Risk Response Strategies
Risk response strategies are the options a project team chooses to deal with a threat. A threat is a risk that would have a negative effect on one or more project objectives. The PMBOK Guide describes five strategies for threats: escalate, avoid, transfer, mitigate and accept. The Plan Risk Responses process develops the options, selects one strategy per threat and agrees the actions with their owners. Each selected response receives an owner and resources or a reserve. It goes into the project management plan. Apart from escalation, the same strategies apply to overall project risk.
Goal
A strategy acts on the probability of an identified and analysed threat, on its impact or on its owner. Acceptance acts on none of the three. You will find the business analysis side of risk treatment in risk analysis and management.
The technique settles one question per threat: which response to commit to, at what cost and who carries it.
The team delivers updated rows of the risk register. Each row carries the selected strategy, the action, its owner, its due date and its cost. Responses that change the plan produce change requests and updates to the project management plan. Threats accepted actively receive a contingency reserve.
A risk with a positive effect is an opportunity. The PMBOK Guide gives it five strategies of its own: escalate, exploit, share, enhance and accept. Opportunity analysis applies them.
Usage
When to use it
- Threat analysed in the high zone of the matrix: choose and cost a response before the next risk review.
- Threat outside the project scope or response beyond the project manager's authority: escalate to the programme, the portfolio or the unit whose objectives are affected.
- Contract, tender or insurance policy in preparation: write the clauses that transfer specific risks to the third party.
- Budget awaiting approval: cost the responses and the contingency reserve for the threats accepted actively.
- Overall project risk outside the sponsor's thresholds: replan, reduce the scope or share the risk with a partner.
- End of a HERMES phase or end of a release: reassess the strategies before the next phase or the next release is approved.
- Start of a sprint in agile development: review the threats in the backlog and adjust the responses.
- Response in place with no measurable effect: change strategy or strengthen the action.
When not to use it
- Threats neither identified nor rated: there is no priority to choose by; set up the risk register and the probability and impact matrix first.
- Event that has already occurred: the PMBOK Guide classes it as an issue; record it in the issue log and decide on immediate action.
- Uncertain gain: the strategies for threats do not apply; treat the opportunity with opportunity analysis.
Description
Threat, overall risk and threshold
The PMBOK Guide defines a threat as a risk that would have a negative effect on one or more objectives. Overall project risk is the effect of uncertainty on the project as a whole. It includes the individual risks and every other source of uncertainty.
Risk appetite is the degree of uncertainty an organisation is willing to accept in anticipation of a reward. The risk threshold quantifies it as the acceptable variation around an objective. A threshold of ±5% on cost reflects a lower appetite than a threshold of ±10%. According to the PMBOK Guide, appetite and threshold guide or limit the responses. The risk management plan sets them before any response.
Strategies for threats
| Strategy | What changes | When to choose it | Examples of responses |
|---|---|---|---|
| Escalate | An owner outside the project | Threat outside the project scope or response beyond the project manager's authority | Handover to the programme or the portfolio |
| Avoid | Probability brought to zero or objectives protected from the impact | Priority threat with high probability and high impact | Remove the cause, extend the schedule, reduce the scope, clarify a requirement |
| Transfer | Owner and impact passed to a third party | A third party can manage the risk and bear its impact for a premium | Insurance, performance bond, warranty, contract |
| Mitigate | Probability or impact reduced | An early cost-effective action reduces one of the two | Simpler process, more testing, more stable supplier, prototype, redundancy |
| Accept | None; a reserve or a review | Low-priority threat; no other response possible or cost-effective | Contingency reserve, periodic review |
Escalate
Escalation fits when the team or the sponsor finds that a threat lies outside the project scope. It also fits when the proposed response exceeds the project manager's authority. The programme, the portfolio or another part of the organisation then manages the threat. The project manager decides whom to notify and passes on the details. As a rule, the threat goes up to the level of the organisation whose objectives it would affect.
