Reserve Analysis
According to the PMBOK Guide, reserve analysis evaluates the risk on a project and its schedule and budget reserves to determine whether the reserve is sufficient for the remaining risk. It covers two reserves. The contingency reserve funds the identified risks in the risk register. The management reserve covers unforeseen work that nobody has identified. The team sizes both when the budget is built and repeats the analysis at every review.
Goal
Reserve analysis sets the amount of time and money a project keeps for its risks. The PMBOK Guide lists it among the data analysis tools of the processes: Develop Schedule, Estimate Costs, Develop Budget and Monitor and Control Finances. It also names it among the tools for monitoring risks.
The technique links the risk register to the budget. The register states which risks threaten the project and what they would cost. The budget states how much the organisation has approved. The analysis turns the first into lines of the second and sets who may spend them. At each review it compares the reserve left with the risk left and calls for a decision: maintain, top up, reduce or release.
The deliverables are the contingency reserve recorded in the cost documentation, the management reserve with the rule that states who releases it, the cost baseline and the project funding requirements. During the project the analysis adds the reserve status at each review and updates the risk register.
Usage
When to use it
- Budget awaiting approval: size the contingency reserve from the risk register rather than as a negotiated lump sum.
- HERMES project execution order in preparation: present the estimates with their accuracy and the reserves that follow from it.
- "Accept" response chosen for a risk: size the reserve that funds active acceptance.
- Phase or milestone review: check that the reserve left covers the risk left.
- Risk occurred: draw on the reserve, close the line and recalculate what remains.
- New risk identified during the project: decide whether the existing reserve absorbs it or needs a top-up.
- Public project or small project with little financial flexibility: the PMBOK Guide recommends cautious reserves for these.
When not to use it
- Risk register empty or not quantified: the analysis has nothing to compare; identify and assess the risks first with the risk register.
- Schedule protected by critical chain buffers: an added time reserve counts the same margin twice; manage the schedule through the buffers of the critical chain method.
Description
The two reserves
The PMBOK Guide defines a reserve as a provision in the project management plan to mitigate cost or schedule risk.
The contingency reserve is the time or money allocated in the schedule or cost baseline for known risks with active response strategies. The PMBOK Guide calls these risks known-unknowns: identified risks whose amount remains unknown. The guide cites rework expected on some deliverables, whose extent nobody knows. The reserve can cover any level between one activity and the whole project. The risk management plan sets who uses it.
The management reserve is the time or money that management sets aside in addition to the baseline. It covers unknown-unknowns: the risks that nobody has identified. According to the PMBOK Guide, management usually releases it at its discretion for unforeseen work that stays within scope. Some organisations give this decision to the project manager or to the project management team.
Acceptance ties reserves to the risk response strategies. According to the PMBOK Guide, acceptance most often uses schedule or cost reserves. Its most common active form is a contingency reserve. For overall project risk, active acceptance sets a contingency reserve for the whole project.
| Contingency reserve | Management reserve | |
|---|---|---|
| Risks covered | Identified risks with an active response (known-unknowns) | Unforeseen work within scope (unknown-unknowns) |
| Place in the budget | Usually in the cost baseline; outside it depending on the organisation | Outside the cost baseline, in the funding requirements |
| Who releases it | Under the rules of the risk management plan | Usually management; the project manager in some organisations |
| Sizing | Percentage of the estimate, fixed amount or quantitative analysis | Organisational rule or management decision |
| During the project | Used, reduced or eliminated as information improves | Released case by case on request |
Inside or outside the baseline
The cost baseline is the approved time-phased version of the budget. It changes only through formal change control. Actual costs are measured against it. The PMBOK Guide describes two ways to build the initial budget (figure 2-25).
When reserves are managed implicitly, the initial budget adds up the work package estimates, the contingency reserve and the management reserve. The cost baseline contains the contingency reserve and excludes the management reserve. When reserves are managed explicitly, the initial budget and the baseline contain the estimates alone. The two reserves stand apart.
According to the PMBOK Guide, the contingency reserve usually sits in the initial budget. It can move out of it because of organisational preferences or external constraints. The guide's reference sections describe the inputs, outputs and tools of the processes. They assume the first case, in which the contingency reserve is part of the baseline.
The two budget build-up scenarios
Grants management at a cantonal office. Illustrative amounts in CHF.
The project's funding requirements derive from the cost baseline. According to the PMBOK Guide, the total funding required equals the baseline plus any management reserve. Funding often arrives in quarterly or annual instalments. The chosen scenario changes what the baseline contains and the variances measured against it. The financial management plan should state which one applies.
The sequence of the analysis
The steps synthesise the PMBOK Guide's passages on reserves, the budget and risk monitoring.
- List the identified risks from the register and their cost or schedule exposure.
- Size the contingency reserve.
- Record it in the cost documentation.
- Set the management reserve outside the baseline and name the authority that releases it.
- At each review, compare the reserve left with the risk left.
- Use, reduce or release the reserve under the planned authority.
The sequence of reserve analysis
Synthesis of the PMBOK Guide passages on reserves, the budget and risk monitoring
List the risks
Each risk taken from the register in step 1 carries a probability and an impact in francs or in days. A risk without a quantified impact enters no reserve calculation.
