Your Training Partner
Techniques Toolbox
Two bell curves of equal width and with a standard deviation of 5 µm lie between the specification limits −30 and +30 µm. On the left, the mean sits at the centre of the tolerance: Cp 2.00 and Cpk 2.00. On the right, the mean is at +10 µm. The 60 µm tolerance still holds 6σ twice: Cp 2.00. Between the mean and the upper limit, 20 µm hold 3σ 1.33 times: Cpk 1.33.

Process capability

Process capability measures the ability of a stable process to produce within the tolerance that the customer sets. It compares the width of the tolerance with the natural spread of the process, which equals six standard deviations: this is the Cp index. The Cpk index divides the distance between the mean and the nearer limit by three standard deviations: it takes centring into account. The study assumes a process in statistical control and normally distributed data. The control chart checks stability. The histogram and the normal probability plot check normality.

Goal

A capability study tells whether a stable process meets the customer's tolerance and measures its margin. NIST defines it this way: it compares the output of an in-control process with the specification limits using capability indices. A process is capable when almost all its measurements fall between the limits.

The technique answers a question that the control chart leaves open. The chart tells whether the process is predictable: it compares the values of the process with the limits that the process itself produced. The capability study compares the process with the limits that the customer, the contract or the technical drawing imposes. A process can be stable and produce out of tolerance.

The study supports a decision: deliver, adjust the process or reduce its spread. Its report states the characteristic, its limits, the sample size, the evidence of stability, the distribution check, the indices and their confidence interval.

Usage

When to use it

  • New machine or new process: show before series production that the output will meet the tolerance.
  • Customer requirement: the contract or the sector sets a minimum Cpk that the supplier must demonstrate.
  • Measure phase of a DMAIC: quantify the baseline performance against the customer's limit.
  • Before and after an improvement: show whether the spread has dropped or the centring has changed.
  • Choice between two machines or two suppliers: compare their indices on the same characteristic and the same tolerance.
  • Service lead time under a contractual limit: the one-sided index Cpu compares the lead time with its upper limit alone.
  • Critical characteristic under monitoring: recalculate the index at the frequency that the control plan sets.

When not to use it

  • Unstable process: the chart shows special causes. Stabilise the process on the control chart first.
  • No specification limit: the index has nothing to compare with. Track the variation on a control chart.
  • Conforming or nonconforming result: Cp and Cpk need a continuous measurement. Track the proportion of defects on an attributes chart.

Description

The elements

The characteristic is the quantity measured: a diameter, a weight, a processing time. The specification limits bound the values that the customer accepts. The lower specification limit is written LSL. The upper specification limit is written USL. The gap between them is the tolerance. A target value T is added when the customer sets one. It often coincides with the middle of the tolerance.

The process has a mean μ and a standard deviation σ. Its natural spread equals 6σ: three standard deviations on either side of the mean. For a normal distribution, this range contains 99.73% of the values. NIST estimates μ by the sample mean x̄ and σ by the sample standard deviation s.

The indices

IndexWhat it comparesFormula
CpThe width of the tolerance relative to six standard deviations(USL − LSL) / (6s)
CpuThe distance from the mean to the upper limit relative to three standard deviations(USL − x̄) / (3s)
CplThe distance from the lower limit to the mean relative to three standard deviations(x̄ − LSL) / (3s)
CpkThe smaller of the two: the side of the nearer limitmin(Cpu, Cpl) = Cp × (1 − k)
CpmThe tolerance relative to the spread around the target T(USL − LSL) / (6√(s² + (x̄ − T)²))
The capability indices according to NIST: what each one compares and its formula. x̄ and s are the sample mean and the sample standard deviation.

Cp ignores where the mean lies. It states what the process would achieve if it were centred. That is its potential. Cpk takes the limit nearer to the mean. The factor k measures how far the process is off centre: it divides the distance between the mean and the middle of the tolerance by half the tolerance. It equals 0 for a centred process and 1 when the mean reaches a limit. Cpk is therefore at most Cp. Cpk equals Cp for a centred process.

Cp and Cpk by centring
The mean moves by 10 µm and the standard deviation stays at 5 µm
Centred process
−30−20−100+10+20+30LSL −30USL +30tolerance 60 µmx̄ = 06σ = 30 µmdeviation from nominal size (µm)
Cp = 60 / 30 = 2.00
Cpk = 2.00
Off-centre process
−30−20−100+10+20+30LSL −30USL +30tolerance 60 µmx̄ = +1020 µm = 3σ × Cpk6σ = 30 µmdeviation from nominal size (µm)
Cp = 60 / 30 = 2.00
Cpk = 20 / 15 = 1.33
Both processes have the same standard deviation of 5 µm between the limits −30 and +30 µm. Cp stays at 2.00 when the mean moves to +10 µm. Cpk falls to 1.33: between the mean and the upper limit only 20 µm remain. That is 1.33 times three standard deviations.

Cpm penalises the distance from the target. A process with little spread but far from T gets a high Cpk and a low Cpm. The index applies when each deviation from the target costs the customer even inside the limits.