Escalation succeeds when the recipient accepts ownership of the threat. The team no longer monitors the threat after escalation. The register may keep it for information. A threat handed over without acceptance has no owner anywhere. The register therefore records the recipient, the date of handover and the date of acceptance.
Avoid
Avoiding eliminates the threat or protects the project from its impact. The PMBOK Guide considers this strategy suited to priority threats with a high probability and a high negative impact. The team changes some aspect of the project management plan or the objective in jeopardy. The probability of the threat then falls to zero. The risk owner can also protect the project objectives from the impact.
The guide cites removing the cause, extending the schedule, changing the project strategy or reducing the scope. Some threats disappear when the team clarifies a requirement, obtains information, improves communication or acquires expertise. Avoidance has a price: a date, a feature or an option given up. An extended schedule or a reduced scope touches a baseline and goes through a change request.
Transfer
Transferring shifts ownership of a threat to a third party. That party manages the risk and bears its impact if the threat occurs. Transfer often involves a risk premium paid to the third party. It works through insurance, performance bonds, warranties and contracts that assign ownership of and liability for specified risks.
Transfer moves the impact that the contract names. The rest stays with the project. A fixed price for the data migration transfers the overrun to the software vendor. The delay stays with the project if the contract provides for no penalty. A transfer to a third party that cannot pay or cannot manage the risk leaves the project with the threat and the premium.
Mitigate
Mitigating reduces the probability or the impact of a threat. Acting early is often more effective than repairing the damage after the threat has occurred. The guide cites less complex processes, more testing, a more stable supplier and a prototype before scale-up. When the probability cannot fall, the response targets the factors that drive severity. Redundancy in a system reduces the impact of a component failure.
For a mitigation, the team estimates the probability and the impact before and after the action. Without these two values, nobody can compare the action with its cost.
Accept
Accepting acknowledges the threat without proactive action. The strategy fits low-priority threats. It also fits when no other response is possible or cost-effective. The most common active acceptance sets a contingency reserve: time, money or resources to deal with the threat if it occurs. Passive acceptance is limited to a periodic review that checks the threat has not changed.
The PMBOK Guide defines the contingency reserve as the time or money allocated in the schedule or cost baseline for known risks with active response strategies. Reserve analysis sizes it and tracks it at each review. The register can also carry a trigger: the event or condition that indicates the risk is about to occur. The owner monitors this trigger.
"Accept" often labels a threat that nobody has dealt with. Acceptance is a decision. The register names the person who took it, the active or passive form and the date of the next review.
Choosing the strategy
The PMBOK Guide says when escalating, avoiding and accepting fit. For transfer and mitigation, it describes the effect of the response. It sets no decision order. The tree turns the guide's conditions and the cost of the response into questions. This order is a synthesis. Authority comes first: a threat that the project cannot treat goes to escalation whatever its priority. Priority comes next. For a priority threat, the team tries to remove it, then to hand it to a third party, then to reduce it. Each response must cost less than the expected loss it avoids. A threat that no cost-effective response treats is accepted.
The cost of the response is weighed against the loss it avoids. The expected loss of a threat is its probability multiplied by its impact. A threat with a 40% probability and an impact of CHF 50'000 carries an expected loss of CHF 20'000. A mitigation that costs CHF 8'000 and brings the probability down to 10% leaves CHF 5'000 of expected loss. It avoids CHF 15'000 of expected loss for CHF 8'000.
The same test applies to a transfer: the premium is weighed against the expected loss transferred. In the municipality example, a premium of CHF 12'000 transfers the overrun of M-03: an impact of CHF 42'000 at a probability of 40%, that is CHF 16'800 of expected loss.
The process draws on alternatives analysis, cost-benefit analysis and multi-criteria decision analysis. Multi-criteria analysis helps when cost alone cannot settle the choice: a legal deadline, the organisation's reputation, a safety requirement.
