Opportunity Analysis
Opportunity analysis applies risk management to the positive risks of a project. An opportunity is a risk with a positive effect. The analysis identifies opportunities and rates them on the same matrix as threats. For each one it chooses a strategy from the PMBOK Guide: escalate, exploit, share, enhance or accept. Each opportunity gets an owner and a line in the risk register.
Goal
Opportunity analysis looks for uncertain events that would gain the project time, money or value. The PMBOK Guide gives the Risk performance domain a double aim: to increase the probability and impact of positive risks and to decrease those of negative risks.
Many risk registers hold only threats. The possible gains then stay outside the plan: nobody looks for them, puts a figure on them or acts to make them happen.
The analysis settles one question per opportunity: which response to commit, at what cost and under whose responsibility. It delivers lines of the risk register. Each line carries the opportunity statement, its rating, the chosen strategy, the action, its owner and its trigger. Responses that change the project plan also produce change requests.
Usage
When to use it
- Risk register with no opportunity: look for the favourable side before the next risk review.
- Constraint that the sponsor can remove or relax: put a figure on the gain that assumption and constraint analysis found, then choose the response.
- First risk identification at start-up: ask the favourable question beside the unfavourable one.
- Three-point estimate with a distant optimistic bound: look for the event that would make the favourable outcome likely.
- Contingency reserve or Monte Carlo simulation in preparation: enter the opportunities before sizing the reserve.
- Overall project risk that is favourable and outside the thresholds: add high-value scope or review the thresholds with the sponsor.
- Sponsor who reads only the unfavourable variances: present the opportunities in the risk report beside the threats.
- Phase or milestone review: close the opportunities that occurred or expired and look for new ones.
When not to use it
- No risk register and no impact scale: first set up the risk register and the probability and impact matrix.
- Gain that is certain or already secured: enter it in the schedule or the business case.
- Market opportunities of the organisation outside any project: list them with SWOT analysis or market analysis.
Description
Risk, threat and opportunity
The PMBOK Guide defines risk as an uncertain event or condition that, if it occurs, would have a positive or negative effect on one or more objectives. A threat is a risk with a negative effect: a delay, a cost overrun, damage to reputation. An opportunity is a risk with a positive effect: a larger market share, a cost saving, a favourable effect on the environment.
ISO 31000 defines risk as the effect of uncertainty on objectives. A note specifies that the effect is a deviation from the expected. This deviation can be positive, negative or both. It can create opportunities as well as threats.
The BABOK Guide starts from another definition. Its risk analysis and management technique deals with the uncertainties that could harm value. Only one of its responses aims at a gain: increasing the risk taken to seize an opportunity. The PMBOK Guide describes responses specific to opportunities.
The same cycle as for threats
The risk management processes of the PMBOK Guide cover both sides of uncertainty. The Identify Risks process recognises negative and positive risks. The analysis rates them on a shared matrix: a positive definition of impact for opportunities, a negative definition for threats. The risk register carries both in the same columns. The Implement Risk Responses process aims to reduce threats and to maximise opportunities.
Only the response strategies differ. Avoid, transfer and mitigate apply to threats. Exploit, share and enhance apply to opportunities. Escalate and accept serve both.
Threats and opportunities in the risk cycle
PMBOK Guide processes and strategies, 8th edition
Threats
Opportunities
Identify
Negative and positive risks
Analyse
impact in lossesSame probability and impact matriximpact in gains
Respond
Monitor
Same risk register with one owner per risk
1. Identify the opportunities
Identification looks for what could turn out better than planned. It starts from the sources used for threats and asks them the opposite question.
Constraints are the source that the PMBOK Guide names. According to the guide, a constraint can yield an opportunity when whoever set it removes or relaxes it. Assumption and constraint analysis asks this question of every constraint.
The strengths of the organisation yield others. When the PMBOK Guide uses SWOT analysis to identify risks, it draws the opportunities of the project from the strengths.
Estimates also carry gains. The optimistic bound of a three-point estimate describes a favourable outcome. The team asks what would make it likely: a supplier who delivers early, a reused module, a task simpler than expected.
