Grid of the TECOP categories for the mobile ticket sales of a regional transport company. In the free round, the team names two technical risks and one commercial risk. In the category round, it adds two operational risks and two political risks. Two of these four risks are opportunities. The Environmental category carries the note "examined, no risk".

Prompt List

A prompt list is a predetermined list of risk categories. The project team works through it during risk identification. Under each category, the team looks for the events that could affect the project objectives. The list guides an identification technique such as brainstorming, interviews or a workshop. The PMBOK Guide places it among the tools of the Identify Risks process.

Goal

The PMBOK Guide defines the prompt list as a predetermined list of risk categories. These categories can give rise to individual project risks and can be sources of overall project risk. An individual project risk is an uncertain event or condition. If it occurs, it affects one or more project objectives. Its effect can be negative (a threat) or positive (an opportunity). Overall project risk is the effect of uncertainty on the project as a whole.

According to the PMBOK Guide, the list frames idea generation when the team applies an identification technique. It therefore supplements a brainstorming session, an interview or a workshop. It answers one question: has the identification examined every risk category? Without a list, the participants choose the topics themselves. With a list, the project manager sets them before the session in the risk management plan. Each category becomes an agenda item.

The deliverable is the list adapted to the project. The risk management plan holds it. After each session, the team enters in the risk register the risks found and the category of each. It also notes the categories where nobody found a risk.

Usage

When to use it

  • First risk identification of a project: give the session an agenda that covers each category.
  • Single-discipline group: have the group examine commercial risks, political risks and the other categories outside its own field.
  • Phase change or new information: work through the list again, since risk identification is iterative.
  • Decision to launch, continue or bid: examine the sources of overall risk with PESTLE, TECOP or VUCA.
  • Series of one-to-one interviews: examine the same categories with each person and compare the answers.
  • Organisation without a risk history: the list names categories and needs no data from past projects.
  • Team spread over several sites: the list structures a shared whiteboard with one column per category.

When not to use it

  • Identified risks to sort: risk categorization files them by source, for example with the risk breakdown structure.
  • Issue that has already occurred: an issue is not a risk. Look for its causes with root cause analysis.

Description

A list of categories

Each entry in the list names a category: a source or an area that a risk can come from. "Suppliers", "regulation" and "volatility" are categories. "The supplier delivers the interface late" is a risk. The list contains no risks.

The PMBOK Guide distinguishes two scopes. For individual risks, the team takes the categories at the lowest level of the risk breakdown structure (RBS). For the sources of overall risk, the categories come from strategic frameworks: PESTLE, TECOP and VUCA. An organisation without an RBS can keep a simple list of categories or a structure based on the project objectives.

ListCategoriesScopeSource
Lowest level of the RBSThe leaves of the organisation's or the project's RBSIndividual risksPMBOK Guide
Organisation's own listA simple list of categories or a structure based on the project objectivesIndividual risksPMBOK Guide
PESTLEPolitical, economic, sociocultural, technological, legal, environmentalOverall riskPMBOK Guide
TECOPTechnical, environmental, commercial, operational, politicalOverall riskPMBOK Guide
VUCAVolatility, uncertainty, complexity, ambiguityOverall riskPMBOK Guide
Software risk taxonomyProduct engineering, development environment, program constraintsIndividual risks of a software projectSEI
Categories and scope of the lists that the PMBOK Guide and the SEI name.

The lists other than VUCA name areas. The VUCA categories name properties of the project environment. Under "volatility", the team looks for what can change quickly. Under "ambiguity", it looks for what the stakeholders understand in different ways.

In 1993 the Software Engineering Institute (SEI) published a taxonomy of software project risks. It has three levels: class, element and attribute. A questionnaire asks questions at attribute level. This taxonomy plays the role of a prompt list. Its classes apply to software. For another type of project, the team keeps the SEI's way of running the session and changes the categories.

Prompt list, checklist and categorization

The PMBOK Guide cites the checklist and the prompt list as two separate tools of the Identify Risks process. It places risk categorization in risk analysis, after identification.

 ContentTimingQuestion
Prompt listRisk categoriesBefore and during identificationHas the team searched in each category?
ChecklistSpecific risks that have already occurred in similar projectsDuring identificationDo these known risks threaten this project?
Risk categorizationThe risks already identifiedAfter identificationWhere do the risks come from and where do they concentrate?
PESTLE analysisThe factors of the external environmentBefore a strategic decisionWhich external influences lie outside the organisation's control?
What each tool holds, when the team uses it and which question it answers.

According to the PMBOK Guide, no checklist can be exhaustive: the team also looks for what is not on it. A team that keeps a checklist compares it with the register after the identification session. The comparison shows the known risks that nobody named.

PESTLE is a prompt list with external categories. TECOP mixes internal categories (technical, operational) with external ones (political, environmental). Outside a project, PESTLE analysis scans the organisation's environment and feeds a SWOT analysis.

The International Electrotechnical Commission (IEC) lists checklists, classifications and taxonomies among the risk assessment techniques of its standard IEC 31010:2019. According to its technical committee TC56, they help to identify risks and to group them.

