Two charts side by side. On the left, the expected shape in three descending bars: many small changes, fewer medium ones, very few large ones. On the right, a schedule of six periods in bars stacked by size. The third period holds two large changes and is labelled "Peak". The fifth receives only one small change and is labelled "Gap". The values are illustrative.

Inverse Power Law for Loading

The Inverse Power Law for Loading is a planning technique that spreads the changes a population receives over time. It starts from a regularity that Anderson borrows from the statistics of natural phenomena: small events are many, medium events rarer and large events very rare. The team classifies the planned changes by size and places them on a schedule. There it finds the peaks where large changes pile up. It splits, moves or works around changes until the schedule takes this shape. George W. Anderson describes the technique in Design Thinking for Tech (2023).

Goal

The team that applies the Inverse Power Law for Loading decides when to deliver each change and in what form. It prevents a population from receiving several large changes in the same period. The population is the group that receives the changes: the users of an application, a department or an IT team. Anderson speaks of a community.

According to Anderson, the larger a change, the more it weighs on the schedule and the less time it leaves for other changes. Size therefore matters more than the number of changes.

The deliverable is a rebalanced schedule that classifies a population's changes by size.

Usage

When to use it

  • Rollout under way: decide whether the team takes on more sprints while the users receive the latest release.
  • Scheduling user acceptance testing (UAT): avoid the quarterly close and the testers' peak season.
  • Changes too heavy for the population: split two medium changes into four smaller ones by module or by wave.
  • Internal transformation during an upheaval in the industry: plan around the change imposed from outside.
  • Progress that has become unpredictable: rebalance upcoming tasks, changes and events.
  • Several projects target the same population with no shared schedule: gather each project's separately planned changes on one schedule.

When not to use it

  • Measuring absorption capacity: the technique does not measure it; trace past changes with the Culture Snail.
  • Spreading working hours across people: the technique counts changes without converting them into hours; use resource levelling and smoothing.

Description

A natural law used as an analogy

Anderson calls the relationship between the size and the frequency of natural events the Inverse Power Law. He presents it as a fact of nature. He says that it also appears in biology and astronomy. He uses it as a constraint for loading tasks, for learning and for judging what a population can absorb. In statistics, a quantity follows a power law when the probability of a value decreases as a power of that value. According to Newman (2005), the sizes of cities, earthquakes, solar flares and fortunes appear to follow such a law. Clauset, Shalizi and Newman (2009) tested 24 data sets claimed to follow a power law. Some confirm the law. For others, the tests rule it out.

Reliability engineering has an acceleration model with a similar name and no link to the technique: the life of a component decreases as a power of the stress applied to it. The NIST handbook describes it as the (Inverse) Power Rule for the voltage on capacitors. In the technique's name, loading means the load of changes that people receive.

What the book gives

In three pages, Anderson gives the law, a figure and six questions drawn from planning situations, then says how to read a schedule. The team records the size and frequency of the changes inside the project and around it. It looks at how the schedule, the changes and the goals overlap over time. It looks for the gaps, where few changes occur. According to Anderson, a gap may offer the bandwidth for one more task or change.

Figure 16.4 of the book is a change log. Each month from March to go-live has one bar that stacks the small, medium and large changes. The small changes form the largest part of each bar. The large ones stay close to zero until the go-live month. According to the caption, the law helps determine how many small, medium and large changes a population can absorb over a period.

The steps, the size scale and the reading of the schedule are our own. They keep to Anderson's law, his six questions and his reading.

The steps

  1. Define the population and the horizon. The analyst names the population. The analyst also chooses the horizon and the period, for example six to twelve months divided into months.
  2. List the changes. The analyst gathers every change that the population will receive. The analyst takes them from the roadmap, the release plan and the change log, then adds the announcements of other projects, of management and of human resources. Anderson also counts the changes around the project, which the project does not control and must still absorb.
  3. Set the scale and classify. The team sets the size scale with a key user from the population. It assigns a size to each change.
  4. Place the changes on the schedule. The team stacks the changes by period and by size. It adds the business events that keep the population busy: period-end closings, peak seasons, holidays.
  5. Read the peaks and the gaps. The team asks the reading questions.
  6. Rebalance. The team splits, moves or works around changes. It rereads the schedule after each decision.
  7. Submit the schedule for a decision and keep it current. The project manager presents the rebalanced schedule to the steering committee, which arbitrates between the projects. The team updates the schedule whenever a change is announced.

Classifying changes by size

The team sets the scale before classifying. Without a shared scale, everyone classifies in their own way. The scale measures size by what the change asks of the population. It leaves out the effort of the team that delivers the change.