Size the contingency reserve
The PMBOK Guide allows a percentage of the estimated cost, a fixed amount or a quantitative analysis method.
The simplest quantitative method multiplies each risk's probability by its impact. The product is its expected monetary value. This method measures a risk's exposure by that value. The sum of the expected values gives a reserve that covers the average cost of the risks. This reserve is exceeded when the risks that occur cost more than the reserve holds. A risk that occurs costs its full impact.
A Monte Carlo simulation draws the risks and the estimates together and gives the distribution of the total cost. The reserve is then the difference between the cost at the chosen confidence level and the base estimate. The sponsor sets this level according to the overrun they accept. Sensitivity analysis identifies the risks that weigh most on this difference. Decision trees compute the expected value of an option when the response to a risk is a choice between several paths.
Record the reserve
According to the PMBOK Guide, the contingency reserve must be clearly identified in the cost documentation. The team puts it on a separate line that lists the risks it covers and the amount of each. A reserve blended into the estimates can no longer be compared with anything. Nobody knows which risk it funds or how much of it is left.
HERMES sets a similar requirement for the traditional approach. The estimates appear in the project execution order and in the project management plan with their accuracy and the reserves that follow from it. The assumptions behind these estimates are documented for the transparency that governance requires.
Set the management reserve and its authority
The management reserve is not calculated from the register, since it covers what the register does not contain. Its amount comes from an organisational rule or a management decision. According to the PMBOK Guide, a small project with little financial flexibility calls for a cautious approach with both reserves. A public project that answers for its spending assesses its reserves with a wider margin. The sponsor and stakeholders of such a project influence this assessment.
According to the PMBOK Guide, the risk management plan sets the rules for using both reserves. These rules should name who draws on the contingency reserve, who releases the management reserve and above what amount the decision moves up. Without them, every drawdown becomes a negotiation.
Compare at each review
The reserve left is the initial reserve minus what the risks that occurred have consumed. The risk left is the sum of the exposures of the risks still open. These are the risks in the initial register that have neither occurred nor closed, plus the risks identified since. The gap between the two calls for the decision.
The team repeats the analysis in each risk monitoring or finance control cycle and at each phase review. Each review updates the risk register: a risk that occurred is closed with its actual cost, a risk that disappeared is closed at zero.
Use, reduce or release
According to the PMBOK Guide, the contingency reserve can be used, reduced or eliminated as better information becomes available. A risk that occurs consumes it. A risk closed without occurring frees a surplus. The planned authority decides whether this surplus stays in the reserve or leaves it. The answer to a negative gap is a risk response, a top-up of the reserve or the explicit acceptance of an uncovered risk. A top-up that raises the baseline goes through formal change control.
The schedule reserve
The same reasoning applies to the schedule. The reserve is then counted in days and recorded in the schedule baseline. According to the PMBOK Guide, schedule control reviews the time reserves needed. Network analysis assesses the need to aggregate them where several paths converge or diverge. It also checks whether risky activities on the critical path need a reserve or a risk response.
The critical chain method pools the variability of the activities into a project buffer. According to the PMBOK Guide, this buffer replaces the safety margins of the individual activities.
In an adaptive approach
The PMBOK Guide notes that an agile project can receive and revise its budget each quarter based on the work completed. The team compares the reserve left with the risk left at each budget revision.
Pitfalls
The reserve hidden in the estimates
An estimator who adds 15% to each work package "to be safe" creates a reserve that nobody sees. It does not appear in the cost documentation. It is spent without a decision. A contingency reserve added on top counts the same margin twice. The analyst asks for the basis of each estimate and moves the margin into the reserve, where it receives a risk and an owner.
The management reserve in the baseline
According to the PMBOK Guide, planned value excludes the management reserve. A baseline that contains it distorts earned value management in a way that depends on where the reserve sits. Placed on a line outside the work package budgets, the reserve is never earned and the cost variance stays correct. The budget at completion is inflated: percent complete never reaches 100% and the estimate at completion is too high. Spread across the work package budgets, the reserve enters the earned value of the work done. The cost variance and the cost performance index then look better than they are.
The sum of expected values taken as a ceiling
A reserve equal to the sum of the expected values covers the average cost of the risks. In the cantonal office example, if the four risks are independent, the CHF 86'000 reserve is exceeded with a probability of 42.5%. It holds only if no risk occurs, if a single risk occurs or if R3 and R4 alone occur. The historical data rework before migration (R2) enters the reserve at CHF 40'000 and consumes CHF 70'000 of it. The report that presents the reserve gives the probability of exceeding it next to its amount.
The lump sum carried over
A fixed percentage carried over from project to project does not depend on the register. It does not fall when a risk closes and does not rise when a risk appears. The review then has nothing to compare. The PMBOK Guide allows the percentage. The analyst records the risks the percentage is meant to cover alongside it so that the review can track them.
The reserve used for a scope change
The management reserve covers unforeseen work that stays within scope. A feature added during the project changes the scope. It goes through change control with its own funding. Paid from the reserve, it empties the provision meant to cover the unforeseen.