A one-sided specification has only one limit. A processing time has an upper limit and no useful lower limit. Cp does not exist in that case: the study calculates Cpu alone. A minimum strength has only a lower limit and gives Cpl alone.

Tolerance (USL − LSL)CpRejectsShare of the tolerance used
6σ1.000.27%100%
8σ1.3364 ppm75%
10σ1.660.6 ppm60%
12σ2.002 ppb50%
The NIST table of Cp against the proportion of rejects for a centred process with a normal distribution. ppm: parts per million. ppb: parts per billion.

These rejects assume a centred process. An off-centre process produces more rejects for the same Cp: the proportion out of tolerance then depends mainly on Cpk.

The ISO 22514-2 standard

The ISO 22514-2 standard covers the capability and performance of processes. It describes their calculation in particular for a process that does not stay in statistical control. It classifies the results into eight distribution types and applies only to continuous characteristics.

Running the study

The order of a capability study
The study checks stability and distribution before it calculates the indices
Characteristic, LSL, USL, target · measurement system checked
Sampling in subgroups in time order (at least 100 values)
Control chart: process stable?
Remove the special causes, then sample again
Histogram and normal probability plot: normal distribution?
Transform the data (Box-Cox) or calculate non-parametric indices
Calculate Cp, Cpk and the confidence interval of Cpk
Compare the lower bound with the customer's requirement
The study checks stability on the control chart, then the distribution. The team removes the special causes of an unstable process. It transforms non-normal data or calculates non-parametric indices.
  1. Set the characteristic and its limits. Take LSL, USL and the target from the drawing or the contract, with their unit. Check the measurement system before measuring: an instrument with too much spread inflates s and lowers the indices.
  2. Sample in time order. Take subgroups of a few consecutive parts at regular intervals. The subgroups cover the shifts, the material batches and the settings that production will see. NIST generally asks for at least 100 values for a capability study.
  3. Plot the control chart. With no signal, the process is stable and the study continues. With a special cause, the team finds and removes it. Then it samples again.
  4. Check the distribution. Plot the histogram and the normal probability plot. Points that fall on a straight line indicate a normal distribution. If the data depart from it, NIST first recommends the Box-Cox transformation when it succeeds. Failing that, it proposes non-parametric indices. These indices replace the mean with the median. They replace 6s with the gap between the 0.135% and 99.865% percentiles of the data.
  5. Calculate x̄, s, then the indices. Calculate Cp, Cpu, Cpl and Cpk. Add Cpm if the customer sets a target.
  6. Calculate the confidence interval of Cpk. Keep its lower bound.
  7. Read the pair and decide. Compare Cp and Cpk with each other, then the lower bound with the customer's requirement.
  8. Write the report. It states n, the period, the evidence of stability and the distribution check next to the indices. It names the standard or the manual that defines the indices calculated.

Reading the Cp and Cpk pair

The gap between the two indices separates a centring problem from a spread problem.

CpCpkDiagnosisAction
Meets the requirementMeets the requirementCapable processMonitor on the control chart
Meets the requirementBelow the requirementCentring problemMove the mean to the middle of the tolerance
Below the requirementBelow the requirementSpread problemReduce the variation, then centre the mean
Reading the Cp and Cpk pair against the customer's requirement: the diagnosis and the action.

The case of a low Cp with a high Cpk does not exist: Cpk never exceeds Cp. An adjustment raises Cpk only up to Cp. Beyond that, only a lower spread raises both indices.

An index is an estimate

According to NIST, the indices are random variables with variation that is not negligible. Two samples from the same process give two different Cpk values. NIST gives a common approximation of the confidence interval of Cpk. It holds from 25 values upward:

Cpk ± z × √(1 / (9n) + Cpk² / (2(n − 1)))

For a two-sided 95% interval, z equals 1.96. A Cpk estimated at 1.33 on 125 values lies between 1.16 and 1.51. On 30 values, the same Cpk lies between 0.97 and 1.70. With 30 parts, the lower bound falls below 1: the study does not guarantee three standard deviations between the mean and the nearer limit. The report therefore gives n and the interval. The decision rests on the lower bound.

The confidence interval of Cpk by n
The same Cpk of 1.33 estimated on 30 to 200 values
n = 30
0.97 to 1.70
n = 50
1.05 to 1.61
n = 100
1.14 to 1.53
n = 125
1.16 to 1.51
n = 200
1.19 to 1.47
1.00 3σ to the nearer limit1.20 requirement in the example contract
Two-sided 95% interval of a Cpk estimated at 1.33, by sample size. The lower bound rises from 0.97 on 30 values to 1.19 on 200 values. It stays below the contract requirement of 1.20 in the example.

Common mistakes

Calculating a Cpk without a control chart. A process that drifts during sampling gives a mean and a standard deviation that describe none of its states. The index predicts nothing about the next production run.

Applying the formulas to skewed data. A processing time has a long upper tail and cannot fall below zero. The formulas based on the normal distribution assume two symmetric tails. The calculated Cpu no longer reflects the proportion of overruns. The study transforms the data or switches to non-parametric indices.

