Management levels stacked from top to bottom: business layer, project board, project manager, team manager. On the left, each level sets the tolerances of the level below: project, stage and work package tolerances. On the right, what goes up: checkpoint reports and issues to the project manager, highlight reports and exception reports to the board, project exceptions to the business layer. The only orange arrow carries the exception report from the project manager to the board.

Management by Exception

Management by exception is the PRINCE2 mechanism by which each management level of a project delegates its authority to the level below. The guide calls the limits of this delegation tolerances. The lower level runs its work without referring up as long as its forecasts stay within these limits. As soon as a forecast shows a breach, the lower level raises an exception with the level above. That level decides. PRINCE2 7 defines tolerances for seven aspects of performance and describes the path from the alert to the exception plan in six steps.

Goal

Management by exception delegates the direction of a project level by level and escalates only the variances that exceed the delegated authority. PRINCE2 7 makes it one of its seven principles. The project board sets tolerances for the project manager and steps in when a forecast exceeds them.

It addresses a tension in project governance: decision-makers have little time, yet they are accountable for the result. PRINCE2 7 describes the responsibility of each level in three parts. The level above delegates its authority by setting tolerances. It puts controls in place that flag a forecast breach as an exception and escalate it at once. An assurance mechanism gives each level confidence that these controls work.

The technique serves one decision: what to do with a variance that the delegated level can no longer absorb. It produces tolerances written into the plans of each level. When an exception occurs, the project manager writes an exception report that sets out the situation, the options and a recommendation. If the board asks for it, the project manager draws up an exception plan that replaces the plan of the current management stage. A stage is the part of the project that the board authorises in one decision.

Usage

When to use it

  • Project board with little time: keep it for decisions on variances and spare it the day-to-day monitoring.
  • Project divided into stages: set the tolerances of each stage and review them at its end.
  • Work package entrusted to a team or a supplier: write its tolerances into the work package description or the contract.
  • Timeboxed delivery: hold time and cost tight and let scope vary within its tolerance.
  • HERMES project: write the tolerances that trigger escalation into the project management plan.
  • Project within a programme: the programme sets the project's tolerances and steps in only on its exceptions.

When not to use it

  • No forecast of cost or time: the exception arrives with the breach; first set up earned value management or an estimate at completion.
  • Threat outside the project's scope: no project tolerance covers it; escalate it according to the risk response strategies.

Description

Setting tolerances

PRINCE2 7 defines tolerance as the permissible deviation above and below a plan's target. As long as the deviation stays within that margin, nobody escalates it to the level above. Tolerance applies to seven aspects of performance: benefits, cost, time, quality, scope, sustainability and risk.

The aspects of tolerance in PRINCE2 7: one example per aspect and the documents that carry each tolerance.
AspectWhat the tolerance limitsExampleDocuments that carry it
BenefitsThe variance on the expected benefitsCHF 400'000 of savings a year, ±10%Business case (project level), stage plan
CostAn overspend or underspend of the budgetStage budget: CHF 480'000, ±10%Project plan, stage plan, work package description
TimeFinishing early or late against the target dateStage end on 30 April, from −4 to +2 weeksProject plan, stage plan, work package description
QualityThe permitted deviation on the acceptance criteriaResponse time of 2 s at most; up to 2.5 s for 5% of requestsProject product description, product descriptions
ScopeThe variation in the products deliveredAll "must have" and "should have" items; a "could have" may be deferredPlans (at stage and work package level, above all in agile delivery)
SustainabilityThe variance on the sustainability targetsPower consumption of the hosting infrastructure: 120 MWh a year, +5%Business case, stage plan, work package description
RiskThe cumulative exposure to threatsTotal exposure of CHF 60'000 at most; no single threat above CHF 25'000Business case, stage plan, work package description

The quality tolerance is set in the acceptance criteria of the products. A stage plan or a work package description does not summarise the quality tolerance. Scope is often bounded by priority. The project manager may defer a "could have". For a "should have" or a "must have", the decision rests with the board. MoSCoW prioritisation supplies these categories.

Many projects set tolerances only on cost and time. PRINCE2 extends the forecast to the seven aspects. A project that holds its budget by delivering fewer products or by relaxing an acceptance criterion exceeds a tolerance without anyone seeing it.

The delivery approach shapes how the tolerances are set. In timeboxed iterative delivery, time and cost are fixed with tight tolerances; the margin lies in scope. When a supplier delivers a work package, the contract carries the tolerances of that work package. The project board reviews the tolerances at the end of each stage to follow how the project and its environment change.

PRINCE2 sets no tolerance values. The delegating level sizes each tolerance from the accuracy of the estimate behind the target and from what it is willing to lose without being consulted. A tolerance narrower than the uncertainty of the estimate turns ordinary variations into exceptions. The board then receives so many that it stops reading them. A tolerance wider than the loss the board can accept leaves the project manager with decisions that belong to the board. Reserve analysis shows you how to size the time and budget reserves.

