrum and the Nexus Sprint Backlog.
- Agile Alliance, Agile Glossary, "Scrum of Scrums": the term ambassador, the possible profiles of the delegate, the interfaces and boundaries of responsibility that the delegates agree on, the Scrum of Scrums' own backlog and the synonym "Meta Scrum".