Organizational and Resource Breakdown Structures
The organizational breakdown structure (OBS) is the hierarchical representation of a project's organisation. It sets out the units that carry out the work and places each unit's work packages under it. The resource breakdown structure (RBS) is the hierarchical representation of the project's resources by category and by type. Both names are terms of the PMBOK Guide (8th ed.). The guide files both among the hierarchical charts beside the work breakdown structure (WBS). The WBS says what the project produces. The OBS says which unit is responsible for it. The RBS says what resources the work uses.
Goal
The OBS breaks the project organisation down into directorates, departments, teams and suppliers. The RBS breaks down what the project consumes: personnel, materials and equipment.
The WBS says neither which unit is responsible for each work package nor which trades, materials and equipment it consumes. Without these two axes a head of department cannot see what the project expects of the department. The project manager does not know how many test days to book across all the work packages.
The technique produces both coded structures. Each work package receives the code of the unit that carries it out. Each assignment of a resource to a work package receives the code of the resource. The project manager then adds up effort and costs by unit or by resource category. From these totals the project manager derives the budget of each control account and the resources to acquire. On the calendar, the same assignments show the periods when demand exceeds capacity.
For the business analyst, the OBS names the unit responsible for the work package that delivers a requirement. The analyst knows whom to ask about that work package and whom to consult on the impact of a change request. The RBS shows the analyst the business roles that the project must book, for example the key users for user acceptance testing (UAT).
Usage
When to use it
- A project delivered by several departments or suppliers: place each work package under a single unit and show each unit its work packages.
- Earned value management: open the control accounts where the WBS crosses the OBS.
- Resource estimating: describe the needs of each work package by category and by type before costing them.
- A scarce skill or a skill shared between projects: spread the demand by role and by period, then spot the overloads before levelling.
- A budget tracked by cost centre: add up the costs by OBS unit in line with the organisation's budget breakdown.
- Capital costs kept apart from expenses: code the assignments to separate the two totals.
When not to use it
- A small project with a single team: the OBS has only one unit and the resources fit in a list. Record the roles in the RACI matrix.
- A whole organisation under analysis for a change: the OBS covers only the project. Use organizational modelling.
Description
Hierarchical charts
The hierarchical charts of the PMBOK Guide show positions and relationships from the top down. They take the form of the traditional organisation chart. The guide cites the WBS, the OBS, the RBS and the value breakdown structure.
In a 1993 article in PM Network, Levine describes the formal rules that the WBS, the OBS and the RBS share. Each element has a single parent. Durations, effort and costs add up level by level to the project. The OBS ties these totals to the organisation's budget. The RBS groups them by trade or by skill and separates capital costs from expenses.
| Structure | What it breaks down | Question | Carries the code on |
|---|---|---|---|
| WBS | The work, by deliverable | What does the project produce? | The work package and its activities |
| OBS | The project organisation, by unit | Which unit is responsible for the work? | The work package and its activities |
| RBS | The resources, by category and by type | What resources does the work use? | The assignment of a resource to a work package or an activity |
The OBS: units and their work packages
The OBS follows the existing directorates, departments, teams or suppliers. Under each unit it lists the work packages or the activities that this unit carries out. According to the PMBOK Guide, a department such as IT or purchasing sees in its part of the OBS everything that the project expects of it.
The US Department of Energy (DOE) publishes a handbook that interprets the ANSI/EIA-748 standard on earned value management systems. According to this handbook, a single OBS brings together all the units responsible for the project. It includes the major subcontractors and the work given to other organisations. Each unit has a manager with enough authority to carry out its work. In a flat OBS the unit managers report directly to the project manager. A multi-tier OBS places functional managers between them and the project manager.
The organisation chart that organizational modelling produces shows a whole organisation with its roles and its reporting lines. The project organisation chart of the PMBOK Guide shows the team members and their reporting relationships. The OBS covers only the project and places each unit's work under that unit. If the organisation has no project organisation chart, the DOE asks the project to write an equivalent. At a minimum, a code shows who reports to whom.
The RBS: categories and types
The first level below the project holds the resource categories. The PMBOK Guide cites labour, materials, equipment and supplies. Its list stays open: for example, an IT project adds external services. The levels below hold the types: the role, the skill level, the grade or the required certification. In the example of the PMBOK Guide, personnel divides into roles and then each role into levels. A material divides into grades.
