Techniques Toolbox
Cumulative curves of a CHF 100'000 project over ten months. Cumulative planned value rises to the budget at completion. At the status date at the end of month 4, planned value stands at CHF 40'000, earned value at CHF 32'000 and actual cost at CHF 36'000. The schedule variance measures CHF −8'000. The cost variance measures CHF −4'000. A dashed line extends actual cost to an estimate at completion of CHF 112'500. That estimate exceeds the budget by CHF 12'500.

Earned value management

Earned value management (EVM) measures the state of a project by comparing three amounts at one date. Planned value (PV) is the budget for the work scheduled up to that date. Earned value (EV) is the budget for the work completed. Actual cost (AC) is what that work cost. The variances between these amounts measure cost and schedule performance in francs. The same amounts also forecast the final cost. The method comes from the C/SCSC (Cost/Schedule Control Systems Criteria) that the US Department of Defense introduced in the 1960s.

Goal

Earned value management is a project control method. At each status date it compares the budget for the work planned with the budget for the work completed and with the cost of that work. The project manager uses it to answer two questions. Has the project produced the work planned for this date? Has it spent on that work what the budget allowed?

Ordinary budget tracking compares spending with the budget. It does not measure progress. A project that has spent 36% of its budget at 40% of its duration looks under control. It is under control on cost if the work completed is worth at least what it cost. It is under control on schedule if that work reaches the work planned for this date. Earned value supplies this third measure in the same unit as the other two.

The variances and indices inform the decisions of the steering committee: a corrective action, a change request, a baseline revision, a request for additional funding. The deliverable is an earned value report per work package and for the whole project. It carries the three values, the variances, the indices and the estimate at completion.

The PMBOK Guide places earned value analysis among the tools of two processes: Monitor and Control Finances and Monitor and Control Schedule. The HERMES 2022 task "Manage and control project" calls for a periodic check of progress based on the plan and on the degree of completion of the outcomes. The task compares planned with actual and forecasts effort, cost and dates. Earned value puts figures on this check.

Usage

When to use it

  • Approved cost and schedule baseline: in a predictive or hybrid approach, the budget is broken down into dated work packages.
  • Report to the steering committee: cost and schedule read in a single unit for each work package and for the project.
  • Final cost forecast requested: the estimate at completion puts a figure on the need before a request for additional funding.
  • Capped budget or fixed price: the cost index signals an overrun while budget remains to correct it.
  • Work packages placed with several suppliers: a common measurement rule consolidates progress reported in different ways.
  • Iterations in a hybrid project: report the francs spent against the story points completed.

When not to use it

  • No costed baseline per work package: without planned value there is nothing to compare; track delivered scope with a burnup.
  • Costs not chargeable to work packages: if time recording does not break down by work package, actual cost remains unknown; track progress alone on a Gantt chart with a status date.
  • Short project with low stakes: setting up the measurement costs more than the variance it would detect; track milestones and spending in a project status report.

Description

The three values

Planned value (PV) is the authorised budget for the work scheduled up to the status date. It excludes the management reserve. Accumulated over the duration of the project, it forms the performance measurement baseline (PMB). Its total is the budget at completion (BAC).

Earned value (EV) is the budget for the work completed at the same date. The PMBOK Guide specifies that the EV of a component never exceeds its authorised PV: a completed CHF 30'000 work package earns CHF 30'000 of EV, whatever it cost.

Actual cost (AC) is what the work measured by EV cost. It has no ceiling. It must follow the definition chosen for PV and EV: direct hours only, direct costs only or full costs including overheads. An AC at full cost compared with a PV in direct hours produces an overrun that comes only from the mismatch.

Older literature calls these values BCWS (budgeted cost of work scheduled), BCWP (budgeted cost of work performed) and ACWP (actual cost of work performed). The PMBOK Guide uses PV, EV and AC.

Variances and indices

The three values give two variances and two indices. A variance is expressed in francs. An index is a ratio. It can be compared between work packages or projects of any size.