The management levels and what they delegate

The business layer covers senior management, the programme or the customer that commissions the project. It sets the project tolerances. The project board directs the project within these limits. It sets the project manager's tolerances for each management stage. The project manager runs the stage day to day. Each team manager agrees with the project manager on the tolerances of the team's work package.

The team manager sends checkpoint reports to the project manager and raises issues. The project manager sends highlight reports to the board at fixed intervals and an exception report when a stage or project tolerance is threatened. The board passes the exceptions that affect the whole project to the business layer.

Each level sets the tolerances of the level below and receives its reports. A stage exception climbs from the project manager to the project board. It reaches the business layer only when a project tolerance is threatened.

Delegation binds both sides. A board that steps into the stage while the forecasts stay within tolerance takes back the authority it delegated. The project manager then waits for its instructions instead of deciding. Conversely, a project manager who silently absorbs a forecast breach takes a decision that belonged to the board.

An exception is a forecast

PRINCE2 7 defines an exception as a situation where it can be forecast that a deviation will exceed the agreed tolerances. The guide sees no need to wait for the actual breach. The exception report therefore goes out as soon as the forecast leaves the tolerance, even if the actuals still follow the plan.

The technique relies on a regular forecast of each aspect: the estimate at completion for cost, the likely end date, the products that will be delivered and the acceptance criteria that tests confirm. Earned value management provides the estimate at completion.

You will find the cadence of periodic reports in the project status report. In PRINCE2, checkpoint reports and highlight reports follow a schedule. The issue report and the exception report are triggered by an event.

The level of the exception

The threatened tolerance determines the level that decides.

By threatened tolerance: who raises the exception, to whom, in what form and who decides.
Threatened toleranceRaised byToIn what formWho decides
Work packageTeam managerProject managerIssueProject manager (within the stage tolerances)
StageProject managerProject boardIssue report and exception reportProject board (within the project tolerances)
ProjectProject boardBusiness layerReferral with the exception reportBusiness layer

A project exception takes away the board's authority to direct the project.

The steps of exception management

PRINCE2 7 describes the exception management technique in six steps. A project can replace it with another procedure, for example the one its programme uses. The project records this choice among the tailoring decisions in the project initiation documentation.

  1. The team manager raises an issue. The team manager forecasts that the work package will exceed a tolerance and reports it to the project manager as an issue. If the project manager resolves it within the stage tolerances, no exception report follows. The issue appears in the next highlight report. A note can go into the lessons log.
  2. The project manager writes the exception report. If the forecast exceeds a stage or project tolerance, the report describes the situation, the options and the project manager's recommendation. It goes to the board with the data the decision needs.
  3. The project board chooses. It can cover the stage overrun with part of the project tolerance. It can revise the priorities of the requirements to reduce or redefine the scope. It can ask for time to examine the report. It can accept the report and request an exception plan. If a project tolerance is affected, it refers the matter to the business layer. The business layer instructs the board, which then instructs the project manager.
  4. The project manager prepares the exception plan. The project manager closes the current stage and updates the project initiation documentation. An end stage report can accompany the plan.
  5. The board assesses the exception plan. It can approve it. If it rejects it, it requests changes or tells the project manager to continue the stage as planned.
  6. The project manager implements the plan. The exception plan becomes the plan of the revised stage. The project manager authorises the new work packages and aims to finish the revised stage on the date planned for the original one. The planned end stage decisions then keep their dates.
The steps of exception management across the management levels. The project board decides at steps 3 and 5. The business layer steps in only when a project tolerance is affected.

An exception report that offers a single option leaves the board to choose between accepting it and building other options in the meeting. The report serves the decision better when it prices at least two options and the effect of each.

The exception report and the exception plan

The exception report tells the board that a stage plan or the project plan will exceed its tolerance. It contains an identifier, the date, the description of the exception, its cause and its consequences. It presents each option with its effect on the business case, the risks and the tolerances. It ends with the recommendation and the lessons learned. PRINCE2 does not set its format: a presentation, an email or a dashboard will do. An urgent exception is announced orally first, then in the agreed format.

The exception plan explains how the project responds to the exception within the stage. If the response reaches beyond the stage, the project plan changes too. A team plan has no exception plan: a work package exception is settled within the stage. The revised stage begins when the board approves the exception plan. An ordinary stage begins in the same way when the board approves its plan.

Raising the alarm early

The project manager can warn the board at the first signs, then send the exception report. PRINCE2 counts the escalation of an issue or a risk as good practice. The earlier it comes, the more time remains to correct course. The guide names psychological safety and a no-blame culture as conditions for early escalation.

Where reporting an overrun costs the reporter dearly, the project manager keeps the forecasts inside the tolerance until the actuals cross it. The exception then arrives too late to leave any options.

The same tolerances govern the escalation of risks. The communication plan sets the recipient and the channel of the alert; the tolerance sets the moment it goes out.

In a HERMES project

HERMES 2022 does not define tolerances. The task Manage and control project has the project manager take measures when deviations from the plan have occurred or are forecast. Under the task Deal with problems and benefit from lessons learned, the person responsible immediately escalates to those responsible in the project organisation any problem that he or she cannot solve or cannot solve in time. According to HERMES, the project management plan defines this resolution process.

