Phase Gate
A phase gate is the formal decision that closes a project phase and authorises the next one. HERMES calls it phase release. The project manager prepares it by planning the next phase and writing the phase report. The project sponsor examines this dossier and then accepts or rejects the phase outcomes. On acceptance, the sponsor releases the next phase and its resources. HERMES describes its milestones as quality gates. The PMBOK Guide uses the term phase gate. In HERMES, the German name is Phasenfreigabe and the French name is libération de la phase.
Goal
A phase gate is the decision that moves a project from one phase to the next. At the end of a phase, the project sponsor decides whether to release the next phase with its resources: finances, staff, infrastructure.
HERMES is the project management method of the Swiss Confederation. It places a milestone at the start and at the end of each phase. According to the reference manual, these milestones are the points where outcomes and the way forward are decided. At the release, the sponsor also checks that the project complies with the requirements and serves the strategic objectives of the core organisation. HERMES calls the line organisation that commissions the project the core organisation.
Without a formal decision, the next phase starts because the team is available. Nobody has decided to commit resources to it. The release forces the project to show that the outcomes are available in the required quality and that the plan for the next phase holds. The sponsor guarantees the resources until the end of the project.
The project manager delivers the phase report with the updated project management plan and project status report. The phase report summarises the outcomes and decisions of the phase and presents the organisation of the next one. The sponsor's decision produces the Phase release milestone, the completed checklist and an entry in the List of steering project decisions.
Usage
When to use it
- HERMES project under the traditional approach: the release closes the Concept phase and then the Implementation phase.
- Resources committed phase by phase: the sponsor releases the resources for the next phase on the basis of its detailed plan.
- Project under a regulator's oversight: in healthcare, the regulator judges at each phase gate whether a drug merits further development (PMBOK Guide).
When not to use it
- Execution phase of an agile HERMES project: no phase release between releases; the project management plan can provide for a release decision.
- Tracking progress between two milestones: the release comes only at the end of a phase; track progress in the project status report.
Description
The HERMES decision milestones
HERMES runs a traditional project in five phases: Initiation, Concept, Implementation, Deployment and Closure. Under the agile approach, a single Execution phase replaces the three middle phases. A milestone marks each decision of the sponsor. Phase release refers to the two middle milestones of the traditional sequence. At the end of Concept, it releases Implementation. At the end of Implementation, it releases Deployment.
Each neighbouring milestone is another decision with its own task and checklist. The execution release closes Initiation. The closure phase release follows Deployment or Execution. Under the agile approach, the project management plan can require a release decision between two releases. These decisions follow the same mechanics: a dossier, a checklist and the sponsor's decision.
Who prepares, who decides
The project manager is responsible for the preparation and writes the phase report with the user representative and project support. The project sponsor decides. HERMES separates two decision levels. The sponsor takes all decisions at the steering level. The project manager takes those at the management level. The project committee, the project manager and the user representative advise the sponsor as needed. The quality and risk manager works on the checklist with the sponsor and the project manager. At the sponsor's request, the quality and risk manager writes the QA and risk report, which gives an independent view of the project.
HERMES defines a business analyst role without linking it to these two tasks. A business analyst who knows the solution domain in depth can take the role of user representative, who co-writes the phase report. The phase report draws on much of the analyst's work: the solution requirements, the organisation concept, the results of preliminary acceptance at the end of Implementation. Preliminary acceptance is a management-level decision: before deployment, tests and inspections show that the transfer of the solution will most likely succeed. The analyst gives the project manager the status of these outcomes and the known deviations. The analyst also reports any requirement that the next phase will not be able to meet.
Preparing the release
The HERMES task Prepare phase release summarises the outcomes for the decision-makers and plans the next phase. The project manager starts from the project management plan, the project status report, the change status list and the lessons learned. Under the agile approach, the project manager also starts from the release report. The project manager carries out these activities:
- Plan the next phase in detail and verify the overall plan.
- Summarise the outcomes and changes of the phase in the phase report. Assess their quality.
- Update the project management plan. Coordinate it with the parties involved and with the rule-setting and controlling bodies.
- Update the project status report. It becomes the appendix to the phase report.
- Create the other prerequisites for the release: an adapted project organisation, available resources.
- Submit the requests for acceptance of the outcomes, for the next steps and for the release of resources.
- Request the decision from project steering.
