Three-stage diagram. On the left, the sponsor signs the project charter, which is an input to the Plan Resource Management process. In the centre, this process produces the team charter that the team writes. It carries six headings: values, communication, decisions, conflicts, meetings, team agreements. On the right, the team charter is an input to the Lead the Team process. During this process the team reviews the charter, presents it to new members and updates it. A return arrow brings the updated version back to the team charter.

Project Ground Rules

Project ground rules are the behaviours that the members of a project team commit to. The team writes them at the start of the project and adopts them together. The PMBOK Guide calls the document that holds them the team charter: values, communication guidelines, decision-making, conflict resolution, meeting guidelines and team agreements. The same practice goes by other names: team agreements in The Standard for Project Management and working agreements in agile teams. The project charter is a different document. The sponsor signs it to authorise the project. The team charter comes after it: the team writes it to settle how it works.

Goal

Project ground rules are the written list of behaviours that the team expects of its members. A ground rule says what a member does when a question blocks the work, when they dispute a decision or when a meeting starts without an agenda.

They address misunderstandings about how the team works. Each member arrives with the habits of their previous teams. As long as nobody states those habits, everyone takes them for granted and judges the others by rules the others do not know. The PMBOK Guide notes that clear rules accepted early reduce misunderstandings and increase productivity. When members discuss conduct, communication, decision-making and meetings, they discover the values that matter to one another. The guide also lists ground rules among the ways to reduce conflict within the team.

A study by Mathieu and Rapp followed 32 teams of MBA students through a business strategy simulation. The teams that had both a high-quality charter and a sound plan for the task itself sustained the best performance over time.

The technique settles ahead of time the questions that the team would otherwise reopen every time an incident occurs. Who decides a disputed technical choice? Which channel carries an urgent question? What happens when two members disagree? The deliverable is the team charter: one or two pages.

Usage

When to use

  • Forming a project team: write the rules before the first disagreement.
  • A team drawn from several organisations: align the habits of the client, the supplier and the contractors on one way of working.
  • A distributed or hybrid team: set the channels, the availability windows and the response times that a shared office left implicit.
  • A bilingual team: decide the language of meetings, documents and minutes.
  • A new member joins: hand them the written rules rather than let them discover the rules by breaking them.
  • Recurring conflicts about how to work: make explicit the unwritten rule that members disagree about.
  • The team deals directly with stakeholders: set who may promise a deadline and how the promise is recorded.

When not to use

  • A group that meets for a single session: the workshop facilitator sets the session's ground rules at the opening.
  • A question of roles and responsibilities: the charter governs behaviour; the RACI matrix assigns activities.
  • Authority, budget or project boundaries at stake: these questions belong to the project charter, which the sponsor signs.

Description

The headings of the charter

The PMBOK Guide defines the team charter as the document that establishes the team's values, agreements and operating guidelines. It names six headings and leaves the list open.

The headings of the team charter in the PMBOK Guide and what the team sets under each.
HeadingWhat the team sets
Team valuesThe principles to which the team ties its rules: transparency, keeping one's word, work reviewed before delivery.
Communication guidelinesThe channel for each type of message, the expected response time, the working language and the availability windows.
Decision-making criteria and processesWho decides what, by which rule (consent, majority, ruling by the project manager). The decisions that stay within the team and those that leave it through a change request.
Conflict resolution processesThe first step, the time given to the people involved and the escalation when they cannot agree.
Meeting guidelinesThe agenda, punctuality, duration, note-taking and the recording of decisions.
Team agreementsThe other working conventions: focus time, peer review, absences, remote work.

The values justify the rules under the other five headings. The charter states each value together with the behaviour that makes it checkable.

In the same volume as the PMBOK Guide, The Standard for Project Management uses "team agreements" in a broader sense. In its principle Build an Empowered Culture, team agreements are the rules of behaviour and the working norms that the team establishes at the start of the project and that each member commits to uphold. The standard describes the same practice under another name.

Where the charter sits in the project

The PMBOK Guide places the team charter in the Resources performance domain. It is an output of the Plan Resource Management process, which takes the project charter among its inputs. The Lead the Team process then takes it as an input and updates it. In this process the project manager can work with the team on a charter and on operating guidelines to ease communication, problem-solving and consensus-building. For a virtual team, the guide suggests creating a team charter and defining ways of working.

Project charter
Signed by the sponsorAuthorises the project
input
input
Plan Resource Management
output
output
Team charter
Written by the team
  • Values
  • Communication
  • Decisions
  • Conflicts
  • Meetings
  • Team agreements
input
input
Lead the Team
ReviewedPresented to new membersUpdated
Updated version
Updated version
The Plan Resource Management process receives the project charter and produces the team charter. During the Lead the Team process, the team reviews the charter, presents it to new members and updates it.