MeasureFormulaReading
Cost variance (CV)EV − ACPositive: the work completed cost less than its budget. Negative: overrun.
Schedule variance (SV)EV − PVPositive: more work completed than planned. Negative: delay.
Cost performance index (CPI)EV / ACAbove 1: each franc spent produces more than one franc of budgeted work.
Schedule performance index (SPI)EV / PVAbove 1: the project is progressing faster than planned.
Earned value variances and indices, after table 5-1 of the PMBOK Guide.

An SV of CHF −8'000 means that the project has completed CHF 8'000 less budgeted work than planned. It does not give the delay in days.

Preparing the measurement

The project manager prepares the measurement during planning and starts from the work breakdown structure (WBS). Each work package receives a budget and dates. The work packages roll up into control accounts. A control account is a point in the WBS where the project compares budget, progress and cost. The sum of the time-phased budgets gives the PMB.

The financial management plan then sets the performance measurement rules. In the PMBOK Guide, these rules include the measurement points in the WBS, the progress rule of each work package and the EAC formulas. The same plan sets the control thresholds as a percentage of variance from the baseline. For example, a CPI or SPI below 0.90 triggers an analysis of the causes. The project chooses the threshold and adds the definition of actual cost.

The progress rule determines the EV.

RuleEarned value creditedSuits
Fixed formulaA fixed share of the budget when the work package starts, the rest when it finishes: 0/100, 50/50.Short work packages that fit within one or two reporting periods.
Weighted milestonesEach milestone reached earns the share of the budget assigned to it.Long work packages broken down into verifiable outcomes.
Percent completeThe percentage completed multiplied by the budget of the work package.Work that is counted in quantities: records migrated, metres laid, test cases executed.
Progress rules named by the PMBOK Guide and the earned value that each one credits.

Percent complete estimated by expert judgement is the first trap. A work package owner reports 60%, then 80%, then 90% over several status dates. EV then rises faster than the work. The remedy is a physical measure: a counted quantity or a milestone whose outcome can be verified. Each WBS component receives a measurement criterion. A work package without a criterion produces EV that nobody can verify.

The second trap is to count work that does not meet its acceptance criteria. A module delivered and then rejected in user acceptance testing (UAT) has consumed its budget without producing value. We recommend counting a milestone only once its outcome is accepted.

Collecting the data at each status date

For each work package the project collects actual cost and physical progress. The project manager calculates EV with the rule of the work package and reads PV from the baseline at the same date. From these the project manager calculates the variances and the indices and compares each index with its threshold.

The project manager tracks EV for the period and cumulatively. The period value shows the present state. The cumulative value shows the trend. A cumulative CPI of 0.89 in the fourth month, after 0.94 and 0.92 at the two previous status dates, describes a drift. A single period CPI below the threshold may come from an invoice booked late.

A common trap is that accounting lags behind the work delivered. A supplier invoice arrives a month after the service. The actual cost of the period is then too low, then too high. The remedy is to add to actual cost the services received and not yet invoiced, which accounting books as accrued liabilities (accruals).

Forecasting the final cost

The estimate at completion (EAC) is the expected total cost of the project. It adds the actual cost and the estimate to complete (ETC). The variance at completion (VAC) compares the budget with this estimate: VAC = BAC − EAC.

The PMBOK Guide gives four EAC formulas. Each assumes a different cause for the observed variance. The project manager therefore chooses the formula according to the cause that the analysis has established.

Assumed cause of the varianceFormulaEACVAC
The observed cost efficiency continuesBAC / CPICHF 112'500CHF −12'500
The variance is a one-off and the rest runs at the planned rateAC + (BAC − EV)CHF 104'000CHF −4'000
Both cost and delay weigh on the restAC + (BAC − EV) / (CPI × SPI)CHF 131'625CHF −31'625
The original plan no longer holdsAC + estimate to complete re-estimated per work packageto be re-estimatedto be re-estimated
EAC formulas of the PMBOK Guide applied to a budget of CHF 100'000 with an earned value of CHF 32'000, an actual cost of CHF 36'000, a CPI of 32'000 / 36'000 and an SPI of 0.80.