Finally the team starts from the threats in the register. For each one, the team asks whether the opposite event is possible and what it would bring. An interface delivered late is a threat. The same interface delivered early is an opportunity.
The team words each opportunity like a threat: a cause, an uncertain event, a consequence. Here the consequence is a gain: "Since vendor A has finished its specification, it can deliver its login module four weeks before the contract date. The project would gain four weeks of development." A line that expresses a wish ("increase user satisfaction") names no uncertain event. It stays out of the register.
The benefit that the business case promises belongs to the plan. It becomes an opportunity only if an uncertain event can increase it or bring it forward.
2. Rate on the same matrix
The team rates each opportunity with the scales used for threats. Impact reads as a gain: weeks saved, francs saved, value added for users. The risk management plan sets these positive definitions beside the negative ones. The probability and impact matrix then places threats and opportunities on a mirrored grid with the same priority zones.
An impact scale written only in losses leaves the half of the grid reserved for opportunities empty. The team then ranks the opportunity off the grid by judgement. Nobody can compare its priority with that of the threats any more.
Quantitative analysis treats opportunities like threats. A Monte Carlo simulation that omits them shifts the distribution of cost or date towards the worst case. The date and cost it gives at an 80% confidence level are then too pessimistic. Sensitivity analysis shows opportunities as negative correlations: the inputs that shorten the project or cut its cost when they occur.
3. Choose a strategy
Each strategy changes the owner, the probability or the impact of the opportunity.
| Strategy | What it changes | When to choose it | Threat side |
|---|---|---|---|
| Escalate | An owner outside the project | Gain outside the scope or response beyond the project manager's authority | Escalate |
| Exploit | The probability raised to 100% | High-priority opportunity that the organisation wants to see realised | Avoid |
| Share | A third-party owner who receives part of the gain | A third party can capture the gain better than the project | Transfer |
| Enhance | The probability or the impact | The team can act on the causes of the event or on the size of the gain | Mitigate |
| Accept | Nothing; possibly a reserve | Low-priority opportunity; no other response possible or cost-effective | Accept |
Escalate
The team escalates an opportunity that falls outside the scope of the project or whose response exceeds the authority of the project manager. The opportunity is then managed at programme or portfolio level or in another part of the organisation. The project manager names the person to inform and passes on the details. According to the PMBOK Guide, the opportunity goes up to the level of the organisation whose objectives it would serve.
The escalation holds once the recipient agrees to become its owner. After the escalation, the team no longer monitors the opportunity. The register may keep it for information. An opportunity passed on without an answer from the recipient has no owner anywhere. The register therefore records the date it was passed on and the date it was accepted.
Exploit
Exploit targets a high-priority opportunity that the organisation wants to see realised. The response raises the probability to 100%: the team makes sure that the event happens. The PMBOK Guide cites the examples of assigning the organisation's best resources to finish earlier and using a new technology that cuts cost and duration.
An exploited opportunity is no longer uncertain. It enters the plan: the schedule, the budget or the scope. The response therefore often goes through a change request. Exploiting has a cost. An opportunity with a 40% chance of a CHF 60'000 gain is already worth CHF 24'000. Exploiting it adds CHF 36'000 of expected value. The team compares the cost of the response with this amount.
Share
Sharing hands ownership of the opportunity to a third party better placed to capture it. This third party receives part of the gain if the opportunity occurs. The PMBOK Guide advises choosing the new owner with care. The project often pays a premium to the third party that takes on the opportunity. The guide cites risk-sharing partnerships, joint teams, special-purpose companies and joint ventures.
Transfer moves the impact of a threat to a third party together with ownership of the response. The project pays to rid itself of a loss. A project that shares keeps part of the gain and pays the third party to make that gain more likely. A sharing contract drafted as a transfer cedes the whole gain to the third party: the project pays the premium and receives nothing.
Enhance
Enhancing increases the probability or the impact of an opportunity. For the probability, the team acts on the causes of the event. If the probability does not move, the team acts on what sets the size of the gain. The PMBOK Guide cites adding resources to an activity to finish it early. According to the guide, acting early is often more effective than acting once the opportunity has occurred.