According to HERMES, the phase report "must show that all the necessary outcomes are available in the required quality".
HERMES sets ten content headings for the phase report and lists them separately from the decision activities. The right-hand column matches each heading to a decision activity.
| Phase report heading | What the sponsor checks |
|---|---|
| Background | The outcomes that the phase delivered and that the sponsor approves or rejects |
| Strategy reference and implementation of requirements | Compliance with overarching strategies, standards and requirements; the confirmations of the competent bodies |
| Benefits and economic efficiency | The benefit of the solution in the light of new findings |
| Legal basis | The state of the legal bases the solution depends on. The legal basis analysis provides it. |
| Planning and organisation | The resources for the next phase and for the whole remaining duration of the project |
| Forecast regarding objective achievement and solutions | The feasibility and the achievement of the objectives |
| Problems and measures | The open problems and the measures that address them |
| Risks | The project and operating risks identified, analysed and assessed (end of Concept); the deployment risks judged acceptable (end of Implementation) |
| Requests | The requests the sponsor rules on |
| Conclusion | The project manager's opinion |
Deciding on the release
According to HERMES, the phase report and the project management plan are aligned with the overarching requirements of the core organisation before the decision. At that point the sponsor decides on adjustments to the plan and to the project organisation. If a controlling, quality assurance or risk management body oversees the project, it submits its report to the sponsor. The sponsor carries out the activities of the HERMES task Decide on phase release:
- Add project-specific release criteria to the Phase release checklist.
- Review the objectives, feasibility and benefit of the solution in the light of new findings. Align them with the objectives of the core organisation.
- Check compliance with overarching strategies, standards and requirements. Check that the competent bodies have given their confirmations.
- Guarantee resources for the whole remaining duration of the project: staff, finances, infrastructure, knowledge and experience.
- Coordinate the decision with the core organisation.
- Review the phase report, the project management plan and the phase outcomes. Approve or reject them.
- Take the formal decision on phase release or reject the outcomes.
At the end of a phase, the sponsor checks that the project manager has taken the necessary technical decisions, for example the decision on the architecture. Otherwise the sponsor does not release the next phase. The sponsor can therefore decide without technical expertise of their own.
The conditions specific to each release
For each phase release, HERMES sets conditions that come from the phase that is ending.
| Milestone | Phase released | Conditions |
|---|---|---|
| End of Concept | Implementation | The project and operating risks are identified, analysed and assessed. The feasibility of the solution is demonstrated and validated. The resources are released according to the refined project management plan and the available offers. |
| End of Implementation | Deployment | The decision taken after preliminary acceptance is the basis for the release. The deployment risks are assessed and judged acceptable. The resources are released according to the refined project management plan. |
According to HERMES, the case for carrying out the project is also reviewed at the end of Concept. The project can stop if it is not profitable, if its risks are too high, if it is not feasible or if it does not meet the objectives, strategies and priorities of the organisation.
The possible decisions
On accepting the phase outcomes, the sponsor closes the current phase and releases the next phase and its resources. The project reaches the Phase release milestone. Work on the next phase can then begin. The sponsor informs those affected.
The sponsor can also reject the outcomes while the objectives remain achievable. The sponsor sets the corrective measures, their deadline and the date of the new decision. The phase continues until that decision. The PMBOK Guide calls this option "remain in the phase". HERMES does not describe this option. This procedure comes from our practice.
If the set objectives cannot be achieved, the sponsor determines corrective measures or decides on project discontinuation. HERMES treats discontinuation as an unplanned step. It is possible only between the execution release and the closure phase release. The sponsor alone takes that decision in the task Decide on project discontinuation.
Each entry in the List of steering project decisions records the decision, whether the milestone was achieved, the underlying documents, the decision-makers and the date.
