Leadership Styles
A leadership style is the way a leader runs a project team: who decides and what the leader does for the team. The PMBOK Guide files three entries under the Leadership tool of the Lead the Team process: the centralised structure, the distributed structure and servant leadership. The two structures place authority and decisions. Servant leadership describes how the leader serves the team. The project manager sets the allocation decision by decision. The team's experience, the variability of the work and the project's governance guide that choice. The project manager writes the allocation into the team charter.
Goal
The technique sets who takes each recurring project decision and what the project manager does for the team. It targets the decisions that stall or contradict each other because nobody has written down who holds them. The PMBOK Guide describes the Lead the Team process as a mix of management and leadership activities. Management deals with the means: processes, planning, coordination, measurement and monitoring of the work. Leadership deals with people: influencing, motivating, listening, enabling each person to act.
The deliverable is a written document in two parts: the allocation of decisions and the project manager's support plan. For each decision, the allocation gives the owner, the decision mode, the terms and the person to whom the decision escalates when it goes beyond those terms. The support plan ties each of the project manager's actions to a project objective. The PMBOK Guide counts decision-making among the topics that the team discusses when it drafts its team charter.
Usage
When to use it
- Team formation: write down who decides what before the first contested decision.
- Project new to the organisation: the PMBOK Guide calls for more oversight and a more directive style there.
- Agile implementation in a HERMES project: separate what the project manager leads from what the team organises itself.
- Decisions that stall or contradict each other: establish in writing who settles each one.
- A team that waits for the project manager to settle everything: write down what the team decides itself and within which terms.
- A team spread over several sites: set in writing what each person decides alone.
- A change of sponsor, governance or development approach: review the allocation, since the change often shifts it.
When not to use it
- The behaviour of a single person: a team allocation does not settle it. Use motivation models or conflict management instead.
- A difficulty that stems from the team's stage rather than from the allocation of decisions: use the Tuckman ladder.
Description
Two separate questions
The centralised structure and the distributed structure place authority and decisions. The PMBOK Guide files them as centralized management and leadership and distributed management and leadership. It defines servant leadership as a practice: the way the leader runs the team. According to Section 5 of the guide, leadership is a matter for every team member, whereas management can be centralised or distributed. Leadership skills are as useful under a centralised authority as under shared leadership.
The Standard for Project Management appears in the same volume as the guide. The Standard itself separates leadership from authority. Authority is the position of control that the organisation gives a person. Leadership means inspiring and motivating others. In shared leadership a team member, a stakeholder or a specialist can step into the leader's role. Centralisation and distribution form an axis: the decision belongs to one person or is spread across several. From this a practitioner concludes that servant leadership is a stance that the leader adopts at any point on that axis. A project manager who alone decides the schedule can spend the week clearing the team's obstacles. A self-organising team can have a facilitator who runs the meetings without asking what the members need.
Where is the decision made?
- One person answers for the outcome
- Project new to the organisation
- Predictive approach
- Self-organising teams for part of the work
- Decisions spread across individuals and teams
- Rotating facilitator role
- Team experienced in this type of project
- Highly variable work
What does the leader do for the team?
Understand the members' needs and development to serve the project's objectives
The centralised structure
In a centralised structure, authority and decisions sit with a few senior leaders. Instructions flow down to the other levels. According to the PMBOK Guide, accountability for the outcome then usually rests with one person: the project manager or a similar role. The project charter or another authorising document authorises that person to form the team. HERMES describes the same structure for the traditional approach: there the project manager assigns the work through work orders.
The PMBOK Guide notes that a decision taken alone is fast. The lone decision-maker also gets it wrong more often than a diverse group. Such a decision can demotivate the people concerned when they feel that their view was ignored. The centralised structure fits when one person must answer for the outcome to the sponsor or when the team lacks experience of the type of project.
Tannenbaum and Schmidt tie the sharing of decisions to forces in the manager, in the subordinates and in the situation. The situation covers the type of organisation, the group's effectiveness, the problem itself and the pressure of time. The more the manager feels the need for an immediate decision, the harder it is to involve other people. At project scale the PMBOK Guide observes the opposite effect. In a highly variable project there is no time to assign tasks and take decisions centrally. The guide treats collaborative teams as indispensable there.
The trap is the bottleneck. A project manager who keeps every technical decision settles matters that the team knows better. Meanwhile the team waits. The PMBOK Guide describes a way to consult without giving up the decision. To escape the influence of a superior, each member first formulates options alone. The group then converges on a solution. The decision owner decides on that basis.
The distributed structure
In a distributed structure, authority and decisions are spread across several individuals and teams. The PMBOK Guide gives two forms. In the first, a project management team shares the management activities. The team members carry out the work. In the second, the team organises itself. One member then facilitates communication and collaboration in place of a designated project manager. This role can pass from one member to another. The Scrum Guide describes a team of this kind: it decides internally who does what, when and how.
HERMES allows both structures in one project. In agile implementation the project manager leads the project but must not interfere in the self-organisation of the agile implementation organisation. The user representative steers the team's work through the requirements.
