Resource levelling and smoothing
Resource levelling and resource smoothing shift the activities of a schedule so that the demand for resources fits within the capacity. Smoothing moves an activity only within its float: the critical path and the finish date stay the same. Levelling delays an activity as far as the resource requires: the critical path can change and the finish date can move later. The PMBOK Guide lists both among the resource optimization techniques.
Goal
Levelling and smoothing produce a schedule that the project's people and equipment can keep to. The critical path method places each activity at its early start without asking who performs it. An analyst assigned to two parallel activities carries a 200% load that the network does not show.
The two techniques differ in what they protect: the date or the team. At a steering committee meeting, the sponsor decides which of the two is fixed.
The deliverable is a levelled or smoothed schedule together with the resource histogram before and after. Once the dates are set during schedule development, the team checks whether levelling is needed before the schedule becomes the baseline.
Usage
When to use it
- One person on two activities at once: remove the overload before it delays both activities.
- Specialist or equipment available on set dates: fit the activities to the dates when the specialist or the equipment is available.
- Staff shared between projects: check the schedule against their other assignments.
- Schedule ready for approval: level before setting the baseline.
- Contractual or statutory finish date: smooth within the available float and quantify the overload that remains.
- Team with a constant headcount: level to keep the workload steady.
When not to use it
- Repetitive production of standard items: level volume and mix with heijunka.
- Stable team working in iterations: the iteration's capacity already caps the workload; order the backlog and plan with time boxing.
Description
What each technique moves
The PMBOK Guide defines resource optimization as adjusting the start and finish dates of activities to balance the demand for resources with the available supply. Levelling adjusts the dates to the resource constraints and can change the critical path.
Free float is the amount of time by which an activity can be delayed without moving the early start of any successor. Total float is the amount of time by which it can be delayed without moving the project finish. A shift within free float affects only the activity moved. A shift within total float pushes its successors and consumes the float of the whole path.
| Question | Smoothing | Levelling |
|---|---|---|
| What stays fixed | The finish date | The resource capacity |
| Activities moved | Non-critical activities within their float | Any activity beyond its float if the resource requires it |
| Critical path | Unchanged | Can change |
| Finish date | Unchanged | Can move later |
| Overload | Can remain in some periods | Removed over the whole duration |
The PMBOK Guide states the limit: smoothing cannot always optimize all resources. An overload that lasts longer than the available float remains after smoothing. The guide also defines smoothing by a ceiling: demand stays below a limit set in advance. Practitioners describe smoothing as shaving the peaks off the histogram. The two readings coincide when the ceiling is the capacity.
Funding limit reconciliation applies the same logic to money: it compares planned spending with the project's funding limits. Where they diverge, the scheduler imposes date constraints that level the rate of spending.
Gathering the inputs
Both techniques work on a network that has already been calculated. The scheduler gathers the activity network, the resource requirements of each activity, the team assignments and the resource calendars. A resource calendar states when the resource is available and for what share of its time: part-time work, holidays, cantonal public holidays and assignments to other projects.
A wrong capacity produces a wrong levelled schedule. To check it, each team member compares their dates with their calendar.
Measuring the load
The scheduler draws the resource histogram of the early-start schedule. For each resource the histogram shows demand per period and capacity as a horizontal line. Every period where the bar rises above the line is an overload. For an employee working 60%, the capacity line sits at 0.6; a full-time activity overloads her from the first day.
The histogram period follows the grain of the schedule. A weekly histogram adds up the days of the week. It hides a two-day overload in a week that is otherwise light.
A lower bound checks the result. A single resource that performs its activities one after another cannot finish before the sum of their durations. No levelled schedule falls below the higher of two bounds: this sum and the length of the critical path.
Smoothing within the float
The scheduler first moves the non-critical activities that cause the overload. It uses free float first, then total float. After each shift the scheduler reads the histogram again: a moved activity empties one period and can load another.
Smoothing consumes float. An activity pushed to its late start has none left: the slightest delay makes it critical. A smoothed schedule carries several near-critical paths where the early-start schedule had only one. The scheduler keeps float on the most uncertain activities and smooths the activities with the best-known durations first.
Deciding the remaining overload
An overload that remains after smoothing goes to the sponsor. When the finish date is fixed, the sponsor resolves the overload outside the calculation: extra staff, overtime, subcontracting or a reduced scope. Crashing compresses the schedule by adding resources and is one of these options. It works only on critical activities whose duration shortens with additional resources. When the capacity is fixed, the scheduler levels and the finish date moves later.
Levelling
The scheduler first ranks the activities that compete for the resource by a priority rule. The usual rule serves the activity with the lowest total float first: the critical activity goes ahead, the one with float waits. In the insured-members portal example, B (float 0) goes before C (float 3): C waits for B to finish.
The serial scheme then takes the activities one at a time in priority order. It places each one at the first date when its predecessors are finished and its resource is free. The parallel scheme advances period by period and assigns the free resource to the ready activities in the same order.
The delayed activity waits for the end of another activity that it does not depend on. This resource link does not appear in the dependency network. The critical path can run through it. The PMBOK Guide calls this path the resource-loaded and levelled critical path (RLCP). It treats the RLCP as a synonym for the critical chain.
