Two trees for an insurer whose business teams bypass the request intake tool. On the left, the problem tree: the focal problem in the middle, three direct causes and their causes below, three direct effects and one second-level effect above. On the right, the objectives tree: the same cards reworded as desired situations, the causes turned into means and the effects into ends. One means card is deleted. Three braces mark the means branches that can become the project.

Problem Tree Analysis

Problem tree analysis is a group analysis technique from the logical framework approach, which development cooperation uses to plan its projects. A group places a focal problem in the middle of the board. It puts the direct causes below the problem and the direct effects above it, then develops each level the same way. It then rewrites each card as a desired situation. The causes become means and the effects become ends. The problem tree becomes an objectives tree, on which the group chooses the branch the project will address.

Purpose

A problem tree is a cause-and-effect diagram that a group builds around a single problem. The group then turns it into an objectives tree, which describes the desired situation with the same structure.

The group first decides on the diagnosis: it agrees on a focal problem and on the links that explain it. It then decides on the plan: it picks the branch of the objectives tree that the project will address. According to the European Commission's 1993 manual, the exercise draws its value from the shared picture of reality that participants build as they compare their perceptions.

The deliverable is two diagrams and a set of notes. The problem tree carries the focal problem with its causes and effects over several levels. The objectives tree carries the same cards reworded as desired situations and linked from means to end. The notes collect the solutions, concerns and decisions that come up in the discussion.

Usage

When to use it

  • Broad problem shared by several stakeholders: build a common view of the causes before proposing a project.
  • Scoping a project or programme: move from the diagnosis to the objectives, then to the choice of a strategy.
  • Request phrased as a solution: take "we need a new tool" back to the negative state the tool should correct.
  • Disagreement on what to address first: make the cause-and-effect links visible before the trade-off.
  • Little data available: the tree starts from what the participants know and points to the causes to verify afterwards.
  • Preparing a logical framework: the objectives tree supplies the intervention logic of the matrix.

When not to use it

  • Measured effect whose cause must be proven: the tree collects perceived causes; test the causes with the methods of root cause analysis.
  • Options already formulated without a cause analysis: compare them directly in a decision matrix.

Description

The elements of the tree

Each element sits on a card that describes one problem in one sentence. The focal problem takes the middle of the board. The causes go below it: first the direct causes of the focal problem side by side, then the causes of those causes. The effects go above it on the same principle. An arrow runs from cause to effect, so from bottom to top.

The toolkit of the Overseas Development Institute (ODI) describes the tree by its trunk, roots and branches. The trunk carries the focal problem. The roots carry the causes and the branches carry the effects. The handbook of the Norwegian development agency (NORAD) already speaks of a problem tree without naming a trunk or roots. The European manual of 1993 speaks of a problems diagram. The two vocabularies name one technique.

The objectives tree keeps the layout of the problem tree. Each card in it describes a desired situation. The bottom cards become means and the top cards become ends. The reworded focal problem stays in the middle of the board.

Where the technique comes from

The logical framework originated at the US development agency USAID in 1969 and 1970. Around 1980 the German agency GTZ added a workshop procedure called ZOPP (Zielorientierte Projektplanung: objectives-oriented project planning). ZOPP runs through the analysis of participants, the problem tree, the objectives tree, the analysis of options and the project matrix. In the early 1990s NORAD, the Danish agency DANIDA and the European Community applied versions of it. The tree therefore belongs to the analysis phase that precedes the matrix. The method also applies to a project in a company or a public administration.

Writing the cards

According to the NORAD handbook, a card describes a problem that exists, not a possible, imagined or future one. A problem is an existing negative state, never the absence of a solution. A card carries one problem. The handbook illustrates the rule with a crop: "no pesticide is available" is wrong, "the crop is infested with pests" is right.

