Influence Diagrams
An influence diagram is a directed graph with no loops that models a decision under uncertainty. A rectangle marks each decision. An oval marks each uncertain variable. A diamond marks the value that the decision maker optimises: a cost, a duration, a gain. According to Howard and Matheson, an arrow into a decision shows what the decision maker knows at the moment of choosing. An arrow into an oval shows which variables its probability depends on. The PMBOK Guide places the technique in risk analysis: the team quantifies the diagram and a Monte Carlo simulation then shows which elements affect the result most.
Goal
The PMBOK Guide defines the influence diagram as a graphical representation of a decision situation under uncertainty. According to the guide, the diagram shows causal influences, the time ordering of events and other relationships among variables and outcomes. The diagram supports the decision with calculations: the option with the best expected value, the elements that affect the result most and what it is worth to test before deciding.
Howard and Matheson described the notation. It grew out of work at SRI International in the 1970s. For them, the diagram is a formal description that a computer can process. It is also a representation that people of any occupation and any level of technical skill understand. The diagram links the qualitative description of a problem to its quantitative specification.
The deliverables are the diagram with the definition of each node, the table that quantifies the nodes and the result of the evaluation: the recommended decision, the S-curve or the tornado diagram.
Usage
When to use it
- Decision under uncertainty with several linked variables: show what depends on what before quantifying.
- Quantitative risk analysis of a cost or a schedule: structure the risk factors before the Monte Carlo simulation.
- Whether to run a test, audit or study before the main choice: calculate what the information is worth and compare it with its cost.
- Experts and decision makers who must agree on the structure: discuss the nodes and arrows before any number.
- Decision tree that runs off the page: the diagram keeps one node per variable whatever the number of paths.
- Risk factor shared by several cost items: draw it once so that it is not counted twice.
When not to use it
- Question about a feedback loop: the diagram forbids loops; system dynamics models them.
- Repeatable decision governed by known rules: there is no probability to set; decision modelling describes it in a table or a rule tree.
- Probabilities that neither data nor an expert can estimate: a quantified evaluation would have no basis; a qualitative risk analysis ranks the risks without figures.
Description
The elements of the diagram
Howard and Matheson define two node types: the rectangle for a decision and the circle for an uncertain variable. In their notation the value is a variable. Bielza, Gómez and Shenoy describe the common convention. It has three node types and gives the value its own shape.
| Element | Shape | What it asserts |
|---|---|---|
| Decision node | Rectangle | A choice that the decision maker controls. Each option is a value of the node. |
| Chance node | Oval | An uncertain variable. It receives a probability distribution. |
| Value node | Diamond | The criterion to optimise. It has no successor. |
| Information arrow | Arrow into a decision | The source variable is known at the moment of choice. |
| Conditioning arrow | Arrow into a chance node | The probability of the node depends on the source variable. |
| Arrow to the value node | Arrow into the value node | The value is calculated from the source variable. |
The node that an arrow enters sets its meaning. The parents of a node are the nodes from which an arrow leads to it. A node without parents is an input node. Howard and Matheson call an arrow into a decision an information arrow and an arrow into a chance node a conditioning arrow. In their definition, the decision maker sees only the parents of the decision.
A missing arrow is an assertion. According to Howard and Matheson, the diagram asserts that the influences it does not draw do not exist: without an arrow between two variables, no direct dependence links them. The successors of a node are the nodes that a path of arrows reaches from it. Once the parents of a chance node are known, the variables that are not its successors add nothing to its probability.
The graph contains no loop. Howard and Matheson forbid loops because a loop leaves no order in which to condition the probabilities.
The decisions form a sequence. In the convention with three node types, a directed path passes through every decision and fixes their order. The decision maker forgets nothing. At the second decision they still know what they knew at the first.
Two readings of the same technique
In the PMBOK Guide, the diagram models a project as a set of entities, outcomes and influences. An uncertain element receives a range or a probability distribution. Its uncertainty comes from a project risk or from another source. A Monte Carlo simulation evaluates the diagram and shows which elements affect the result most. The outputs are those of the other quantitative risk analysis methods: the S-curve and the tornado diagram.
Decision analysis starts from the decision. Howard and Matheson use the diagram to show the probabilistic dependences of a decision analysis and what the decision maker knows at the moment of choosing. They also use it to specify the states of information under which an independence is assumed. The evaluation calculates the strategy with the best expected value: for each decision, the option to take given the information available.