Run the identification with the list

The steps are our synthesis of the PMBOK Guide and of the SEI's session method. The note on categories examined without a risk in step 6 is our proposal.

Risk identification with a prompt list. The facilitator presents the list in the category round that follows the free round. The sort sends the risks to the register and the issues to the issue log. A concern becomes a risk or leaves the process. The team runs the process again when the information changes.1Choose the listrisk management plan2Adapt to theproject and thephase3Free round4Categoryround5Sortbrainstorming, interview or workshopPrompt list6Record in the registerand note the emptycategories7Return when theinformationchangesIssue logDiscardedRiskConcernIssueRewritten as a risk
Risk identification with a prompt list. The facilitator presents the list in the category round that follows the free round. The sort sends the risks to the register and the issues to the issue log. A concern becomes a risk or leaves the process. The team runs the process again when the information changes.
  1. Choose the list during planning. The risk management plan holds the risk categories of the project. The team chooses the list there: the lowest level of the organisation's RBS, PESTLE, TECOP, VUCA or a list of its own. It can combine one list for individual risks with one list for overall risk. A one-line definition per category settles the borderline cases in advance.

  2. Adapt the list to the project and the phase. The SEI adapts its questionnaire to the project and to the stage of the life cycle. A project without a subcontractor removes the questions on subcontracting. The team adds the categories specific to its sector: public procurement for a public authority, data protection for a register that holds personal data. A list copied unchanged from a textbook names none of these sources. Nobody then looks for risks in them.

  3. Let the group speak, then present the list. The team uses the list inside an identification technique. The group first names risks freely. The facilitator then presents the list. The SEI applies this principle to each question: its cues come only after the free answer. The free round extends the principle to the whole list. This extension is our synthesis. The risks of the free round also show where the group looks of its own accord.

  4. Work through the list category by category. In the category round, the facilitator asks an open question for each category: "Which supplier event could delay the project or make it more expensive? Which one could bring it forward or make it cheaper?" Identification covers threats and opportunities. A list worked through for threats alone leaves the opportunities aside. The SEI keeps the session on identification and excludes the search for solutions from it. Every minute spent looking for an answer takes time from the next categories.

  5. Sort the items. According to the PMBOK Guide, identification separates risks from non-risks such as concerns and issues. An issue has already occurred: it goes to the issue log. A concern expresses a worry without a specific event: "the schedule is tight". The team rewrites it as a risk if it can name the uncertain event. Otherwise the team discards it. The SEI gives the second part of the session to clarifying the items: the participants sharpen their wording, file each item under a class and merge the equivalent items.

  6. Record the risks and note the empty categories. The team enters each risk in the register with its category. For each category without a risk, the facilitator or the note-taker enters the note "examined, no risk", the date of the session and the group that examined the category. The note distinguishes an examined category from a forgotten one.

  7. Return to the list when the information changes. The team cannot identify every risk at the outset. Identification therefore continues throughout the project. The team works through the list again at each phase change, at each change of scope and when a new supplier arrives. It first adapts the list to the project and its current phase, then rereads the categories marked "examined, no risk".

Choose the participants and run the session

The SEI draws a few session rules from its field trials. A group has five peers at most. No participant reports to another: the presence of a superior holds subordinates back. The facilitator has no reporting line to any participant, stays neutral and does not judge the answers. A session lasts two and a half hours at most. The remaining categories move to the next session. The SEI has each group start at a different point in the questionnaire so that the time limit does not always cut the same categories.

According to the report, the method brought to light known risks and risks that nobody knew of until then. The SEI bases this finding on feedback from the participants.

Pitfalls

A category entered as a risk. The line "political risk" in the register names neither the event nor the effect. Nobody can rate it or assign a response to it. The team enters the event found under the category.

Two lists that overlap. PESTLE and TECOP both have a political category and an environmental category. A team that works through both finds the same risk twice. The sort in step 5 merges the duplicates.

A complete pass mistaken for a complete identification. A list worked through to the end shows that the group examined each category. It does not show that the group found the risks of each category. A risk that fits under no category signals an incomplete list. The team adds the missing category.

A list never reviewed. The lessons learned from a completed project show the risks that occurred without having been identified. The organisation adds their category to its list.

AI considerations

The PMBOK Guide cites artificial intelligence among the tools of the Identify Risks process. According to the guide, AI can analyse data from past projects and industry benchmarks to identify the risks of a new project.

A language model proposes an adapted list from the project description and its sector. It turns each category into open questions for the facilitator. It reads the exported register and flags the categories that carry neither a risk nor the note "examined, no risk". It spots the duplicates between two combined lists. It rewrites the items of the free round as risk statements.

The risks that the model proposes arrive after the two rounds. If they came earlier, they would steer the group in the same way as a list presented too early. A model that fills an empty category with plausible risks erases the "examined, no risk" signal. The team puts each proposal through the sort in step 5.

According to the PMBOK Guide, AI can carry the biases of its training data. The team checks the AI's output. A generated list repeats the published frameworks. It often omits the categories specific to the sector and to the Swiss context. The register names suppliers and contractual weaknesses: the contract and the non-disclosure agreements decide whether it may go to an external AI service. The Federal Act on Data Protection (FADP) applies to the names of the risk owners. The team removes or pseudonymises them before sending.