Phase release and phase gate
The Project Management Institute (PMI) defines the phase gate in the glossary of its PMBOK Guide as a review at the end of a phase. This review decides whether the work continues to the next phase, continues with modification or ends the programme or project. The PMBOK Guide gives the "go/no-go" decision as an example. HERMES does not use the term "go/no-go".
| Point | HERMES 2022 | PMBOK Guide, 8th edition |
|---|---|---|
| Name | Phase release. The milestones are quality gates. | Phase gate. Also stage gate, gate review, iteration review, decision point review. |
| Position | End of Concept and end of Implementation | End of a phase. The PMBOK Guide adds decision points at the start of a phase (pre-phase gates). |
| Decision-maker | The sponsor | None in the definition |
| Criteria | The Phase release checklist, which the sponsor completes | Exit criteria (acceptance criteria, contractual obligations, performance targets) and entry criteria (resource availability, viability, alignment with objectives) |
| Possible decisions | Release of the next phase. Rejection of the outcomes and corrective measures. Project discontinuation by a separate decision. | Continue. Continue with modification. End the project or phase. Remain in the phase. Repeat the phase or part of it. Park the project to deal with another urgent initiative. |
Both frameworks describe the same end-of-phase decision. HERMES is more specific: its decision covers the outcomes, names the decision-maker and handles discontinuation separately.
For new product development, Robert G. Cooper describes the Stage-Gate process. From idea to launch, work stages alternate with decision points.
Pitfalls
Releasing a phase that has already started. When the team has already started the next phase, the decision only records a fact. The sponsor can no longer refuse without a loss. Cooper counts weak governance among the failings of Stage-Gate processes. He recommends decision points that can stop a project ("gates with teeth") and designated decision-makers bound by rules of engagement. The project management plan sets the decision date before the planned start of the next phase. No work on the next phase starts before the milestone.
A report that tells a story. A phase report that describes the activities carried out does not say whether the outcomes are available in the required quality. The sponsor cannot rule on a narrative. Each expected outcome appears in the report with its status and any deviation.
Resources secured for the next phase only. According to HERMES, the sponsor guarantees the resources for the whole remaining duration of the project. A project released for Implementation without a deployment budget reaches the end of Implementation with no means to deploy. The dossier therefore also shows the funding of the later phases.
Confusing the phase report with the project status report. The project status report gives an account of progress at fixed intervals. The phase report requests a decision.
Deciding without the core organisation. A sponsor who releases the phase without coordinating the decision with the core organisation leaves overarching requirements unchecked. The IT department, information security or the legal department then discovers the project in the middle of Implementation.
A checklist that keeps growing. Cooper also points to excessive bureaucracy and recommends leaner decision points. A checklist that the sponsor extends with every project slows every release. The sponsor adds only the criteria that can change the decision.
AI considerations
A language model writes a first draft of the phase report. It starts from the project status reports, the change status list and the project management plan. It sorts their content into the ten headings. It compares the updated plan with the version released at the start of the phase and lists the cost, schedule and scope variances. It checks the dossier against the decision activities. It flags the gaps it finds: an empty heading, a requested resource without the period it covers, a risk without an assessment. For a bilingual committee, it drafts the German or French version that the team then reviews.
The model checks that a heading is filled in. It cannot tell whether the content is true. It does not know whether the core organisation supports the project or whether a competent body has given its approval. It does not judge whether an operating risk is acceptable. These judgements stay with the project manager, the quality and risk manager and the sponsor. The conclusion of the report remains the project manager's: a model can write a favourable conclusion that the headings do not support. The phase report contains amounts, names and sometimes assessments of suppliers. The project manager submits it only to an AI service that the organisation approves for that classification level.
Examples
The phase report below closes the Concept phase of the "Online Permit" project. The Risks heading shows that a HERMES condition for the end of Concept is missing. The other headings are favourable.
| Heading | Content |
|---|---|
| Background | Concept from 01.11.2026 to 30.04.2027. Delivered: solution requirements, organisation concept, solution architecture, operating concept, deployment concept. Contract awarded on 12.04.2027. |
| Strategy reference and implementation of requirements | The project implements the cantonal e-government strategy. The architecture complies with the IT directives of the canton: confirmed by the IT directorate on 18.04.2027. |
| Benefits and economic efficiency | 14'000 applications a year move online. Estimated annual saving: CHF 260'000. Revised total cost: CHF 1'610'000 (study: CHF 1'480'000). Spent by the end of April: CHF 310'000. |
| Legal basis | The revised implementing ordinance allows electronic filing from 01.01.2028. |
| Planning and organisation | Implementation from 15.06.2027 to 31.01.2028: CHF 1'120'000 and 3.5 FTE. Deployment in February 2028. Go-live on 01.03.2028. Deployment and closure: CHF 180'000 in the 2028 cantonal budget. |
| Forecast regarding objective achievement and solutions | Objectives achievable. Go-live postponed by one month (study: 01.02.2028). |
| Problems and measures | The vendor of the cantonal residents' register must adapt its interface. Order placed on 20.04.2027. This adaptation explains the one-month delay. |
| Risks | Project risks: identified, analysed and assessed. Each risk in the register has its measure. Operating risks: identified. The cantonal IT centre delivers their analysis and assessment on 31.05.2027. |
| Requests | Accept the outcomes of Concept. Release Implementation with CHF 1'120'000 and 3.5 FTE. |
| Conclusion | The project manager recommends the release. |
Against the advice of the project manager, the sponsor rejects the outcomes: HERMES requires analysed and assessed operating risks before Implementation is released. The decision goes into the List of steering project decisions.