Shams and Fayek apply the influence diagram to the cost of a construction project. Their diagram generally holds chance nodes and a value node. When a decision arises, they evaluate one scenario per option and compare the results.
Building the diagram
The order of the steps is a synthesis.
Howard and Matheson distinguish three levels of specification. The relation says what depends on what: income depends on age and education. The function gives the form of the dependence: the distribution of income for each age and each level of education. The number sets the unconditional distributions and the values. The distribution of age is one of them. Step 3 sets the relation. Step 4 sets the function and the number.
- Name the decision and the value. Write down the choice to make and its options. Set the criterion that decides between them: a total cost in francs, a go-live date, a gain.
- List the variables. Identify the decisions linked to the first one and the uncertain variables that affect the value. For a cost, Shams and Fayek start from the cost item and trace the risk factors back up to project level.
- Draw the arrows. Link each chance node to the variables its probability depends on. Link each decision to the variables known at the moment of choice. Check that the graph has no loop. Each missing arrow must match an independence that the experts accept.
- Quantify. Give each chance node one distribution per combination of its parents' values. In the PMBOK Guide reading, an uncertain element can receive a range instead of a distribution. Write the value function: the cost of each combination of options and outcomes.
- Evaluate. List each combination of outcomes with its joint probability: the probability of an outcome multiplied by the probability of the observed result given that outcome. For each result that the decision maker can observe, multiply the value of each option by the joint probability of each matching combination and add up the products. Keep the best option. Add the kept sums to the cost of the information to obtain the expected value of the strategy. If the nodes carry ranges, run a Monte Carlo simulation.
- Measure the value of information. Add an information arrow into the decision and evaluate again. The difference in expected value is the value of the information.
According to Howard and Matheson, different people can fill in the successive levels. In their example, an executive knows that sales depend on price. The executive leaves the probabilistic description of this link to others. The following division of work is a synthesis: the analyst draws the arrows in a workshop with the decision makers and the experts, then quantifies each node with the expert who knows the variable.
Measuring the value of information
Howard and Matheson model perfect information, which they call clairvoyance, with an information arrow added from an uncertain variable to the decision: the decision maker knows the variable before choosing. In their model, an imperfect test becomes one more chance node. An arrow enters it from the variable that it measures. Another leaves it towards the decision.
For them, the value of perfect information is the upper limit of what a test, an audit or a study can be worth. A study that costs more than this limit is not justified.
Howard and Matheson work through the numbers for a chemical suspected of causing cancer. The decision maker can ban it, restrict its use or permit it. A substitute process costs USD 1 million under a restriction and USD 5 million under a ban. The best decision is to restrict. Its expected cost is USD 2.2 million. If the decision maker knows the carcinogenic activity before choosing, the expected cost falls to USD 1.1 million: perfect information on the activity is worth USD 1.1 million. On human exposure, it is worth USD 0.4 million. On both variables, it is worth USD 1.38 million. This is less than the sum of the two separate values. A free laboratory test of the activity brings the expected cost down to USD 1.96 million. The text of §15.2 derives a value of USD 0.24 million from it. This amount is the highest price that the decision maker should pay for the real test. An imperfect test of exposure is worth zero because the decision remains a restriction whatever the test shows.
Influence diagram, decision tree and causal loops
The decision tree handles the same decision with another notation. The PMBOK Guide lists both among the data analysis techniques of risk analysis. It evaluates the tree by the expected monetary value of each branch.
| Influence diagram | Decision tree | Causal loop diagram | |
|---|---|---|---|
| What it shows | The dependences between variables and the information available at each decision | Every possible sequence of choices and outcomes | The feedback loops of a system |
| Order imposed | In the common convention, the decisions | All the variables | None |
| Loops | Forbidden | Impossible by construction | The subject of the model |
| Size of the drawing | One node per variable | One path per combination of choices and outcomes | One node per variable |
The tree fixes the order of every variable. According to Howard and Matheson, this order is rarely the natural order in which to assess the decision maker's probabilities. The nodes of the diagram need not follow a complete order. This freedom makes probability assessment and computation easier. Howard and Matheson do not impose the order of decisions that the common convention fixes. They call a diagram that orders all its decisions with no forgetting a decision network. A decision network converts into a tree after a probability calculation where needed. Some diagrams have no equivalent tree, for example two decisions taken on disjoint information.
A two-state variable adds one node to the diagram. It doubles the number of paths in the tree. The municipality example fits in five nodes. Its tree has twelve paths.