Tolerances per level give this process a criterion. The project management plan then states which forecast variance the project manager settles alone and which one goes to the project board.

AI considerations

A language model prepares the exception report from the project documents. It extracts the description, the cause and the figures of the variance from the issue register, the forecasts and the stage plan. It puts the options into the structure of the report. It reads a plan or the project initiation documentation and lists the aspects without a tolerance: a plan that bounds only cost and time stands out. It drafts the spoken version of an urgent alert.

The project manager calculates the options in a spreadsheet, where the board can check each amount. The delegating level sets the tolerances itself: they express what it is willing to risk. The forecast comes from the estimates of the team that does the work. The board chooses the option and is accountable for it.

An exception report contains contract amounts, supplier names and sometimes a judgement on a team. It goes through an AI tool that the organisation has approved for such data, never through a consumer service.

Examples

An electricity distributor in the canton of Vaud is migrating its billing system. Exception report EX-03 flags a stage exception: the forecast exceeds the cost and time tolerances of stage 3 but stays within the project's cost tolerance. The report therefore goes to the project board.

Exception report for stage 3 (interface with the smart meters) of the billing migration project. Amounts in CHF excluding VAT.
IdentifierEX-03
Date10 March
DescriptionForecast stage cost: 543'000 against a budget of 480'000 (+13.1%; tolerance ±10%). Forecast end on 21 May instead of 30 April (+3 weeks; tolerance +2 weeks). Actual cost to date: 190'000 against 195'000 planned.
CauseOn 3 March the meter supplier announced a new version of its reading interface. The old version shuts down on 1 June. The adaptation takes three weeks and 70 person-days at 900, that is 63'000.
ConsequencesStage 4 (acceptance tests) starts three weeks later. Go-live stays within the project's time tolerance (+1 month).
Option A: exception planStage at 543'000, ending on 21 May. Business case: project cost +63'000, that is 60% of its cost tolerance (105'000); benefits unchanged. Risks: one week of margin remains on the project schedule. Tolerances: the board sets the tolerances of the revised stage.
Option B: remove the load curve display ("should have")Stage at 509'000 (+6.0%), ending on 7 May (+1 week): cost and time stay within their tolerances. The board decides without an exception plan. Business case: the benefit of 40'000 a year in avoided calls to customer service is deferred until the later delivery of the feature, which will cost at least the 34'000 removed. Tolerances: benefits fall by 40'000 a year (−10%) and reach the limit of their tolerance. Removing a "should have" takes the project manager outside the scope tolerance the board has set.
RecommendationOption A. Option B defers a cost of at least 34'000 and a benefit of 40'000 a year.
LessonsThe contract with the meter supplier set no notice period for an interface change. Future contracts set a notice period of six months.

Option B brings the stage back within its cost and time tolerances. It still requires a decision from the board: removing a "should have" takes the project manager outside the scope tolerance the board has set.

Visualisations

The chart of the stage's cumulative cost shows the forecast from the example. Actual cost follows the plan until 10 March. On that day the forecast end point falls outside the tolerance zone on both cost and time. The exception report goes out the same day. The forecast shows that actual cost would reach the CHF 528'000 limit only in mid-May.

0100'000200'000300'000400'000500'000600'0003 February1 March1 April1 May31 MayCumulative stage cost (CHF)PlanActual costForecastTolerance zone:±10%, from −4 to +2 weeksForecast end: 21 May,CHF 543'00010 March:exception report EX-03Actual cost would reachthe limit around 18 May0100'000200'000300'000400'000500'000600'0003 February1 March1 April1 May31 MayCumulative stage cost (CHF)PlanActual costForecast
10 March: exception report EX-03
Tolerance zone: ±10%, from −4 to +2 weeks
Forecast end: 21 May, CHF 543'000
Actual cost would reach the limit around 18 May
Cumulative cost of stage 3 in the example. On 10 March the actual cost follows the plan, but the forecast end point falls outside the tolerance zone on both cost and time. The exception report goes out that day.

Cost

PhaseLevelRationale
PreparationMediumSet tolerances for seven aspects at three levels, then write them into the business case, the plans and the work package descriptions. One project board meeting at initiation, then a review at the end of each stage.
ExecutionLowForecasting is already part of routine monitoring. A stage exception requires a report of two to three pages and a decision meeting.
DocumentationMediumEach stage exception produces an exception report. An exception plan adds a full stage plan and the update of the project initiation documentation.

Tooling

A spreadsheet is enough to hold the tolerances per level, compare each forecast with its tolerance and price the effect of the options in an exception report. Conditional formatting colours the row whose forecast leaves the margin.

Scheduling software (Microsoft Project, ProjectLibre) calculates the likely end date and the estimate at completion from the progress entered. A ticket tracker (Jira, Redmine) holds the issue register and keeps a trace of each escalation. A dashboard (Power BI, Excel) compares each forecast with its tolerance for the highlight report.

Sources