Ground rules also cover stakeholders. The PMBOK Guide defines ground rules as the behaviour expected of team members and other stakeholders when the team involves them. It lists them among the tools of the Manage Stakeholder Engagement process.

The kick-off meeting often produces the team charter. On the Tuckman ladder, the team writes its charter at the first stage (forming).

The team charter and its neighbours: the question each one settles, who sets it and when.
DocumentQuestion settledWho sets itWhen
Project charterIs the project authorised, with whom, within which limits?The sponsor, by signingAt the start of the project or of a phase
Team charterHow does the team work together?The team itselfWhen the team is formed
Workshop ground rulesHow does the group conduct itself during the session?The facilitatorAt the opening of the session
RACI matrixFor each activity, who is responsible, who is accountable, who is consulted, who is informed?The project manager with the people in the roles concernedDuring planning, then for each new deliverable
Communications management planWho receives which information, in what form and how often?The project managerDuring planning

Who writes the rules

According to the PMBOK Guide, the team charter works best when the team develops it or at least has an opportunity to contribute to it. All team members share responsibility for making sure its rules are followed.

Two forms occur in practice. In the first, the team writes the charter in a session from a blank page structured by the six headings. In the second, the project manager drafts a first version of the rules, presents it to the team and has the team amend it. The second is faster. It holds only if the team can change or withdraw a rule: a charter that the team signs without discussing it has nobody to defend it.

The organisation's staff regulations, its internal data protection directive or its working hours bind the team. The charter cites them without putting them to a vote.

Drawing up the charter

The steps come from practice. They apply what the guide says about the charter's content, its authors and its review. For a team of five to nine people, the session lasts one and a half to two hours.

  1. Prepare. The facilitator (the project manager or a designated member) gathers the rules that the organisation imposes, prepares a board with the six headings and schedules the session within the team's first two weeks.
  2. Start from experience. Heading by heading, each member says what helped and what got in the way in their previous teams. The points that recur become proposed rules.
  3. Write each rule as a behaviour. A rule can be checked: an observer can say whether it was followed yesterday. The facilitator rewords each vague proposal until it passes this test.
  4. Agree how breaches are handled. The team decides how a member flags a broken rule: on the spot, one to one or at the next retrospective.
  5. Adopt. Each member says whether they can work with each rule. The team rewords or withdraws a rule that someone rejects. The team publishes the charter where its members work.
  6. Set the reviews. The team writes into the charter what triggers a review: the end of a phase or of an iteration, a new member joining or a conflict that keeps returning to the same rule.
Vague proposals from the session and the checkable rules written at step 3.
Proposal in the sessionRule written in the charter
"Respect others"Let the person speaking finish. Criticise the deliverable, not its author.
"Share information"A working document goes into the project's shared space. An email gives its link instead of attaching it.
"Pay attention in meetings"In a video call the camera stays on and messaging stays closed.
"Be transparent"Report a delay on the day it becomes known, even without a solution.

Keeping the charter alive

According to the PMBOK Guide, the team can review and update the charter periodically to keep the rules understood and to orient and integrate new members. A ten-minute item in a retrospective is enough to ask which rule the team kept, which one it ignored and which one is missing. A new member receives the charter on the first day. Their question "why this rule?" often points to a rule that has outlived its purpose.

An experience report presented at the Agile Alliance's Agile2019 conference describes working agreements as a living document that the team revisits as it learns. It observes that drawing them up brings to light cultural and logistical problems that nobody had named.

Pitfalls

The first pitfall is the values-only charter. "Respect, trust, excellence" fits on a poster and governs no behaviour. A charter made only of values is never broken because it asks for nothing.

The second is the ready-made charter. The project manager hands out a completed template and the team signs it. The rules the team follows remain the ones nobody wrote down. The project manager becomes the referee of every breach.

The third is the charter that absorbs the project management plan. The PMBOK Guide puts the format, the frequency and the recipients of information in the communications management plan. It also places guidelines for meetings there. A rule that describes a document or a flow of information to stakeholders goes into the plan. A rule that describes how one member behaves towards another stays in the charter.

The fourth is the never-reviewed charter. A rule broken without anyone saying so stops being a rule. After a few weeks the team is back to following unwritten rules. The charter then describes a team that no longer exists. At step 4 the team agrees how a member flags a breach. At step 6 it writes down what triggers a review. These two agreements prevent this drift.

The last is the charter dismissed as superfluous. In an informal culture, writing down rules of conduct looks bureaucratic and the team skips the step. Unwritten rules exist all the same. Such a team starts from the friction its members have already experienced (step 2), keeps the charter to one page and calls it "working agreements".