Accept
Accepting acknowledges the opportunity without proactive action. The strategy suits low-priority opportunities. It also suits the case where no other response is possible or cost-effective. Active acceptance sets up a contingency reserve: time, money or resources ready for use if the opportunity occurs. Passive acceptance is limited to reviewing the opportunity from time to time to check that it does not change significantly.
The reserve for an accepted opportunity is there to capture a gain. The reserve for a threat absorbs a loss. Reserve analysis sizes the contingency reserve and monitors it at each review. You will find the strategies specific to threats under risk response strategies.
Overall project risk
Overall project risk is the effect of uncertainty on the project as a whole. The PMBOK Guide applies the same families of responses to it in pairs: avoid or exploit, transfer or share, mitigate or enhance, accept. When overall risk is favourable and outside the agreed thresholds, the team can exploit it. The team extends the scope with deliverables of high value to the stakeholders. It can also change the risk thresholds with the agreement of the key stakeholders to capture the opportunity. To enhance it, the team replans, changes the scope or reallocates the resources.
Risk appetite and expected value
The PMBOK Guide defines risk appetite as the degree of uncertainty that an organisation or an individual is willing to accept in anticipation of a reward. The risk threshold quantifies it as an acceptable variation around an objective. A threshold of ±5% on cost reflects a lower appetite than a threshold of ±10%. An organisation with a low appetite forgoes exploiting an opportunity if the response pushes another objective outside its threshold. An organisation with a high appetite accepts a wider variation for a larger gain.
The team then compares the cost of the response with the expected value it adds. The expected value of an opportunity is its probability multiplied by its gain. A response that raises the probability of a CHF 40'000 gain from 25% to 60% adds CHF 14'000 of expected value. It is justified if it costs less.
4. Name an owner and plan the response
Each opportunity gets a named owner. The owner leads the response and monitors the opportunity until it is closed. The register line carries the strategy, the action, its due date, its cost and the trigger that signals that the opportunity is arising. The trigger is an observable signal.
An opportunity often has a window: a date after which the gain is no longer possible. The register carries this date. Line R-22 of the building permit project holds a co-funding opportunity. Its trigger is the publication of the call for projects; the window closes four weeks later. An opportunity whose window closes without a response disappears although nobody decided to let it go.
5. Implement and monitor
The team reviews the opportunities at every risk review. When an opportunity occurs, the owner closes it and records the actual gain. The owner closes an opportunity whose window has passed with no gain. The risk report counts opportunities like threats: open, occurred, closed.
A gain that occurs must enter the plan to count. Four weeks gained on an activity are lost if the next activity keeps its start date. The owner brings the next activity forward or records the weeks gained as a reserve.
AI considerations
For each threat in the risk register, a language model proposes the opposite event and what it would bring. It does the same for the constraints in the assumption log. The team keeps the candidates whose event is uncertain and whose gain can be quantified. The model then rewrites each retained opportunity as cause, event and gain.
The model also checks the register. It flags opportunities with no owner, no trigger or no window. It spots a "share" response whose text cedes the whole gain to the third party or an "exploit" response that leaves the probability below 100%. It writes the spreadsheet formula for the expected value that each response adds. It flags a response that costs more than it adds.
The model knows neither the partners nor the sponsor's latitude. It produces plausible gains and probabilities without a source. The owner of the opportunity supplies the probability and where it comes from. The sponsor decides to exploit, share or escalate because these responses commit budget or a third party. Agreements with a partner and the amounts in a bid stay out of online services whose terms of use the organisation does not control.
Examples
A French-speaking canton digitises building permit applications. The extract shows the opportunities in its register after response planning. The amounts are illustrative.