AI considerations
A language model turns an export of the risk register into a reserve table: one line per risk, the expected value, the totals, the gap. The analyst checks every formula on two lines calculated by hand. The analyst also checks that the table keeps only the risks with an active response, because otherwise the model adds up the expected values of the whole register. Without a register, a model asked to propose a reserve answers with a flat percentage: the pitfall of the lump sum carried over.
The model compares the estimates in the cost documentation with their basis and flags the work packages whose amount exceeds what the basis justifies. These gaps are candidates for a hidden reserve. The estimator confirms or explains each one.
The model drafts the review note for the steering committee from the reserve status. The sponsor or management decides the confidence level of a reserve, the amount of the management reserve and each release. The risk owners supply the probabilities and state where each one comes from. Budgets, supplier offers and contractual risks stay out of online services whose terms of use the organisation does not control.
Examples
A cantonal office is replacing its grants management application. The work package estimates total CHF 1'200'000. The office manages its reserves implicitly. The contingency reserve of CHF 86'000 is the sum of the expected values of the four risks in the register. An internal directive sets the management reserve at 5% of the estimates, that is CHF 60'000. The same directive gives the steering committee the authority to release it. The cost baseline is CHF 1'286'000 and total funding reaches CHF 1'346'000. The amounts are illustrative.
| Risk | Status | Probability | Impact (CHF) | Initial reserve (CHF) | Consumed (CHF) | Risk left (CHF) |
|---|---|---|---|---|---|---|
| R1. Land register interface delivered late | Closed, did not occur | 30% | 60'000 | 18'000 | 0 | 0 |
| R2. Historical data rework before migration | Closed, occurred | 50% | 80'000 | 40'000 | 70'000 | 0 |
| R3. Second user acceptance test (UAT) cycle | Open | 40% | 45'000 | 18'000 | 0 | 18'000 |
| R4. Supplier rate increase at the annual indexation | Open | 25% | 40'000 | 10'000 | 0 | 10'000 |
| R5. Data protection impact assessment requested by the cantonal data protection commissioner | New | 50% | 30'000 | 0 | 0 | 15'000 |
| Total | 86'000 | 70'000 | 43'000 | |||
| Contingency reserve left | 86'000 minus 70'000 = 16'000 | |||||
| Gap | 16'000 minus 43'000 = minus 27'000 | |||||
| Steering committee decision | Release CHF 27'000 from the management reserve, which falls to CHF 33'000. The cost baseline rises to CHF 1'313'000 through a change request. Total funding stays at CHF 1'346'000. | |||||
The gap comes from the R2 overrun and from R5, which did not exist when the reserve was set.
Visualisations
The reserve status at a single review shows a gap. The sequence of reviews shows how it forms. The reserve falls in steps when a risk occurs. The risk left falls when a risk closes and rises when a risk appears.
In the grants project, R1 closes without occurring at the end of the concept phase. The risk left drops to CHF 68'000 and the reserve stays at CHF 86'000. After the acceptance test, R3 closes without occurring and R5 occurs for CHF 25'000. The reserve left is then CHF 18'000 against a risk left of CHF 10'000. The planned authority decides on the CHF 8'000 surplus.
Reserve left and risk left from one review to the next
Grants project of a cantonal office. Amounts in thousands of CHF
Cost
| Phase | Level | Rationale |
|---|---|---|
| Preparation | Medium | A risk register that quantifies the probability and the impact of each risk. An authority rule written into the risk management plan. |
| Execution | Low | One calculation table per review on the existing register. An optional Monte Carlo simulation requires a full cost model. |
| Documentation | Medium | The reserve line in the cost documentation, the reserve status at each review, the release decisions and the change requests that follow from them. |
Tools
A spreadsheet is enough for the expected monetary value and the reserve status. One sheet per review keeps the history of drawdowns and decisions.
Spreadsheet simulation add-ins (@RISK from Lumivero, Crystal Ball from Oracle) and the risk modules of scheduling tools (Primavera Risk Analysis from Oracle, Safran Risk) size the reserve by simulation. They give the cost or the date at each confidence level.
Scheduling software (Microsoft Project, Primavera P6) carries the time reserve as an activity or a visible buffer in the network. Project financial management systems (SAP Project System, for example) hold the reserve on a separate budget item. Each drawdown leaves an entry there.
Sources
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., §2.3.2.2, §2.3.2.3, §2.4.1 (Reserves, figure 2-25), §2.4.2.2 to §2.4.2.4, §2.4.3.1, §2.7.2.6 and figure 2-53, Section 4 (entries Project funding requirements and Risk management plan), Section 5 (entries Reserve analysis, Earned value analysis, Schedule network analysis, Critical chain project management, Strategies for threats, Strategies for overall project risk), glossary: the definition of reserve analysis and the processes that use it, the contingency reserve and the management reserve, the two budget build-up scenarios, the funding requirements, planned value without the management reserve, schedule reserves, risk acceptance through a reserve, the tailoring cases.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management Reference Manual, 7.4.5.3 Planning in traditional solution development, passage "Planning accuracy over the course of the project": the estimates with their accuracy and their reserves in the project execution order and the project management plan.