RuleCard to rewordCorrect card
An existing negative state, never the absence of a solution"No request tracking tool""Requests get lost between two departments"
A problem that exists today"The business units may abandon the tool""Business teams bypass the tool"
One problem per card"Form too long and slow answers""The form requires technical fields" on one card, "Submitted requests wait for weeks" on another
A specific card rather than a general statement"The request process works badly""Triage happens only at the monthly committee" on one card, "Developers accept direct requests" on another
The rules for writing a card, with a card to reword and its correct form for each rule.

A card that starts with "lack of" or "absence of" already contains its solution. "Lack of training" calls for a training course before the group has seen that users never open the existing module. The card "users do not know how to enter an urgent request" leaves several answers open.

Running the workshop

  1. Frame the subject and the participants. The group sets the boundaries of the subject and names the parties concerned. NORAD runs a stakeholder analysis before the tree. ODI recommends a group of six to eight people, a flipchart and cards. According to the European manual, the diagram is more useful when a moderator who knows group dynamics leads the session. If the group does not agree on the question itself, problem shaping and reframing comes first.
  2. Choose the focal problem. Each participant writes a proposal. The group discusses each proposal and looks for agreement. If the group cannot agree, NORAD has it arrange the proposals in a tree by their cause-and-effect links. The group then tries again to agree on the focal problem on the basis of this overview. If the disagreement persists, the group allocates points, for example by dot voting. It can also adopt one problem provisionally and come back to the others later. The handbook advises against a formal majority vote. ODI adds that the wording can stay approximate: the roots and branches will refine it.
  3. Build the tree. Participants write the cards alone or in pairs. The moderator places the main direct causes side by side under the focal problem and the main direct effects on the row above. The group then develops each cause downwards and each effect upwards. The cards change place as the discussion moves on. The moderator moves a card provisionally when a participant asks. A final move needs the agreement of all participants. The group replaces a card that states a general observation with several specific cards. Ideas that come up go on separate sheets headed solutions, concerns and decisions. The analysis stops when the participants judge that the tree explains the main cause-and-effect relationships.
  4. Review the tree. The group checks that the tree is valid and complete, then adjusts it. ODI suggests questions for this review. Does the tree match reality? Does it cover the economic, political and sociocultural dimensions? Which causes are getting worse? Which effects weigh most? Which causes are the easiest or the hardest to address?

Turning the problem tree into an objectives tree

NORAD runs the conversion in two passes. The first pass starts at the top of the tree and rewords each card as a desired situation. The focal problem becomes an objective. Its card no longer stands out from the others on the board. When a card resists rewording, NORAD advises clarifying the problem card first. The European manual gives the example of "low agricultural production", which becomes "increased agricultural production".

The second pass starts at the bottom and checks each link. For each card the group verifies that the means on the level below are enough to reach the end on the level above. The cause-and-effect link "if cause A, then effect B" must become a means-end link: "means X in order to achieve end Y". NORAD warns that this pass depends on the rewording. When a rewording makes no sense, the group writes a replacement objective or leaves the problem card as it is. It deletes unrealistic or unnecessary objectives. It adds the ones that are missing. The European manual rewords "too many mosquitoes" as "fewer mosquitoes". If that objective is out of reach, the replacement objective can be "increased resistance of the population". Finally the group draws the means-end links.

Choosing the branch

The group then circles the means branches that could become a project and names them, for example "training option" or "income option". It sets aside objectives that are undesirable, out of reach or already pursued by another project. It returns to the stakeholder analysis of the first step and discusses each option in terms of the groups it affects. NORAD compares the remaining options on total cost, benefits to priority groups, probability of achieving the objectives and social risks. The group can add technical, financial, institutional or environmental criteria. A rough rating per criterion is enough (high or low). Without agreement, the group adds criteria or modifies the most promising option: it adds elements of the objectives tree to the option or removes some. A multi-criteria decision analysis takes over when the comparison must be weighted and justified.

The chosen branch supplies the intervention logic of the logical framework. ODI proposes force field analysis as the next step to weigh what drives the change and what holds it back. A desired situation still has to be quantified. SMART objectives give it a measure and a deadline.