Proposed size scale.
SizeWhat the change asks of the populationExample
SmallInformation. People work as before.A report added to the menu.
MediumShort training or a modified procedure for part of the population.A new invoice approval workflow.
LargeA different way of working for a whole role. Training, support during the first weeks and a drop in productivity during adoption.The go-live of a new ERP.

The team classifies the changes population by population. A change that is large for accounting can be small for sales. A project that affects several populations keeps a schedule for each.

Reading the schedule

The team places the classified changes on a schedule that gives each period one bar. The period follows the project's rhythm: the month, the sprint or the quarter. The team then compares the schedule with the expected shape.

  • Do the large changes stay isolated? A period that holds two of them is a peak.
  • Does the period of a large change stay light? Each medium or small change added to that period adds to the load of the large one.
  • Do the medium changes pile up? A period that holds markedly more of them than the others is also a peak.
  • Does the whole schedule keep the shape? Small changes remain the most numerous and large ones the rarest.
  • Where are the gaps? A period that receives few changes is a gap.

The shape of the whole schedule is not enough. A half-year can contain many small changes and only two large ones. If the two large ones fall in the same month, that month is a peak.

The expected shape
SmallMediumLarge
A planned schedule
Number of changes
4152322Peak411Gap31
Period 1Period 2Period 3Period 4Period 5Period 6
SmallMediumLarge
On the left, the expected shape: many small changes, fewer medium ones, very few large ones. On the right, a schedule planned for one population. The third period holds two large changes and is a peak. The fifth receives a single change and is a gap. Illustrative values.

Rebalancing

Split. The team divides a large change into medium changes or a medium change into small ones. Anderson refers to Modular Thinking, which he describes earlier in the book. With Modular Thinking, the team delivers the solution in successive modules or to successive groups of users. A split by module delivers part of the solution to the whole population. A split by wave delivers the whole solution to part of the population. Anderson asks how to split two medium changes into four smaller ones. He also asks how to restructure upcoming changes into chunks that are easier to absorb.

Move. The team moves a change to a gap or postpones it until after the peak. Anderson asks whether to take on more sprints during a rollout.

Work around. Some changes lie outside the project's control: a reorganisation, a new regulation, an upheaval in the industry. The project then removes its own changes from the period that these external changes occupy. Anderson asks how to work around an upheaval in the industry.

After each answer, the team rereads the schedule. A split adds changes. A move can create a peak elsewhere.

With Time Pacing and time boxing

Anderson then describes Time Pacing. The Inverse Power Law deals with the size and frequency of changes. Time Pacing deals with the rhythms of the business. With Time Pacing, the team slows down during the busy periods of the business and places its changes in the quiet periods. Anderson advises making the peaks of the change schedule coincide with the quiet periods of the business. He also advises combining Time Pacing with time boxing to organise the work of the quiet periods.

The car manufacturer's case

Anderson illustrates the technique. At a car manufacturer, the manager of a programme of global rollouts overrides the advice of his consultants and his executive committee. His plan accounts for neither the size nor the frequency of the changes that he imposes on users who are already stretched. The sprints, the tests and the training overlap the company's planned activities and a cycle of product launches. The steering committee cancels the roadmap. A new manager re-plans the programme with the law and Time Pacing. According to Anderson, the programme still meets other difficulties, but this time the users are prepared and trained. They have time to absorb the changes.

Pitfalls

Taking the shape for a measurement. A team that computes an exponent or a ratio on its change log gives an analogy the look of a statistic. The law is a reference shape. It does not say how many changes a population absorbs.

Counting only the project's changes. The population also receives the changes of other projects, of the organisation and of regulation. A schedule limited to the project shows a gap where the population is already busy.

Measuring size by delivery effort. A two-hour configuration change can alter a whole process: a field that becomes mandatory blocks every entry. A technical overhaul of several months can stay invisible to users. The team measures size on the population's side.

Splitting without lightening the population's load. A split into four pieces that each require training yields four medium changes. The team classifies each piece with the scale before placing it.

Taking a gap for availability. A gap in the schedule is not a free period. In Switzerland, the summer holidays empty departments in July and August. A gap that falls during the holidays offers little availability. The business events placed on the schedule show this.

Rebalancing only once. Changes around the project arrive without notice. A schedule rebalanced at launch and never reread no longer shows the peaks.

AI considerations

From the release notes, the change log and the roadmaps of neighbouring projects, a language model lists the changes that affect a population. It proposes a size for each one according to the team's scale and justifies each proposal. It aggregates the sizes by period and produces the chart in a spreadsheet. It simulates a rebalancing and shows the resulting schedule.