| Item | Content |
|---|---|
| Decision | Concept outcomes rejected. Corrective measure: the project manager completes the Risks heading (phase report v1.1) with the analysis and assessment of the cantonal IT centre by 31.05.2027. New decision on 07.06.2027. |
| Milestone achieved | No |
| Underlying documents | Phase report v1.0, project management plan v2.0, project status report for April 2027, QA and risk report of 26.04.2027 |
| Decision-makers | The head of the population office (sponsor), after consulting the project committee |
| Date | 10.05.2027 |
The rejection does not delay Implementation. The new decision falls on 7 June, before the planned start on 15 June.
Visualisations
The first diagram places the phase releases among the HERMES decision milestones in both approaches. The second diagram shows the decision: the dossier goes in, the sponsor decides, the decision leaves through one of its exits. The headings of the phase report, the conditions of each release, the comparison with the PMBOK Guide and the example are tables.
Cost
| Dimension | Level | Rationale |
|---|---|---|
| Preparation | Medium | The project manager plans the next phase in detail, updates the project management plan and writes the phase report. The status reports of the phase provide much of the material. |
| Execution | Medium | The sponsor reviews the dossier and consults the project committee. Coordination with the core organisation and the confirmations of the competent bodies can take several weeks. |
| Documentation | Low | The phase report follows the HERMES headings. The decision fits in one entry of the List of steering project decisions. |
Tooling
HERMES Online (hermes.admin.ch) describes the two tasks, the phase report and the checklist. The reference manual provides a template for each document that details its content.
A word processor holds the phase report. A spreadsheet keeps the checklist: one criterion per row, its status and the evidence for it.
A project portfolio management tool records the milestones and their decisions. It links each release to the budget it releases.
A shared document space keeps the versions of the dossier on which the sponsor decided. In the List of steering project decisions, the underlying documents point to these versions.
Sources
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management reference manual, task 5.4.3.28 Prepare phase release: the purpose, the prerequisites, the activities and the outcomes.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management reference manual, task 5.4.1.5 Decide on phase release: the purpose, the alignment with the core organisation, the activities, the possible decisions and the outcomes.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management reference manual, outcome 4.4.1.29 Phase report: the description and the ten headings.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management reference manual, outcome 4.4.2.8 Phase release checklist.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management reference manual, edition 03/2026: the milestones as quality gates (§B.4 and §1.2.2), the conditions at the end of Concept and at the end of Implementation (§1.4.2.1 and §1.4.2.2), the technical decisions checked at the end of a phase (§5.1.2.1), the sponsor at the steering level (§5.1.2.2), the business analyst in the user representative role (§6.2.3.4), preliminary acceptance (task 5.4.2.6 Decide on preliminary acceptance), the List of steering project decisions (4.4.1.21), the QA and risk report (4.4.1.42), the Phase release milestone (4.4.4.8), the tasks 5.4.1.4 Decide on closure phase release, 5.4.1.6 Decide on project discontinuation and 5.4.1.9 Decide on release.
- Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition: §4.1 Project Phases (the names of the review, the exit and entry criteria, the possible decisions, the decision points at the start of a phase), §4.2.1 Predictive Approaches (the phase gates that a regulator requires) and the phase gate entry in the glossary.
- Robert G. Cooper, "Perspective: The Stage-Gate Idea-to-Launch Process: Update, What's New, and NexGen Systems", Journal of Product Innovation Management, 25(3), 2008, pp. 213-232, DOI 10.1111/j.1540-5885.2008.00296.x: the failings of governance and bureaucracy, the decision points that can stop a project ("gates with teeth"), the designated decision-makers and their rules of engagement.