AI considerations

A language model prepares the session. From the project context (a distributed team, two languages, an external supplier) it proposes questions to put to the team and draft rules to discuss under each heading. During or after the session, it applies the test of step 3 to turn the vague proposals noted on the board into checkable rules. It reviews an existing charter and flags empty headings, rules that describe no behaviour and rules that describe a document. For a bilingual team it translates the charter into the team's second language. A member who speaks that language natively reviews the translation before publication.

The model does not replace the discussion. The charter has value because the members stated their expectations in front of the others and accepted each rule. A charter generated and then adopted without debate falls into the ready-made charter pitfall. The model also knows nothing of the tensions that the team does not put in writing. Retrospective notes and conflict records contain names and judgements about colleagues: they go only to a tool that the organisation has approved.

Examples

A team of eight is replacing the case management software of a bilingual cantonal office. Three members work for the supplier in Zurich.

Team charter for the replacement of the case management software. The eight members adopted it in a session in week 2.
HeadingRule
ValuesTransparency: a problem is reported on the day someone sees it, even without a solution. Keeping one's word: a promise made in a meeting is kept or renegotiated before it falls due.
CommunicationA question that blocks the work goes through the project's Teams channel and gets an answer within half a working day. Core hours from Monday to Thursday: 9:00 to 11:30 and 13:30 to 16:00.
CommunicationIn meetings each person speaks French or German as they prefer. The minutes record the decisions in both languages.
DecisionsA technical choice that affects more than one module is made in the meeting by consent: it passes if nobody raises a reasoned objection. Without consent, the project manager decides within 48 hours. A change of scope or deadline goes to the steering committee as a change request.
ConflictsA disagreement is handled first between the people involved. After a week without agreement, either of them refers it to the project manager.
MeetingsThe agenda goes out by noon the day before. Without an agenda the meeting does not take place. Each decision goes into the decision log before the meeting ends.
Team agreementsTuesday morning is meeting-free. A second member reviews every configuration change before it goes into testing.
StakeholdersOnly the project manager and the business analyst promise a deadline to the business department. A promised deadline goes into the decision log the same day.
ReviewTen minutes at each end-of-iteration retrospective. A full reading when a member joins and at the end-of-design milestone.

The Stakeholders and Review rows add to the six headings of the PMBOK Guide. The team added the first because the three supplier members spoke directly to the business department.

Visualisations

One figure follows the team charter through the project. Its return arrow brings the updated version back to the team charter: the project charter stays outside the loop. The headings of the charter, its neighbours, the rewriting of vague proposals into checkable rules and the completed charter are tables.

Cost

PhaseLevelJustification
PreparationLowGathering the rules that the organisation imposes and preparing a board with six headings takes an hour or two.
ExecutionMediumOne session of one and a half to two hours with the whole team, that is twelve to sixteen hours of work for eight people.
DocumentationLowOne or two pages, reviewed for ten minutes at each retrospective and in full when a member joins.

Tooling

A physical or shared whiteboard (Miro, Mural) carries the session: one column per heading, the proposals on sticky notes and the adopted rules rewritten as a clean copy.

The adopted charter lives where the team works every day: a wiki page (Confluence, SharePoint), a pinned message in the team channel (Teams, Slack) or a page of the project dashboard. The version history of these tools shows which rule changed and when.

A document template with the six headings speeds up preparation. A facilitator who fills it in ahead of time reproduces the ready-made charter.

Sources

  • Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition, PMI: the team charter as an output of the Plan Resource Management process, which receives the project charter as an input (§2.6.2.1, Figure 2-41); the charter as an input and updated output of the Lead the Team process and the project manager's work with the team on the charter and the operating guidelines (§2.6.2.4, Figure 2-44); the team charter suggested for a virtual team (§2.6.3.1); ground rules among the tools of the Manage Stakeholder Engagement process (§2.5.2.4); the team agreements of the Build an Empowered Culture principle (The Standard for Project Management, §3.8.1); the definition of the team charter, its six headings, its development by the team, the shared responsibility and its review (Section 4, entry "Team charter"); the definition of the project charter (Section 4, entry "Project charter"); the definition of ground rules and their effect on conflict (Section 5, entries "Ground rules" and "Conflict management").
  • J. E. Mathieu, T. L. Rapp, "Laying the foundation for successful team performance trajectories: The roles of team charters and performance strategies", Journal of Applied Psychology, 94(1), 2009, pp. 90-103: the study of 32 teams of MBA students and the joint effect of a high-quality charter and a sound plan for the task on performance over time.
  • A. Kanaan, Stop Spinning Your Team's Wheels: It's Time To Revisit Your Working Agreements, experience report, Agile2019, Agile Alliance: working agreements as a living document that the team revisits as it learns.
Project Charter
All techniques
Project Status Report