For self-governance models the PMBOK Guide flags a challenge: fragmented decision-making, where several decision-makers act in conflicting ways. The project loses its direction. Nobody answers for the outcome any more. The guide responds with clear and measurable common objectives, leading indicators and effective feedback mechanisms. A distributed structure therefore keeps leadership and a person or group who answers for the outcome.
The second trap is token delegation. The project manager announces that the team decides and then overturns its choices. A seasoned expert decides for everyone. Tannenbaum and Schmidt note that a team used to strong direction is often thrown when it is suddenly asked to share in decisions. The two authors also describe the conditions that let the manager delegate more. On the subordinates' side they cite a strong need for independence, readiness to take responsibility for a decision and tolerance for ambiguity. They also list interest in the problem, commitment to the organisation's goals, the habit of sharing decisions, the necessary knowledge and the required experience. The manager needs confidence in them and a tolerance for uncertainty. When these conditions are missing, the manager tends to make wider use of authority.
Servant leadership
The PMBOK Guide defines servant leadership as the practice of leading the team by understanding and addressing the needs and development of its members. The aim is the highest possible team performance. The guide specifies that this practice serves the project's business objectives. The Standard ties the concept to respect, humility and availability. The leader listens to feedback, works for the team, meets its needs and removes obstacles whenever possible.
Robert K. Greenleaf coined the term in 1970. For Greenleaf the servant leader is servant first: the wish to serve comes before the wish to lead. His test concerns the people served. Do they grow as persons? Do they become more autonomous? PMI also counts the members' development. For PMI it is a means to performance in service of the project's objectives. The Scrum Guide describes the Scrum Master as a leader who serves the Scrum Team and the organisation.
The trap is service without an objective. A project manager who takes on the team's chores and settles nothing serves the people and leaves the project without decisions. The project manager removes an obstacle when that obstacle delays an outcome that the sponsor expects.
A systematic review of 285 articles published between 1998 and 2018 concludes that the concept's lack of coherence and clarity has held back the development of its theory (Eva et al., 2019). It evaluates sixteen instruments that measure servant leadership. A performance promise attached to the word "servant" therefore rests on a concept that is still poorly defined.
Combining the structures in one project
The Standard describes hybrid coordination. A project with centralised coordination can hand part of the work to self-organising teams. HERMES does the same when it embeds an agile implementation in a project led by a project manager. The Standard also expects the leader to switch between styles as the situation requires. It cites the shift from a more directive style in critical phases to a supportive style when team autonomy serves the project.
Setting the allocation
The Standard splits the work into portions and allocates each portion to centralised coordination or to self-organising teams. The PMBOK Guide gives criteria. A practitioner's method gives each decision an owner and a mode. It combines these criteria with those of Tannenbaum and Schmidt.
- List the recurring decisions
Priorities, technical choices, estimates, acceptance of deliverables, assignment of people, spending, external communication. For each one, note who answers for it to the sponsor. The project charter sets the project manager's authority. Whatever exceeds it stays with the sponsor. In HERMES the project execution order sets these limits. - Read the context
The PMBOK Guide gives pointers. A team experienced in this type of project can manage itself more. A project new to the organisation calls for more oversight and a more directive style. Highly variable work run with an adaptive approach benefits from self-organising teams. Top management may expect the team's style to match its own. - Question the members and yourself
Do the members want to decide on this matter? Do they have the knowledge? The project manager also examines their own tolerance for uncertainty. A project manager takes back a delegation that they cannot live with. - Weigh the time and the cost of an error
The lone decision-maker saves time and gets it wrong more often than a group. A group decision costs the team time and wins more buy-in. To limit interruptions to the work, the PMBOK Guide advises choosing with care which decisions go to group discussion. - Choose each decision's mode and write its terms
For each decision, Tannenbaum and Schmidt place the manager's behaviour on a continuum. The method derives the decision modes from it. Announced decision: the decision owner decides and then announces the decision. Consultative decision: the owner presents the problem and gathers the team's proposals before deciding. Delegated decision: the owner sets the limits within which the team or one of its roles decides. The terms of a delegated decision set the measurable objective, the limits, the indicator tracked and the person to whom the decision escalates when it goes beyond those terms. For anything beyond its authority, the team studies the options and their effects. It then hands the decision to whoever holds the authority. - Draw up the support plan
Write down what the project manager does for the team: the obstacles to remove, what to protect and the development to support. Tie each action to a project objective. - Record and review
The allocation goes into the decisions section of the team charter. The team rereads it when the development approach, the governance or the composition of the team changes. A decision that often escalates to the project manager signals terms that are too narrow or token delegation. Retrospectives bring these escalations to light.
AI considerations
A conversational assistant drafts a first inventory of decisions from the project charter, the backlog and the committee minutes. For each decision it proposes a mode and gives its reasons. The team challenges the proposal in a workshop. It also writes conflict scenarios that test the allocation. For example, the user representative and the architect ask for two different sequences for the same iteration: the allocation must say who settles it.