The limits of the tree

The causes in the tree are perceived causes. The European manual provides for technical, economic or social studies that add to the group's analysis. When a decision rests on a cause, the team verifies that cause before it funds the branch that depends on it. Root cause analysis supplies the methods for this verification.

A tree is often a web. Des Gasper observes that almost every problem tree is a web because of crosscutting effects and feedback loops. A card that feeds two branches goes on the board once with its two arrows. A duplicate hides the link. The single focal problem narrows the project. A project that aims at a quick result and a deep reform at once fits badly into one means-end chain. Gasper also notes that the means-end chain has no explicit time dimension. It renders slow or recursive links poorly.

The tree describes a moment. The European manual points out that the analysis holds at the time the group carries it out. The group adapts it when the situation changes. A team that treats the tree as a fixed plan misreads the method.

The workshop can become too heavy. The method requires training and the buy-in of the participants. The effort scales with the size of the decision. NORAD describes two formats. The simpler one is a short internal exercise. A full workshop brings all parties together for 6 to 12 days. At the identification stage NORAD also cites a mini-workshop of 3 to 4 hours with 2 or 3 decision-makers. These durations apply to the whole logical framework workshop, which runs from the stakeholder analysis to the matrix.

Participants keep quiet about causes that involve their management. Gasper cites ZOPP workshops where the most powerful participants dominated the discussion. The moderator sometimes dominated as well. NORAD recommends a moderator who is independent of the parties. The moderator sticks to the method and stays out of the debate on substance. Cards that each person writes alone and that the moderator collects without names reduce this self-censorship.

The problem tree and its neighbours

TechniqueSorts the causesEffectsProduces
Fishbone diagramBy categoryA single effect at the head of the diagramCandidate causes that the data decide between
Five whysIn a single chainThe starting problemA correctable cause at the end of a chain with evidence behind each link
Problem treeBy level: direct causes, then causes of those causesSeveral levels above the focal problemAn objectives tree and the choice of a strategy
The problem tree compared with the fishbone diagram and the five whys: what each technique sorts, what it shows of the effects and what it produces.

Only the problem tree turns into a project plan. The CTQ tree works down from a customer statement to measurable requirements. A3 problem solving and 8D problem solving carry a problem statement and a root cause step. A problem tree can feed either of them.

AI considerations

A conversational assistant speeds up the work on the cards. It sorts interview notes or a department's tickets into candidate cards of one problem each. It flags the cards that describe the absence of a solution or that carry two problems. After the workshop it transcribes the photo of the flipchart into a structured list. It proposes a positive rewording for each card. The group then checks the means-end link. The assistant also spots cards attached to two branches, which signal a web.

The assistant does not replace the workshop. A generated tree produces plausible causes that nobody in the room has seen or experienced. It also removes the discussion that gives the technique its value. A cause that a model judges probable remains a cause to verify. The cards often name departments and internal failures. Cards that name them are confidential and stay out of a consumer AI assistant.

Examples

In an invented example, the IT department of an insurer in French-speaking Switzerland finds that the business teams bypass the request intake tool. The group builds the problem tree, then turns it into an objectives tree.

Effects
Deadlines promised to the business units are missed
Developers are interrupted mid-task
The committee prioritises from an incomplete list
Requests get lost between two departments
Focal problem
Business teams bypass the request intake tool
Causes
The form requires technical fields
The form reuses the incident ticket
Submitted requests wait for weeks
Triage happens only at the monthly committee
Developers accept direct requests
Business managers have a say in the developers' annual appraisal
Reword as desired situations
Ends
Deadlines promised to the business units are met
Developers work on planned requests
The committee prioritises from the complete list
Each request is tracked until it is closed
Reworded focal problem
Business teams enter their requests in the tool
Means
The form asks only for business fields
The business form is separate from the incident ticket
Submitted requests get an answer within the week
A weekly triage handles incoming requests
Developers redirect direct requests to the tool
Card deleted
Form option
Triage option
Redirect option
On the left, the insurer's problem tree. On the right, its objectives tree. Each card keeps its place and becomes a desired situation. One means card is deleted. Three braces mark the means branches that can become the project. Invented example.