Examples

A regional transport company launches ticket sales on mobile phones. The team adapts the TECOP list to the project. An identification workshop then works through it following steps 3 to 6. The risks are fictitious.

CategoryWhat it covers in this projectOpening question
TechnicalThe sales app, its interface with the fare system of the public transport sector and the inspectors' QR code readerWhich part of the technical solution can fail or arrive late? Which part can be delivered earlier or cost less than planned?
EnvironmentalBad weather and rockfalls that interrupt the company's lines. The canton's environmental requirements for ticketingWhich natural event or environmental requirement can hinder or help the project?
CommercialThe contract with the payment provider, the contract with the app supplier and the price of tickets sold on mobile phonesWhich contract, price or supplier can change to the project's disadvantage or advantage?
OperationalDay-to-day ticket sales and inspection: the inspectors, the ticket counters, customer service and mobile network coverage on the linesWhat can hinder or ease day-to-day sales and inspection?
PoliticalThe decisions of the cantonal government and the Grand Council on ticketing, fares and access for passengers without a mobile phoneWhich political decision can impose or support a choice that the project makes?
TECOP list adapted to the mobile ticket sales project.
Free round
Category round
Technical
Fare interface late
Old phones excluded
Nothing added
Environmental
examined, no risk
Commercial
Payment fee rises
Nothing added
Operational
No inspection without network
Shorter inspection by QR code
Political
Sales without phone required
Climate plan subsidy
ThreatOpportunityFictitious risks.
Risks found under each TECOP category for mobile ticket sales. In the free round, the team finds two technical risks and one commercial risk. In the category round, it adds two operational risks and two political risks. The Environmental category carries the note "examined, no risk". Fictitious risks.
CategoryRisk foundTypeRound
TechnicalThe interface with the fare system of the public transport sector could arrive after user acceptance testing (UAT) starts: a delayed launch.ThreatFree
The app could fail to run on mobile phones more than five years old: a share of the passengers excluded from sales.ThreatFree
Environmentalexamined, no risk By category
CommercialThe payment provider could raise its fee per transaction: a higher operating cost.ThreatFree
OperationalIn the side valleys, a gap in the mobile network could stop the inspector from checking tickets: passengers travelling without inspection.ThreatBy category
Inspection by QR code could shorten each check: more passengers checked per trip.OpportunityBy category
PoliticalThe Grand Council could require sales without a mobile phone: an additional sales channel to deliver.ThreatBy category
The canton could subsidise digital ticketing under its climate plan: additional funding for the project.OpportunityBy category
Risks entered in the register after the TECOP workshop on mobile ticket sales. Fictitious risks.

The three risks of the free round are technical or commercial. The category round adds four operational and political risks, including the two opportunities. The Environmental row carries the note "examined, no risk": the register shows that the workshop asked the question.

Visualisations

The list takes the form of a table: one row per category with its definition and its question. A grid shows the result of a session: the categories against the two rounds. An empty category without a note stands out at a glance. In the register, the category column lets the team count the risks per category.

Cost

PhaseLevelJustification
PreparationLowTake the organisation's RBS or a published list and adapt it to the project. Medium when the organisation has no starting list.
ExecutionMediumA category round adds to the free round of each identification session. The SEI limits a session to two and a half hours.
DocumentationLowA category column in the register and the note for the empty categories.

Tools

A whiteboard carries one column per category. A distributed team uses a shared whiteboard such as Miro or Mural. A spreadsheet holds the list with the definition and the question of each category. It also records the categories examined at each session. A tracking tool such as Jira or risk management software carries the category in a field with fixed values. For a software project, the SEI questionnaire provides ready-made questions and probes. The team removes the questions that do not apply to its project.

Sources

  • Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., PMI: the definitions of individual project risk and overall project risk (§2.7.1); the Identify Risks process, its tools, negative and positive risks, the distinction between risks, concerns and issues, iterative identification (§2.7.2.2, Figure 2-49); the definition of the prompt list, its two scopes, PESTLE, TECOP and VUCA (Section 5, entry Prompt lists); the checklist (Section 5, entry Checklists); risk categorization as a tool of risk analysis (§2.7.2.3; Section 5, entry Risk categorization); the risk categories of the risk management plan (Section 4, entry Risk management plan, heading Risk categories); AI in risk identification (§2.7.3, Table X3-1); AI bias and the verification of AI output (Appendix X3).
  • M. J. Carr, S. L. Konda, I. Monarch, F. C. Ulrich and C. F. Walker, Taxonomy-Based Risk Identification, technical report CMU/SEI-93-TR-6, Software Engineering Institute, Carnegie Mellon University, June 1993: the three-level taxonomy, the questionnaire and its probes, tailoring to the project, the two-part session, the lessons from the field trials.
  • IEC, technical committee TC56, Risk assessment standards: checklists, classifications and taxonomies in IEC 31010:2019.
Project Status Report
All techniques
Protection needs analysis