System dynamics models what the influence diagram excludes: loops. The BPM CBOK describes it through causal and feedback loop diagrams, which give an overall view of the organisation.
Pitfalls
Reading every arrow as a cause
The PMBOK Guide speaks of causal influences. For Howard and Matheson, an information arrow expresses an order of cause and effect. A conditioning arrow only says which variable a probability depends on. Its direction follows a partly arbitrary order of conditioning that Bayes' rule can change. In the municipality example, the error rate in the records conditions the audit result. Bayes' rule reverses this arrow and gives the probability of the error rate given the result. Both directions carry the same information provided the analyst first adds the arrow that gives the two nodes the same information base. In the workshop, an analyst who reads every arrow as a cause argues for a causal link that the model does not assert.
Crediting the decision maker with information they will not have
According to Howard and Matheson, an information arrow asserts that the variable is known at the moment of choice, whatever option is taken. The result of a test carried out after the purchase cannot enter the decision to buy. The correct model adds an upstream decision: run the test or not. The test result then enters the second decision. Howard and Matheson treat the buyer of a used car in this way. In their example, testing the car is a decision taken before the purchase. The municipality example follows this structure.
Removing an arrow to simplify
Each parent added to a chance node multiplies the number of distributions to quantify. According to Howard and Matheson, an added arrow introduces no false assertion. It can only hide an independence. A cut arrow asserts an independence and can therefore introduce a false assertion. Bielza, Gómez and Shenoy note that an arc removed to simplify the model can distort the picture of the problem. Before cutting, the analyst asks the expert whether the source variable changes the node's probability.
Drawing a loop
A loop appears when the team models a feedback effect: the delay increases the pressure on the team, the pressure increases the errors, the errors increase the delay. The influence diagram cannot evaluate it. The analyst can split the loop into periods: the delay in month 1 affects the errors in month 2. If the feedback is the subject of the study, the analyst moves to a system dynamics model.
Counting a factor twice
Shams and Fayek describe this defect in Monte Carlo simulations run item by item. The weather appears in the base estimate of a cost item. The risk analysis counts it a second time. An item-by-item simulation also ignores the factors common to several items. The diagram draws each factor once with an arrow to each item it affects. The double counting becomes visible.
AI considerations
A language model produces a first list of nodes and arrows from the risk register, the assumptions of an estimate and the interview minutes. Each arrow that it proposes or omits is an assertion that the analyst puts to the expert for that node.
The language model writes the calculation: a script or a spreadsheet that enumerates the strategies, calculates the expected value of each and applies Bayes' rule. It also writes the check for loops. The analyst verifies the calculation on a case whose answer they know. According to Howard and Matheson, the value of an imperfect test never exceeds the value of perfect information.
When asked for a probability, a language model gives a plausible figure with no data behind it. The probabilities come from the organisation's data or from the expert who knows the variable. A sample of records from the residents' registration office contains personal data. It stays out of online services whose terms of use the organisation does not control.
Examples
A municipality in the canton of Vaud is migrating the register of its residents' registration office to new software. It can switch directly or clean the records before the switch. Before choosing, it can audit a sample of records. The diagram shows what the audit changes: its result enters the choice of migration mode. The numbers are fictitious.
| Low error rate (probability 0.6) | High error rate (probability 0.4) | |
|---|---|---|
| Cost of direct switch | CHF 80'000 | CHF 200'000 |
| Cost of clean-up then switch | CHF 130'000 | CHF 140'000 |
| The audit finds many errors | probability 0.1 | probability 0.8 |
| The audit finds few errors | probability 0.9 | probability 0.2 |
| No audit | probability 1 when the municipality does not audit | |
| Cost of the audit | CHF 6'000 | |
| Strategy | Calculation | Expected cost |
|---|---|---|
| Direct switch without audit | 0.6 × 80'000 + 0.4 × 200'000 | CHF 128'000 |
| Clean-up without audit | 0.6 × 130'000 + 0.4 × 140'000 | CHF 134'000 |
| If the audit finds few errors: share of the expected cost of each mode | Switch: 0.54 × 80'000 + 0.08 × 200'000 = 59'200. Clean-up: 0.54 × 130'000 + 0.08 × 140'000 = 81'400. | Direct switch kept: CHF 59'200 |
| If the audit finds many errors: share of the expected cost of each mode | Switch: 0.06 × 80'000 + 0.32 × 200'000 = 68'800. Clean-up: 0.06 × 130'000 + 0.32 × 140'000 = 52'600. | Clean-up kept: CHF 52'600 |
| Audit, then mode chosen on its result | 6'000 + 59'200 + 52'600 | CHF 117'800 |
| Error rate known before the choice (perfect information) | 0.6 × 80'000 + 0.4 × 140'000 | CHF 104'000 |
Without an audit, the municipality switches directly at an expected cost of CHF 128'000. Excluding the cost of the audit, the strategy with audit costs CHF 111'800 on average. The audit information is therefore worth CHF 128'000 − CHF 111'800 = CHF 16'200. The audit costs CHF 6'000: the municipality saves CHF 10'200 on average. The coefficients in the two rows "If the audit finds…" are the joint probabilities, for example 0.54 = 0.6 × 0.9 for a low rate and an audit that finds few errors.