Agreeing the actions
The process starts from the risk register and risk report. It also reads the risk management plan, the cost baseline, the schedule, the team assignments and the stakeholder register. When identification has already noted a proposed owner or a possible response, analysis confirms the owner and response planning confirms the response.
Each threat chosen for a response receives a named owner, an action, a due date and a cost. The register also records when the threat can occur. The action falls due before that date: an action due later arrives too late. In the municipality example, the M-04 training takes place in December and precedes the January go-live. The owner leads the response and tracks the threat until it is closed. The process allocates the resources or the reserve. It inserts the response activities into the schedule and the project management plan.
A row that reads "mitigate" with no action, no owner and no due date looks treated in the register. The threat keeps its probability and its impact.
Overall project risk
The strategies for individual risks also apply to overall project risk. They then target the whole project rather than an event. The risk report presents this risk to the sponsor.
| Strategy | When to choose it | Examples of responses |
|---|---|---|
| Avoid | Overall risk clearly unfavourable and outside the agreed thresholds | Remove high-risk elements from the scope; as a last resort, cancel the project |
| Transfer or share | High overall risk that the organisation cannot address alone | Collaborative business structure in which buyer and seller share the risk, joint venture, special-purpose company, subcontracting of key elements |
| Mitigate or enhance | The level of overall risk can change | Replan, change the scope and boundaries of the project, modify its priority, reallocate resources, adjust delivery dates |
| Accept | No proactive response possible | Contingency reserve for the whole project or periodic review of the overall level |
The list for overall risk has no escalation. Transfer and share form a single entry. Mitigate and enhance also share one entry. Avoidance can go as far as cancelling the project. The PMBOK Guide reserves cancellation for the case where the overall level of threat is unacceptable and will remain so. Accepting means continuing the project as defined while overall risk lies outside the thresholds.
Implementing and monitoring
The Implement Risk Responses process executes the agreed plans. The Monitor Risks process tracks their implementation and checks their effect. It also identifies new risks and plans their responses. The team plans responses throughout the project. In agile development, the guide cites a team that assesses risks at the start of each sprint. That team reviews the strategies with the stakeholders at the end of each iteration.
A response that does not produce the expected effect goes back to planning. The owner strengthens the action or proposes another strategy.
In HERMES
In HERMES 2022, the project manager carries out the task Manage risks. The project manager identifies the risks, groups them, analyses them and assesses them. Based on the assessment, the project manager sets a strategy and measures for each risk. HERMES cites avoidance, reduction, outsourcing and acceptance as examples. The project manager commissions a person to carry out the measures and monitors their implementation. The project status report records all of it.
Avoidance, reduction and outsourcing correspond to avoid, mitigate and transfer. HERMES does not name escalation. In the traditional approach, the project manager assesses the risks continuously and at the end of each phase to prepare the release of the next phase. In the agile approach, the project manager conducts an in-depth risk review at the end of each release.
AI considerations
A language model reads the register and proposes response options under each strategy for every threat. It flags the rows with no owner, no due date or no cost. It spots a strategy that the action contradicts: "transfer" with no contract or insurance, "avoid" with a remaining probability, "accept" with no review scheduled. It calculates the expected loss before and after each response and compares it with the cost of the response. On a draft contract or insurance policy, it picks out the clauses that set what the third party covers.
The model does not know the project manager's actual authority or the sponsor's appetite. It produces plausible probabilities without a source. The owner supplies the probability after response and states where it comes from. The sponsor decides to reduce the scope or to sign a transfer, because these responses commit the budget or a third party. The register names suppliers, people and contractual weaknesses. The team sends it to an external AI service if the organisation allows it.