Mixing sources. Two machines, two cavities of a mould or two shifts in one sample give a histogram with two peaks. The standard deviation mixes the gap between the sources with the spread of each. The study separates the sources and calculates an index for each.

Quoting a minimum value without a source. A value taken from an internal manual or a shop-floor habit does not bind the customer. The requirement comes from the contract, the drawing or the sector's reference standard. The report cites it.

AI considerations

An assistant writes the spreadsheet formulas or the Python script that calculates x̄, s, the indices and the confidence interval. The analyst checks that the script takes the minimum of Cpu and Cpl, reads the limits in the right unit and calculates Cp on the whole tolerance. The analyst also checks two identities that NIST gives: Cp = (Cpu + Cpl) / 2 and Cpk = Cp × (1 − k). A script that violates them has an error.

A language model given measurements pasted into the conversation can return a wrong standard deviation without flagging it. The analyst calculates in the spreadsheet or in code.

The model tends to quote a minimum Cpk value as a general rule. It does not know what the customer's contract requires.

The model calculates a Cpk on any column of figures. It sees neither the drift nor the mixing of two machines. The analyst plots the control chart and the histogram before the calculation.

The customer's contract may classify the measurements as confidential: the analyst checks this before handing them to an external AI service.

Examples

A subcontractor in the canton of Vaud machines bushings. The characteristic is the inner diameter: 12.00 mm ±0.03 mm.

ItemValue
CharacteristicInner diameter of the bushing
LimitsLSL 11.970 mm · USL 12.030 mm · target 12.000 mm
Sample25 subgroups of 5 bushings · hourly sampling across three shifts · n = 125
StabilityX̄-S chart: no point outside the limits, no pattern
DistributionBell-shaped histogram · points on a straight line on the normal probability plot
Mean and standard deviationx̄ = 12.010 mm · s = 0.005 mm
Cp0.060 / (6 × 0.005) = 2.00
Cpu(12.030 − 12.010) / (3 × 0.005) = 1.33
Cpl(12.010 − 11.970) / (3 × 0.005) = 2.67
Cpkmin(1.33, 2.67) = 1.33 · two-sided 95% interval: 1.16 to 1.51
Customer requirementLower bound of Cpk ≥ 1.20 (contract, quality annex)
DecisionCapability not demonstrated: lower bound 1.16 < 1.20
DiagnosisCentring: mean 0.010 mm above the target
ActionSet the tool to 12.000 mm, then repeat the study. Expected Cpk: 2.00 if s does not change
Capability study report for the inner diameter of 125 bushings of 12.00 mm ±0.03 mm: Cp 2.00, Cpk 1.33, two-sided 95% confidence interval of Cpk from 1.16 to 1.51. The lower bound stays below the contract requirement of 1.20: capability is not demonstrated.

The estimated Cpk exceeds the requirement. Its lower bound stays below it: the study does not demonstrate capability. Once centred, the same process would give a Cpk of 2.00 with a lower bound of 1.74 on 125 values.

Visualisations

The first diagram shows the same bell curve centred and then off centre between the same limits: Cp does not change, Cpk drops. The second shows the order of the study and its exits: stability, distribution, then indices. The third shows that the confidence interval of a Cpk of 1.33 narrows as n grows. The formulas, the rejects, the interpretation of Cp and Cpk, the report and the cost are made of rows and columns. So they are tables.

Cost

DimensionLevelJustification
PreparationMediumThe limits come from the contract. The team checks the measurement system and sets the sampling plan.
ExecutionMediumAt least 100 measurements across several shifts, a control chart and a distribution check before the calculation.
DocumentationLowA one-page report. The team redoes it after each change to the process.

Tooling

A spreadsheet is enough for a simple study: a column of measurements, the mean and standard deviation functions, a few cells for the indices and the interval. The control chart and the histogram fit in the same workbook.

Minitab and JMP chain the control chart, the normality test, the indices and their confidence interval in a single report. They also offer transformations and indices for non-normal data. They suit a team that tracks many characteristics or works for a customer who imposes a report format. In R, the qcc package calculates the indices. In Python, scipy and matplotlib handle the calculation and the charts.

Sources

  • NIST/SEMATECH, e-Handbook of Statistical Methods, §6.1.6 "What is Process Capability?": the definition, the formulas for Cp, Cpk, Cpm, Cpu and Cpl and their estimators, the factor k, the translation of Cp into rejects, the sample size, the confidence interval of Cpk and the routes for non-normal data.
  • NIST/SEMATECH, e-Handbook of Statistical Methods, §1.3.3.21 "Normal Probability Plot": the normal probability plot as a check of normality.
  • ISO, ISO 22514-2:2026, Statistical methods in process management, Capability and performance, Part 2: Process capability and performance of time-dependent process models: capability and performance on continuous characteristics, in particular for processes that do not stay in statistical control.
Process Analysis
All techniques
Process Classification Frameworks and Reference Models