| Ref. | Opportunity | Gain if it occurs (CHF) | Probability before and after | Strategy | Response and owner | Trigger and window | Response cost (CHF) | Expected value added (CHF) |
|---|---|---|---|---|---|---|---|---|
| R-19 | Since 9 of the 21 municipalities already receive plans as PDF, they can open the digital file three months before the others. | 60'000 of support and fixes avoided at the general go-live | 40% then 100% | Exploit | The sponsor relaxes the single date. The 9 municipalities open on 1 March. Owner: the roll-out manager. | The 9 municipalities confirm their equipment; window until 1 March | 15'000 to run two channels for three months | 36'000 |
| R-20 | Since vendor A has finished its specification, it can deliver its login module four weeks before the contract date. | 40'000 for four weeks of development gained | 25% then 60% | Enhance | The canton opens its test environment to vendor A from June. Owner: the solution architect. | Vendor A announces the end of its internal tests; window until four weeks before the contract date | 8'000 | 14'000 |
| R-21 | Since the neighbouring canton is planning the same plan-checking module, the two cantons can develop it together. | 100'000 of the 200'000 that the module costs | 30% then 70% | Share | An intercantonal agreement entrusts the joint development to the neighbouring canton. Owner: the project manager of the neighbouring canton. | The neighbouring canton launches the call for tenders for the module; window until the award | 20'000 towards the steering of the joint development | 40'000 |
| R-22 | An intercantonal call for projects could co-fund the migration of the archived files. | 50'000 | 20% then 20% | Accept (active) | The project manager reserves five analyst days to submit the application. Owner: the business analyst. | Publication of the call for projects; four-week window | 6'000 if the call opens | 0 |
| R-23 | The land register could receive its applications for entry on the same platform. | Outside the project: a gain for the cantonal administration | Not applicable | Escalate | On 14 October the project manager passes it to the general secretariat of the department that oversees the land register. The general secretariat accepts it on 21 October. The team no longer monitors it. | Not applicable | 0 | Not applicable |
Only R-19 reaches 100% because the decision of the sponsor removes the uncertainty. The owners of the other opportunities estimate their probability after the response. R-21 changes owner. The neighbouring canton leads the response and the project keeps its half of the gain.
Visualisations
Plotting the opportunities by probability and gain shows how far each response moved them. In the example, exploit, enhance and share move the opportunity up the probability axis. Enhance can also move it to the right along the gain axis. Accept leaves it in place. Escalate takes it out of the team's monitoring.
Opportunities before and after response
Building permit project of a French-speaking canton. Illustrative amounts
Probability
R-19Exploit
R-20Enhance
R-21Share
R-22Accept
Gain if it occurs (thousands of CHF)
Before responseAfter response
R-23 EscalateEscalated to the general secretariat and no longer monitored by the team
The expected value of the four monitored opportunities rises from CHF 74'000 to CHF 164'000. The committed responses cost CHF 43'000. If the call for projects opens, the R-22 response costs another CHF 6'000.
Cost
| Phase | Level | Rationale |
|---|---|---|
| Preparation | Low | The risk register already exists. The impact scales of the risk management plan receive their positive definitions. |
| Execution | Medium | One identification workshop per phase. For each selected opportunity, the team costs a response and gets it approved. |
| Documentation | Low | The register columns serve opportunities as well as threats. The window and the actual gain at closure are added. |
Tools
A spreadsheet or the risk register of a project management tool is enough. A type column (threat or opportunity) and impact scales written in losses and in gains let it carry the opportunities.
The team uses a whiteboard or an online tool such as Miro or Mural for the identification workshop. One column per source (constraints, strengths, estimates, threats in the register) guides the collection.
Simulation modules (@RISK from Lumivero, Primavera Risk Analysis from Oracle, Safran Risk) model an opportunity as an event that occurs with a given probability and then reduces duration or cost. They show its effect on the date or the budget at each confidence level.
Sources
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., §2.7.1, §2.7.2, §2.7.2.2 to §2.7.2.6, Section 4 (entry Risk register), Section 5 (entries Assumption and constraint analysis, Probability and impact matrix, SWOT analysis, Strategies for opportunities, Strategies for threats, Strategies for overall project risk): the definition of risk and of opportunity, the double aim of the Risk performance domain, the matrix shared by threats and opportunities, the strategies for opportunities, the responses to overall project risk, risk appetite and risk threshold.
- IIBA, A Guide to the Business Analysis Body of Knowledge (BABOK Guide) v3, §10.38 "Risk Analysis and Management": risk defined by its negative effect on value and the Increase response.
- ISO 31000:2018, Risk management, Guidelines, ISO, 3.1: risk as the effect of uncertainty on objectives and the note that allows a positive or negative effect.