Each level describes the resource more finely than the level above. According to the PMBOK Guide, the team stops the decomposition when the detail is fine enough to combine with the WBS. The team can then plan, monitor and control the work.
Each assignment links a resource to a work package or to an activity and states the quantity. It carries the code of the resource. Levine draws a criterion from this. A structure is an RBS only if it adds up the assignments at any level of its codes. A custom field that only sorts or filters the resources does not qualify, even if it is called RBS. The same criterion applies to the OBS.
Where the WBS crosses the OBS
In earned value management, the DOE handbook and the NASA WBS handbook place the control account where a WBS element crosses an OBS unit. You will find the control account matrix of the cantonal building permit portal under work breakdown structure.
The responsibility assignment matrix shows this crossing. Its rows are the WBS elements and its columns the OBS units. According to the PMBOK Guide, this high-level matrix gives each unit its share of each element. At the lower level, the RACI matrix gives each person a role on each activity.
According to the DOE, a single manager is responsible for each control account. Two managers on one account show that nobody has authority over it. Several accounts can share one crossing when the team must separate the work for control: labour, high-value materials, a major subcontract. If the manager cannot demonstrate responsibility, authority and accountability, the team revises the OBS and the WBS. The direct costs of an account roll up into a single OBS unit. A split between two units would distort the totals of both.
These rules come from contracts subject to the ANSI/EIA-748 standard. The PMBOK Guide applies the OBS to every project without requiring control accounts. A project without earned value keeps the rule of one unit per work package.
Building the OBS
- Start from the validated WBS. The team first defines the work, then assigns the responsibility.
- List the units. The project manager takes the existing organisation chart and lists the directorates, departments, teams and suppliers that carry out at least one work package.
- Choose the flat or the multi-tier form. The form follows the reporting lines of the unit managers.
- Name the manager of each unit.
- Place each work package under a single unit. When two units carry out one work package, the team splits it in two.
- Code the units. Each work package and its activities carry the code of the unit in the planning tool.
- Check the roll-ups. The sum of effort by unit equals the WBS total. A gap points to a work package without a unit or to a work package counted twice.
- Review the OBS every month. The DOE sets this pace because people change positions. The review tracks departures, reorganisations and changes of supplier.
The common pitfall: the team files functions, trades or labour categories in the WBS. A WBS modelled on the organisation gives each head of department a branch.
| Element found in the WBS | What it is (NASA) | Where it belongs |
|---|---|---|
| Design, Engineering, Manufacturing | Functions or organisations | OBS |
| Pipe fitter | A skill type | RBS |
| Direct labour | A labour category | RBS |
Building the RBS
- Start from the resource requirements of each work package. The PMBOK Guide describes them by type and by quantity for each work package or each activity. Bottom-up estimation produces them.
- Set the categories at the first level. The team starts from labour, materials, equipment and supplies. It adds the categories that the project needs.
- Set the types under each category. Under personnel come the roles, then the levels. Under equipment come the models or the classes of equipment.
- Stop at the useful detail. The team separates two types when their rate, their availability or their certification differs. A senior developer billed at CHF 1'200 per day and a junior developer at CHF 1'000 form two types.
- Code and assign. Each type receives its code. Each assignment carries this code in the planning tool.
- Check the roll-ups. The total by category equals the total of the work packages. A gap points to an assignment without a code.
The planning tool spreads the coded assignments over the calendar. The histogram of an RBS element then shows the overloads that levelling resolves.
The RBS then feeds resource monitoring, which compares the planned and the actual use of equipment and materials. An organisation that runs several projects can keep a single shared structure. The totals by role then add up across the projects and show the demand on a scarce skill.
Acronyms that collide
The acronyms OBS and RBS and the term organisation chart each have several meanings. The team writes the full term at its first mention in each document.
| Term | Meaning and source | What it breaks down or shows |
|---|---|---|
| RBS | Resource breakdown structure (PMBOK Guide) | The resources by category and by type |
| RBS | Hierarchical list of roles (Caltrans) | The roles alone without materials or equipment |
| RBS | Risk breakdown structure (PMBOK Guide) | The sources of risk of the project |
| OBS | Organizational breakdown structure (PMBOK Guide) | The units of the project and their work packages |
| OBS | Field in the planning software that Levine described in 1993 | A hierarchy of resources or a second hierarchy of tasks |
| Organisation chart | Model produced by organizational modelling | The roles and the reporting lines of a whole organisation |
| Project organisation chart | Resource management plan (PMBOK Guide) | The team members and their reporting relationships |
| Organigramme des tâches | French term of the ISO 21511 standard | The work by deliverable: this is the WBS |
In HERMES
The HERMES 2022 project management plan contains the project organisation chart, the roles in the permanent organisation and in the project organisation, the staffing of the roles and the resource plan.