Most cards can be reworded directly. Two cards need a decision from the group.

Problem tree cardObjectives tree cardGroup decision
Business teams bypass the request intake toolBusiness teams enter their requests in the toolReworded. The card no longer stands out on the board.
The form requires technical fieldsThe form asks only for business fieldsReworded
Triage happens only at the monthly committeeA weekly triage handles incoming requestsReplaced. The literal rewording does not say which triage replaces the committee. The group writes a replacement objective (NORAD, p. 36).
Business managers have a say in the developers' annual appraisalNoneDeleted. Executive management sets the developers' appraisal. The IT department's project cannot change it. The group deletes an unrealistic objective (NORAD, p. 37).
Four cards from the insurer's problem tree, their card in the objectives tree and the group's decision. Invented example.

The deleted card applies NORAD's rule: the group deletes an unrealistic or unnecessary objective.

OptionTotal costBenefits to priority groupsProbability of achieving the objectivesSocial risks
Form optionhighhighhighlow
Triage optionlowhighhighlow
Redirect optionlowlowlowhigh
The form, triage and redirect options of the insurer example, rated high or low on NORAD's four criteria. The group chooses the triage option: it matches the form option on three criteria and costs less. Invented example.

Visualisations

The group draws the cause-and-effect arrows at the end of the session, when the cards no longer move.

The objectives tree keeps each box in the same place. The reader compares each problem card with its rewording. A deleted card leaves an empty dashed box that keeps the deletion visible. A named brace marks each branch that the group retains as an option.

Cost

PhaseLevelRationale
PreparationMediumDefine the subject, identify the parties concerned and gather six to eight people who voice the viewpoints of these parties. The materials come down to cards and a large board.
ExecutionMediumAccording to NORAD, a mini-workshop lasts 3 to 4 hours with 2 or 3 decision-makers. A full workshop brings all parties together for 6 to 12 days. Both durations apply to the whole logical framework workshop. The tree is one step of it. Disagreement on the focal problem lengthens the workshop.
DocumentationLowCopy out the two trees and the side notes. Update the tree when the situation changes.

Tools

The original medium remains the most direct: a flipchart or a wall, with cards or sticky notes. The cards move during the discussion, which rules out writing straight onto the sheet. A distributed team works on a collaborative whiteboard (Miro, Mural, FigJam) with one note per card. The whiteboard keeps the tree editable after the workshop.

For the clean version, a diagramming tool (diagrams.net, Visio) draws the boxes and the arrows. A spreadsheet links each problem card to its objective card and to the decision taken. This table records the conversion when the objectives tree feeds a logical framework.

Sources

  • NORAD (1999), The Logical Framework Approach (LFA): Handbook for objectives-oriented planning, 4th ed., ISBN 82-7548-170-8: the workshop and the visualisation rules (pp. 17-19), steps 2 to 4 (pp. 30-41) and the mini-workshop of the identification phase (p. 78). Steps 2 to 4 give the rules for writing cards, the choice of the focal problem, the construction of the tree, its conversion into an objectives tree and the choice of strategy.
  • Commission of the European Communities, Evaluation Unit (1993), Project Cycle Management: Integrated Approach and Logical Framework, manual: chapter 4 of part one describes the limits of the method (p. 15). Sections 1.1 to 1.4 of the situation analysis cover the analysis of problems, objectives and strategies.
  • Hovland, I. (2005), Successful Communication: A Toolkit for Researchers and Civil Society Organisations, Overseas Development Institute, §3 Problem Tree Analysis: the image of the trunk, roots and branches, the group size and the review questions. The NORAD and European Commission manuals carry the planning method.
  • Gasper, D. (2000), Logical Frameworks: Problems and Potentials, working paper, Institute of Social Studies, The Hague: section 2 traces the history of the logical framework and assesses ZOPP. Section 3 shows the tree that becomes a web and the missing time dimension. Section 5 describes the workshops that the most powerful participants dominated.
Problem shaping and reframing