The three calculated formulas give CHF 104'000 to CHF 131'625 for the same status data. The gap of CHF 27'625 between the lowest and the highest comes only from the assumed cause. The trap is to adopt the most favourable formula. The second formula gives the lowest EAC. It assumes that the cause of the overrun has disappeared. It holds only if someone can name that cause and say why it will not return.

The last row corresponds to a bottom-up estimate of the remaining work. The formulas check this estimate per work package for plausibility. A bottom-up EAC of CHF 105'000 against a CPI of 0.89 calls for an explanation: what will make the remaining work more efficient than the work already done?

The performance required of the remaining work

The TCPI (to-complete performance index) is the cost performance index that the remaining work must achieve to meet a target. It divides the remaining work by the remaining funds. To stay within the budget, TCPI = (BAC − EV) / (BAC − AC). To meet an approved EAC, TCPI = (BAC − EV) / (EAC − AC).

The index required of the remaining work
The index required of the remaining work0.800.850.900.951.001.051.101.15012345678910MonthIndexBaseline 1.00Status dateCumulative CPI 0.89TCPI (BAC) 1.06TCPI (EAC CHF 112'500) 0.89The index required of the remaining work0.800.850.900.951.001.051.101.15012345678910MonthIndexBaseline 1.00Status dateCumulative CPI 0.89TCPI (BAC) 1.06TCPI (EAC CHF 112'500) 0.89
The cumulative CPI has fallen to 0.89 at the end of month 4. To stay within the budget of CHF 100'000, the remaining work must reach an index of 1.06. To meet the EAC of CHF 112'500, an index of 0.89 is enough.

With a budget of CHF 100'000, an EV of CHF 32'000 and an AC of CHF 36'000, CHF 68'000 of work remains for CHF 64'000 of funds. The TCPI on the budget is 1.06. The team has worked at 0.89 so far. According to the PMBOK Guide, the project manager judges whether this level is attainable in light of the risks, the time remaining and the technical performance. Our reading: a TCPI well above the cumulative CPI signals a budget that will not hold without a change of scope or of organisation. The TCPI calculated on the EAC of CHF 112'500 is 0.89. It equals the CPI because this EAC assumes that the observed efficiency continues.

The limits of the schedule index

The SPI loses its meaning towards the end of a project. When all the work is complete, EV and PV both equal the BAC. The SPI returns to 1.00 even if the project finished two months late. The SV returns to zero for the same reason. The closer the project gets to its end, the less the SPI tells a late project from one on time.

Walt Lipke proposed measuring the delay in time. Earned schedule (ES) is the point in the plan at which PV reached the current EV. The schedule variance in time is SV(t) = ES − AT, where AT is the actual time elapsed. The corresponding index is SPI(t) = ES / AT. At the end of month 4 the EV of CHF 32'000 lies between the PV of month 3 (CHF 21'000) and that of month 4 (CHF 40'000): ES = 3 + (32'000 − 21'000) / (40'000 − 21'000) = 3.58 months. SV(t) is then −0.42 months and SPI(t) 0.89. SV(t) stays negative and SPI(t) stays below 1 until the end of a late project. Earned schedule extends the method.

The delay in francs and in time
At the end of month 4
At the end of month 4020'00040'00060'00080'000100'0000123456MonthCumulative CHFPV CHF 21'000SV CHF −8'000EV CHF 32'000SV(t) −0.42 monthsES 3.58 monthsAT 4 months
SPI 0.80SPI(t) 0.89
Project finished in month 12
Project finished in month 12020'00040'00060'00080'000100'0000123456789101112MonthCumulative CHFPVEVES 10 monthsAT 12 months
SPI 1.00SV CHF 0SPI(t) 0.83
At the end of month 4, the EV of CHF 32'000 equals the PV of the plan at 3.58 months. The delay amounts to CHF 8'000 and 0.42 months. On a project finished in month 12 instead of month 10, the SPI returns to 1.00. The SPI(t) is 0.83.