Examples
Each strategy changes a different element of the threat: its owner, its probability or its impact. Acceptance changes none of them. A municipality in French-speaking Switzerland is replacing the software of its residents' registration office for go-live on 1 January. The extract shows five threats from its register after response planning. The amounts are illustrative.
| Ref. | Threat | Impact if it occurs (CHF) | Probability before and after | Strategy | Response and owner | Response cost (CHF) |
|---|---|---|---|---|---|---|
| M-01 | Because the canton is changing its platform for exchanging notifications in November, the municipality's arrival notifications could be rejected for six weeks. | Outside the project: every municipality in the canton is affected | Not applicable | Escalate | Handed to the cantonal population office on 3 June. Accepted on 17 June. The team no longer monitors it. | 0 |
| M-02 | Because the waste charge module needs custom development, its delay could push go-live back by three months. | 45'000 | 50% then 0% | Avoid | The sponsor removes the module from the scope. The old software bills the waste charge for one more year. Owner: the project manager. | 9'000 for the extended licence |
| M-03 | Because the quality of the data in the old software is unknown, the migration could take 40 days beyond the estimate. | 48'000, of which 6'000 is delay | 40% then 40% | Transfer | The vendor migrates the data at a fixed price and pays for the extra days. The delay stays with the municipality: two weeks of parallel operation. Owner of the response: the vendor. | 12'000 premium over the time-and-materials quote |
| M-04 | Because the counter staff first see the software at go-live, processing an arrival could take twice as long in January. | 20'000 in overtime | 60% then 20% | Mitigate | Two days of training and two weeks of parallel testing in December. Owner: the head of the residents' registration office. | 7'000 |
| M-05 | Because go-live coincides with the January arrivals, the counter could have to open on two Saturdays. | 4'000 | 30% then 30% | Accept (active) | Contingency reserve for two Saturdays. Trigger: more than 60 files pending. Owner: the head of the residents' registration office. | 4'000 reserve |
Only M-02 falls to 0%, because reducing the scope removes the cause. M-03 keeps its probability: the fixed price shifts the overrun to the vendor and leaves the delay with the municipality.
Visualisations
Plotted on the probability and impact axes, the threats show what each response has moved. Avoiding moves a threat down the probability axis or protects the objectives from its impact. Mitigating moves it down or shifts it towards a lower impact: here, the training reduces the probability of M-04. Transferring shifts it to the impact that the contract does not cover: for M-03, the delay of CHF 6'000. Accepting leaves it in place. Escalating takes it out of the team's monitoring.
The expected loss that the municipality bears on the four threats it monitors falls from CHF 54'900 to CHF 7'600. The responses cost CHF 28'000. The M-05 reserve adds CHF 4'000.
Cost
| Phase | Level | Rationale |
|---|---|---|
| Preparation | Medium | The prospective owner costs two or three options for each priority threat before the workshop. |
| Execution | Medium | A response workshop at each risk review, then the approval of the responses that commit budget or a contract. |
| Documentation | Medium | Each row receives its strategy, action, owner, due date and cost. The responses that touch a baseline produce a change request. |
Tools
A spreadsheet or the risk register of a project management tool carries the response columns: strategy, action, owner, due date, cost, probability and impact after response. Jira or Azure DevOps manages each response as a task linked to its risk. It notifies the owner when the due date arrives.
A decision tree compares two responses to the same threat by their expected monetary value. Simulation modules (@RISK from Lumivero, Primavera Risk Analysis from Oracle, Safran Risk) rerun the project model with the responses in place. They show the effect on the date or the budget at each confidence level. For a transfer, the organisation's contract template and the insurer's general terms set what the third party covers.
Sources
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., §2.7.1, §2.7.2.4 and figure 2-51, §2.7.2.5, §2.7.2.6, §2.7.3, table 2-11, Section 4 (entry Risk register), Section 5 (entries Strategies for threats, Strategies for overall project risk, Strategies for opportunities), glossary: the threat, overall project risk, risk appetite and risk threshold; the Plan Risk Responses process with its inputs, tools and outputs; the strategies for threats and for overall project risk; the contingency reserve; the trigger in the register; the agile example. The strategies for opportunities belong to opportunity analysis.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management Reference Manual: the task Manage risks (5.4.3.41), its strategies and measures, risk assessment in the traditional and the agile approach.