The model cannot see what a change asks of the population. A document describes the change and rarely the training, the support or the loss of productivity that it brings. A key user validates each size. The model also misses the events that keep the population busy: period-end closings, stocktakes, absences. The steering committee arbitrates between the projects.

The roadmaps and release plans of other projects are often confidential. The team entrusts them only to an AI service that the organisation has approved for that level of confidentiality.

Examples

From March to September, the accounts payable department of a retail group in the canton of Vaud will receive eighteen changes. The ERP project delivers seventeen of them. The HR project introduces a new expense claims process in April.

Before
Number of changes
31322Peak12112
MarchAprilMayJuneJulyAugustSeptember
After
Number of changes
311113122121
MarchAprilMayJuneJulyAugustSeptember
SmallMediumLarge
From March to September, the schedule classifies the changes planned for the accounts payable department by size. Before: April has two large changes, two medium ones and three small ones. After: April keeps one large change, one medium and one small. Invented case.

Over the seven months, the shape holds: twelve small changes, four medium, two large. In April, the two large changes, two medium ones and three small ones form a peak.

Rebalancing April for the accounts payable department. Invented case.
ChangeOriginSizeBeforeAfterResponse
Rollout of the ERP supplier moduleERP projectLargeAprilAprilKept
Scanning of supplier invoicesERP projectLargeAprilReplacedSplit into two medium changes
Invoice scanning and archivingERP projectMediumNewMayFirst module of the split
Automatic reading of amountsERP projectMediumNewJuneSecond module of the split
New invoice approval workflowERP projectMediumAprilSeptemberMoved to after the summer holidays
New expense claims processHR projectMediumAprilAprilWorked around: the ERP project cannot move it
Two small data-entry changesERP projectSmallAprilMayMoved to the May gap
Small data-entry changeERP projectSmallAprilAprilKept

April keeps one large change, one medium and one small. The split brings the total to nineteen changes. July receives only one small change, but July falls in the holidays: the team moves nothing there.

Visualisations

The figure in the description compares the expected shape with a schedule that shows a peak and a gap. The size table gives the scale for classifying. The example figure shows the accounts payable schedule before and after rebalancing. The decision table states what the team did with each April change.

Cost

DimensionLevelJustification
PreparationMediumList the changes of every project that affects the population. Set the size scale with a key user.
ExecutionLowOne two-hour session to classify, read and rebalance a half-year.
DocumentationMediumThe team updates the schedule whenever a change is announced.

Tooling

A spreadsheet is enough to keep the list. Each row holds one change with its size, its period and its origin. A stacked bar chart shows the shape per period. A physical or virtual whiteboard (Miro, Mural, Microsoft Whiteboard) supports the rebalancing session. It gives each period a column and each size a sticky-note colour. Release tracking and portfolio management tools (Jira, Azure DevOps, Planview) list the changes of other projects. Anderson lists the technique among the exercises for visual collaboration.

Sources

  • George W. Anderson, Design Thinking for Tech: Solving Problems and Realizing Value in 24 Hours, Addison-Wesley, 2023. Hour 16 "Prototyping and Solutioning by Doing", section "Design Thinking in Action: The Inverse Power Law for Loading", pp. 250-252: the law, its use as a planning constraint, figure 16.4, the six questions and the reading of gaps. Same hour, section "Design Thinking in Action: Time Pacing for Interdependencies": the distinction from Time Pacing and the combination of the two. Same hour, section "What Not to Do: Ignoring the Inverse Power Law": the car manufacturer's case. Hour 11 "Guardrails for Thinking Creatively", section "Design Thinking in Action: Modular Thinking and Building": delivery by modules or by groups of users. Hour 5 "Visible and Visual Teamwork", section "Design Thinking in Action: Exercises for Visual Collaboration": the technique among the exercises for visual collaboration. Hour 23 "Making Change Sticky", section "Techniques for Timing Change": the technique among those that help choose the timing of a change.
  • NIST/SEMATECH, e-Handbook of Statistical Methods, 8.1.5.3 "Other models": a reliability model with a similar name.
  • M. E. J. Newman, "Power laws, Pareto distributions and Zipf's law", Contemporary Physics 46, 323-351, 2005: the definition of a power law and the phenomena that appear to follow one.
  • A. Clauset, C. R. Shalizi and M. E. J. Newman, "Power-law distributions in empirical data", SIAM Review 51, 661-703, 2009: the tests that confirm or rule out a power law on 24 data sets.

Newman and Clauset describe the power laws whose shape Anderson borrows. The size scale, the reading, the steps, the pitfalls and the accounts payable case are our proposals.