AI considerations
The PMBOK Guide lists artificial intelligence and predictive analytics among the techniques for estimating resources. A language model drafts an RBS from the resource requirements of the work packages. It flags a role that appears under two names ("Tester" and "Test engineer"). A spreadsheet filter finds the work packages without a unit, the assignments without a code and the work packages placed under two units. The pivot table of the spreadsheet does the roll-ups.
The model does not know who has authority over a work package or who changed position last month. It does not know the internal rates or the framework contracts. The OBS names managers. The RBS carries rates. The team processes them in an AI tool that its organisation has authorised. The PMBOK Guide states that a human is accountable for each decision and that the team checks what the AI produces.
Examples
The cantonal building permit portal totals 290 person-days in its WBS. Its OBS and its RBS break down the same work.
A single list of assignments feeds the roll-ups of both trees. Each line of branch 1.3 carries three codes: the work package, the unit and the resource.
| Work package | Unit | Resource | Quantity | Rate (CHF) | Cost (CHF) |
|---|---|---|---|---|---|
| 1.3.1 Department dashboard | O2.1 | R1.3.2 Junior developer | 14 d | 1'000 | 14'000 |
| 1.3.1 Department dashboard | O2.1 | R1.5 Tester | 6 d | 900 | 5'400 |
| 1.3.2.1 Environment interface | O2.2 | R1.4 Integration architect | 6 d | 1'400 | 8'400 |
| 1.3.2.1 Environment interface | O2.2 | R1.3.1 Senior developer | 8 d | 1'200 | 9'600 |
| 1.3.2.1 Environment interface | O2.2 | R1.5 Tester | 4 d | 900 | 3'600 |
| 1.3.2.1 Environment interface | O2.2 | R2.1 Integration test server | 2 months | 500 | 1'000 |
| 1.3.2.2 Fire safety interface | O2.2 | R1.3.1 Senior developer | 8 d | 1'200 | 9'600 |
| 1.3.2.2 Fire safety interface | O2.2 | R1.5 Tester | 4 d | 900 | 3'600 |
| 1.3.2.2 Fire safety interface | O2.2 | R2.1 Integration test server | 2 months | 500 | 1'000 |
| 1.3.3 Decision and notification | O2.1 | R1.3.1 Senior developer | 10 d | 1'200 | 12'000 |
| 1.3.3 Decision and notification | O2.1 | R1.3.2 Junior developer | 10 d | 1'000 | 10'000 |
| 1.3.3 Decision and notification | O2.1 | R1.5 Tester | 5 d | 900 | 4'500 |
| 1.3.3 Decision and notification | O2.1 | R3.1 Electronic notification platform | 1 year | 3'000 | 3'000 |
| Total for branch 1.3 | 85'700 | ||||
The same thirteen lines add up by unit, then by resource.
| Unit | Work packages | Person-days | Cost (CHF) |
|---|---|---|---|
| O2.1 Portal team | 1.3.1 and 1.3.3 | 45 | 48'900 |
| O2.2 Integration team | 1.3.2.1 and 1.3.2.2 | 30 | 36'800 |
| Total for branch 1.3 | 75 | 85'700 | |
| Resource | Quantity | Cost (CHF) |
|---|---|---|
| R1 Personnel | 75 d | 80'700 |
| R1.3 Developer | 50 d | 55'200 |
| R1.3.1 Senior developer | 26 d | 31'200 |
| R1.3.2 Junior developer | 24 d | 24'000 |
| R1.4 Integration architect | 6 d | 8'400 |
| R1.5 Tester | 19 d | 17'100 |
| R2 Equipment | 2'000 | |
| R2.1 Integration test server | 4 months | 2'000 |
| R3 Services | 3'000 | |
| R3.1 Electronic notification platform | 1 year | 3'000 |
| Total | 85'700 | |
Both roll-ups give CHF 85'700. In the OBS the 19 test days split between the portal team (11 days) and the integration team (8 days). The RBS brings them together on line R1.5. On that line the test lead reads the effort of the role across the whole branch.