The diagram also carries a dashed arrow from the error rate to the migration mode. It measures the value of perfect information: CHF 24'000. However accurate the audit, its information is worth at most CHF 24'000. The audit information is worth CHF 16'200 and stays below this limit.
Visualisations
According to Shams and Fayek, the diagram of a cost generally holds chance nodes and a value node. Each input node shows its range.
The simulation draws a value from each range and recalculates the cost of the migration. It produces the cost S-curve and the tornado diagram that ranks the input nodes. You will find the S-curve under Monte Carlo simulation and the tornado diagram under sensitivity analysis.
Cost
| Phase | Level | Rationale |
|---|---|---|
| Preparation | Medium | Name the decision and the value, list the variables, bring together the decision makers and the experts who know each variable. |
| Execution | High | One workshop is enough to draw the arrows. Quantification requires one distribution per combination of parent values for each chance node. The evaluation requires a tool. |
| Documentation | Medium | The diagram, the definition of each node, the origin of each number and the result of the evaluation. |
Tools
A whiteboard is enough to draw the nodes and arrows in a workshop before any number.
A diagramming tool produces a clean copy of the model. It checks neither the absence of loops nor the consistency of the probabilities.
A spreadsheet evaluates a small model: one row per combination of outcomes with its joint probability and its cost, then one sum per strategy. The municipality's model fits on one sheet.
The simulation tools used for Monte Carlo simulation evaluate a diagram whose nodes carry ranges. They output the S-curve and the tornado.
Decision analysis software that supports influence diagrams evaluates them on the graph. It calculates the value of information and converts the diagram into a tree. Howard and Matheson describe an automated system that builds the tree from the diagram. The user supplies only the initial probabilities. Analytica (Lumina) builds the model as an influence diagram and evaluates it by Monte Carlo simulation when the nodes carry ranges. GeNIe Modeler (BayesFusion) calculates the value of information of a variable observed before the decision. PrecisionTree (Lumivero) adds influence diagrams and decision trees to Excel. In Python, the ShaferShenoyLIMIDInference class of pyAgrum evaluates an InfluenceDiagram in a script.
Sources
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., §2.7.2.3 Perform Risk Analysis (figure 2-50) and Section 5, entries Influence diagrams and Decision tree analysis (figure 5-5): the definition, uncertain elements as ranges or distributions, evaluation by Monte Carlo simulation, the S-curve and the tornado diagram as outputs, the decision tree evaluated by expected monetary value.
- R. A. Howard and J. E. Matheson, "Influence Diagrams", Decision Analysis 2(3), 2005, pp. 127-143: the definition of the diagram as a directed graph with no loops, the two types of arrows, the missing arrow as an assertion, the three levels of specification, the relation to the decision tree, the value of perfect and imperfect information (the toxic chemicals example).
- C. Bielza, M. Gómez and P. P. Shenoy, "Modeling challenges with influence diagrams: Constructing probability and utility models", Decision Support Systems 49, 2010, pp. 354-364: the convention with three node types, the value node as a diamond, the order of the decisions and the risk of removing an arc to simplify the model.
- ABPMP, Guide to the Business Process Management Common Body of Knowledge (BPM CBOK), §3.4.3 System Dynamics: the causal and feedback loop diagrams of system dynamics.
- F. Shams and A. R. Fayek, "A proposed approach for construction project cost risk analysis using influence diagrams", 4th Construction Specialty Conference, Canadian Society for Civil Engineering, Montreal, 2013: the diagram of a project cost built from the cost item towards the risk factors and the double counting of item-by-item simulations.