The priority rule changes the result. On the same network, a rule that serves the longest activity first can give another finish date. So can a rule that follows the order of the list. The software changes the result too: two tools or two settings of the same tool level the same network differently. The scheduler records the rule and the settings used in the schedule assumptions. A levelled schedule that finishes several days after the higher of the two bounds justifies a second run with another rule.
Setting the baseline
The scheduler keeps both versions. The PMBOK Guide lists the levelled and unlevelled schedules and the resource histogram by period among the schedule data. The sponsor chooses which version becomes the baseline. The finish date follows from that choice. After approval, a levelling run that moves the finish date goes through change control.
Pitfalls
The scheduler leaves automatic levelling switched on: the software redistributes the activities at every progress update. The dates issued to the teams change without a decision. The variance against the baseline then mixes real delays with the effects of the recalculation. The scheduler levels on demand and then freezes the result.
A pooled resource hides skills. A "development team" resource with a capacity of three people accepts three activities in parallel, even if only one person knows that interface. The scheduler levels by individual when an activity needs a specific person.
The resource link stays invisible. In the network, an activity delayed by levelling appears free to start. A manager who starts it early recreates the overload that levelling had removed. The scheduler shows the resource link on the Gantt chart or converts it into a dependency marked as a resource link.
AI considerations
Scheduling software smooths and levels reproducibly according to its settings. A language model adds nothing to the calculation. Genetic algorithms are among the optimization tools for scheduling and levelling. These metaheuristics form a family separate from language models.
On an exported schedule, a language model spots the overloaded resources and lists the overlapping activities for each person. For each resource that works alone, it adds up the activity durations to give the lower bound. It compares the levelled and unlevelled versions. It then drafts the note that presents the choice to the sponsor: finish date, activities moved, critical path before and after. It extracts absences and assignments to other projects from the team's messages for the scheduler to enter in the calendars.
The scheduler checks every date that the model proposes. A model that shifts activities without calculating violates a dependency or consumes float without flagging it. The choice between date and capacity stays with the sponsor. A calendar of named resources records each person's absences and the share of full time that the person works: these are personal data within the meaning of the Federal Act on Data Protection (FADP). Before sending the schedule to an online service, the scheduler replaces names with roles or applies the organisation's policy on online services.
Examples
A pension fund is opening an online portal for its insured members. A single business analyst performs five of the six activities.
| Id | Activity | Resource | Duration | Predecessors | Total float (early start) | Early start | Smoothed | Levelled |
|---|---|---|---|---|---|---|---|---|
| A | Scoping workshop | Analyst | 3 | none | 0 | 1 to 3 | 1 to 3 | 1 to 3 |
| B | Process modelling | Analyst | 4 | A | 0 | 4 to 7 | 4 to 7 | 4 to 7 |
| C | Specification of the interface to the insured-members register | Analyst | 2 | A | 3 | 4 to 5 | 7 to 8 | 8 to 9 |
| D | Portal development | Development team | 8 | B | 0 | 8 to 15 | 8 to 15 | 8 to 15 |
| E | Writing the test cases | Analyst | 7 | C | 3 | 6 to 12 | 9 to 15 | 10 to 16 |
| F | User acceptance testing (UAT) | Analyst | 3 | D, E | 0 | 16 to 18 | 16 to 18 | 17 to 19 |
In the early-start schedule the analyst carries two activities from day 4 to day 7. Smoothing moves C and E later by the three days of their float. One overload remains on day 7 and the finish stays on day 18. C and E have no float left. The smoothed schedule has two critical paths: A-B-D-F and A-C-E-F. Levelling places C after B and the finish moves to day 19. The critical path becomes A-B-C-E-F and runs through the resource link between B and C; development gains one day of float. The analyst carries 19 days of work: no schedule can make her finish before day 19. The sponsor chooses between day 18 with one day of extra staff and day 19 with the analyst alone.
Visualisations
The histogram shows the load. The Gantt chart of the levelled schedule shows the resource link that pushes the finish back.
Cost
| Dimension | Level | Rationale |
|---|---|---|
| Preparation | Medium | The effort of each activity and the resource calendars come on top of the network; collecting them takes longer than the calculation. |
| Execution | Low | The software smooths and levels on demand; the scheduler compares the versions and the sponsor decides. |
| Documentation | Low | The two versions of the schedule, the histogram and the priority rule used are enough. |
Tooling
For about ten activities a spreadsheet is enough. It holds one row per resource and one column per day. A formula adds up the demand and colours the cells above capacity. The scheduler moves the activities there by hand and reads the effect on the load.
Microsoft Project levels on demand or automatically. Its option that limits levelling to the available float produces smoothing. Oracle Primavera P6 offers the same setting on total float and a levelling priority per activity. ProjectLibre levels only in its paid online version. Before comparing two levelled schedules, the scheduler checks that they apply the same settings.
Sources
- Project Management Institute (2025), A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition: §2.3.2.2 Develop Schedule and its step 4 "Adjust" for the levelling check before the baseline and for the inputs; entry "Schedule data" in Section 4 for the resource histogram and the levelled and unlevelled schedules; entry "Resource optimization technique" in Section 5 and its sub-entries "Resource leveling" and "Resource smoothing" for the definitions, the situations where levelling applies and the limit of smoothing; entries "Critical chain project management (CCPM)" for the RLCP, "Schedule compression" for crashing, "Funding limit reconciliation" and "Genetic algorithms".
- Federal Act on Data Protection (FADP), SR 235.1: Art. 5 let. a for the concept of personal data.