Visualisations
The team draws both structures as trees with the project at the top. Under each unit, the OBS lists the unit's work packages or their codes. For the steering committee the tree often stops at the units. Day to day, the team keeps both structures as coded lists in the spreadsheet or in the planning tool. A pivot table shows the roll-ups: the assignments in rows and the unit or the resource element in columns.
| Code | Element | Level | Unit of measure | Rate (CHF) |
|---|---|---|---|---|
| R1 | Personnel | category | ||
| R1.1 | Project manager | role | day | 1'500 |
| R1.2 | Business analyst | role | day | 1'300 |
| R1.3 | Developer | role | ||
| R1.3.1 | Senior developer | level | day | 1'200 |
| R1.3.2 | Junior developer | level | day | 1'000 |
| R1.4 | Integration architect | role | day | 1'400 |
| R1.5 | Tester | role | day | 900 |
| R1.6 | Key user | role | day | 700 |
| R2 | Equipment | category | ||
| R2.1 | Integration test server | class | month | 500 |
| R3 | Services | category | ||
| R3.1 | Electronic notification platform | type | year | 3'000 |
Cost
| Phase | Level | Rationale |
|---|---|---|
| Preparation | Medium | A validated WBS and an up-to-date organisation chart as input. Gather the unit managers and the person who keeps the rates. |
| Execution | Low | The team places the work packages under the units in one workshop. It reuses the categories and the types of a previous project. Medium when there are many suppliers. |
| Documentation | High | A code on each work package and on each assignment. The OBS follows every change in the organisation. |
Tools
A whiteboard is enough to place the work packages under the units in a workshop. A spreadsheet holds the two coded lists, the list of assignments and the pivot tables. MS Project carries hierarchical codes on tasks and on resources and groups the assignments by code. Primavera P6 keeps an OBS that assigns the WBS elements to managers. It also keeps a hierarchical dictionary of resources and roles. Visio, draw.io or a mind mapping tool draw the trees for the steering committee.
Sources
- Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., PMI: hierarchical charts among the tools of Plan Resource Management (§2.6.2.1); the RBS as an output of Estimate Resources and artificial intelligence among its techniques (§2.6.2.2); the structure as an input to Monitor and Control Resourcing (§2.6.2.5); the definition of the RBS, its categories, its types and figure 4-4 (Section 4, entry Resource breakdown structure); the project organisation chart (Section 4, entry Resource management plan); the resource requirements by work package (Section 4, entry Resource requirements); hierarchical charts, the OBS and the depth of the RBS (Section 5, entry Hierarchical charts); the responsibility assignment matrix and the RACI matrix (Section 5, entry Responsibility assignment matrix); human accountability and the checking of AI results (Appendix X3.3).
- U.S. Department of Energy, Earned Value Management System Interpretation Handbook (EVMSIH), version 2.0, August 2016: the single OBS, the subcontractors, the flat or multi-tier form, the reporting code and the monthly review (guideline 2); the control account where the WBS crosses the OBS, its single manager and the revision of both structures (guideline 5); direct costs rolled up into a single OBS unit (guideline 18).
- NASA, NASA Work Breakdown Structure (WBS) Handbook, NASA/SP-2010-3404, January 2010: the product-oriented WBS (§2.4); the functions, skill types and labour categories excluded from the WBS (§3.5.2); the control account where the WBS crosses the OBS in the responsibility assignment matrix and the work package assigned to a single unit (Appendix B, glossary).
- Levine, H. A., "Doing the weebis and the obis: new dances for project managers?", PM Network, vol. 7, no. 4, 1993, pp. 35-38: the rules that the WBS, the OBS and the RBS share, the records that carry their codes, their uses and the meanings of the acronym OBS in software.
- California Department of Transportation (Caltrans), Project Communication Handbook, 2nd ed., September 2007, p. 25: the RBS as a hierarchical list of roles.
- ISO, ISO 21511:2018, Work breakdown structures for project and programme management: the French term for the WBS.
- Federal Chancellery, HERMES 2022, Project Management Reference Manual: the content of the project management plan (outcome 4.4.1.34).