The assistant does not know the trust between members or what each of them can do. The choice of a decision's mode rests on a judgement of that trust and those skills. The project manager forms it from watching the team at work. The assistant must not estimate from messages or activity data whether a member is ready to decide alone. In Switzerland, Art. 26 of Ordinance 3 to the Employment Act (OLT 3 / ArGV 3) prohibits systems designed to monitor the behaviour of workers at their workstation. Minutes that name people stay out of the online services that the organisation has not approved.
Examples
The cantonal portal for building permit applications follows HERMES with agile implementation. The project takes its decisions in different modes. The project manager ties each action that they take for the team to a portal objective.
| Decision | Who decides | Decision mode | Terms and escalation |
|---|---|---|---|
| Budget and go-live date | Sponsor on a proposal from the project manager | Announced decision | Outside the team's authority. A deviation goes to the steering committee. |
| Portal go-live | Sponsor | Announced decision | A release decision that the project management plan makes mandatory. The project manager prepares it. |
| Communication to the municipalities | Project manager | Announced decision | A single sender to the municipalities. The user representative reviews every mailing. |
| Interface with the land register | Architect | Consultative decision | Each developer formulates options before the meeting. The decision goes into the decision log. |
| Order of requirements in the backlog | User representative | Delegated decision | Within the scope of the mandate. An addition that affects the budget or the deadline becomes a change request. |
| Allocation of work within the iteration | Implementation team | Delegated decision | Iteration goal set with the user representative. The project manager does not intervene. |
| What the project manager does for the team | Objective served |
|---|---|
| Obtain access to test data from the land register | Meet the go-live date |
| Receive the municipalities' requests in the team's place and pass them on to the user representative | Protect the goal of each iteration |
| Fund training in digital accessibility for two developers | Meet the accessibility requirement of the specification |
The team first wanted to decide the interface with the land register on its own. Nobody had worked with that register. The project manager gave the decision to the architect. The architect decides after gathering the team's options.
Visualisations
The map sorts the portal's decisions by decision mode and shows that the project manager's support plan covers them all.
- Budget and go-live dateSponsor on a proposal from the project manager
- Portal go-liveSponsor
- Communication to the municipalitiesProject manager
- Interface with the land registerArchitect
- Order of requirements in the backlogUser representative
- Allocation of work within the iterationImplementation team
- Obtain access to test data from the land register
- Receive the municipalities' requests in the team's place and pass them on to the user representative
- Fund training in digital accessibility for two developers
Fictitious decisions.
Cost
| Phase | Level | Justification |
|---|---|---|
| Preparation | Low | List the decisions from the project charter, the mandate and the backlog. |
| Execution | Medium | A two-hour workshop with the team and the user representative. The sponsor then approves the limits. |
| Documentation | Low | One section of the team charter. |
Tooling
A whiteboard or an online board is enough to sort the decisions by mode in a workshop. The RACI matrix complements the allocation. It says who is responsible and who is accountable for each deliverable. The allocation says how each decision is taken. A decision log records each consultative decision and its reason.
Sources
- The Standard for Project Management and A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition, PMI. In the Guide: the Lead the Team process with its management and leadership activities and its tools (§2.6.2.4); adapting the style to the team's experience, to the development approach and to governance, collaborative teams in highly variable projects (§2.6.3); the challenge of fragmented decision-making in self-governance models (§2.1.2); the definitions of centralized management and leadership, of distributed management and leadership and of servant leadership, unilateral or group decision-making (entry Leadership), the project charter and the team charter (Section 5). In the Standard: centralised, decentralised or hybrid coordination (§2.4); switching between leadership styles and situational leadership (§2.5.1.1); leadership as distinct from authority, shared leadership, respect, humility and availability as the basis of servant leadership (§3.6).
- Spears, L. C. (2005), The Understanding and Practice of Servant-Leadership, Servant Leadership Research Roundtable, Regent University: quotes the essay The Servant as Leader (1970) by Robert K. Greenleaf and his test of the growth of the people served.
- Eva, N., Robin, M., Sendjaya, S., van Dierendonck, D. and Liden, R. C. (2019), Servant leadership: A systematic review and call for future research, The Leadership Quarterly, 30(1), 111-132: the review of 285 articles and sixteen measurement instruments; the concept's lack of coherence.
- Tannenbaum, R. and Schmidt, W. H. (1958, reprinted 1973), How to Choose a Leadership Pattern, Harvard Business Review: the continuum of the manager's behaviour and the forces (the manager, the subordinates, the situation) that determine how decisions are shared.
- Ken Schwaber and Jeff Sutherland, The Scrum Guide (November 2020), section "Scrum Team": the team that decides internally who does what, when and how; the Scrum Master who serves the Scrum Team and the organisation.
- Swiss Confederation, HERMES 2022, Project management reference manual, Appendix A.6 Management of agile development with HERMES: the project manager's work orders in the traditional approach, the self-organisation of the teams in the agile approach and the ban on the project manager interfering in it.
- Ordinance 3 to the Employment Act (OLT 3 / ArGV 3), SR 822.113, art. 26: the prohibition of systems designed to monitor the behaviour of workers at their workstation.