The SPI also aggregates all the work of the project. A non-critical work package ahead of schedule offsets a critical work package behind schedule. The project SPI then stays close to 1 while the finish date slips. The project manager judges the schedule on the critical path. Earned value says how much work is missing. The network says whether that work delays the finish.

Scope changes and rebaselining

An approved change modifies the PMB through change control. The budget of added work enters PV. The budget of removed work leaves it. The trap is a rebaseline that absorbs an overrun. The project resets the baseline to the observed state. The cumulative variances fall back to zero and the indices restart at 1. The variance has disappeared from the report without disappearing from the project. A change of scope or a plan that has become unrealistic justifies a rebaseline. The project manager documents it together with the cumulative variances that it resets to zero.

In an adaptive approach

The PMBOK Guide applies earned value to work measured in story points. PV is the total story points of the user stories planned up to a date, which is usually the end of the iteration. EV is the total story points of the stories completed at that date. AC comes from the cost of the team during the iteration, which is usually derived from hours of work. PMI's The Standard for Earned Value Management gives the detail.

The burnup answers the same question about scope and date. It does not carry cost. Earned value complements the burnup when the project must report the francs spent against the work delivered. It then requires a release scope estimated in points, without which PV does not exist.

The limits of the method

According to the EVM tutorial of the US Department of Energy, the method requires detailed planning up front and imposes a burden of data collection and processing. It also exposes the team to the risk of managing the indicators rather than the project. A work package owner who knows that their CPI will be read starts with the tasks that earn EV quickly. EV rises while the difficult tasks wait.

AI considerations

The calculation needs no artificial intelligence. A spreadsheet calculates the variances, the indices and the EACs of the three formulas.

A language model helps before the calculation. From an export of the accounting system it proposes how to assign the entries to the control accounts. It flags the entries that it cannot assign. It spots the inconsistencies in a report: an EV above the total PV of a work package, a work package reported at 90% over four status dates, an AC at full cost against a PV in direct hours. It drafts a first commentary on the variances work package by work package, which the project manager corrects.

The work package owner and whoever accepts the deliverable decide on progress and on the acceptance of a milestone. The EAC formula depends on the cause of the variance. That cause lies in the project: a failing supplier, a wrong assumption, a team member who leaves. A model that chooses the formula from the indices alone adopts an assumption that it cannot verify.

Hours recorded per employee are personal data within the meaning of the Federal Act on Data Protection (FADP). Hourly rates are confidential. Neither goes into a public AI service. A report aggregated by work package without names or rates is enough to analyse the variances.

Examples

A vocational school is replacing its enrolment management software. The budget is CHF 100'000 over ten months. The report dates from the end of the fourth month. The project manager calculates the EV of each work package with its progress rule. The rows locate the variance. The total quantifies it.

Work packageBACProgress ruleMeasured progressPVEVACCVSV
Requirements analysis15'000Fixed formula 50/50Complete15'00015'00016'000−1'0000
Configuration30'000Weighted milestones: 20, 20, 20, 15 and 25%2 of 3 planned milestones reached18'00012'00014'000−2'000−6'000
Data migration20'000Percent complete25% of records migrated and checked7'0005'0006'000−1'000−2'000
User acceptance testing (UAT)20'000Fixed formula 50/50Not started00000
Training and go-live15'000Fixed formula 50/50Not started00000
Project100'00040'00032'00036'000−4'000−8'000
Project indicesCPI 0.89SPI 0.80
Earned value report at the end of month 4 in francs, per work package, with the progress rule of each work package.

The project has spent 36% of its budget at 40% of its duration. The report shows that it has produced only 32% of the budgeted work. Configuration carries CHF 6'000 of the schedule variance and migration the remaining CHF 2'000. The cost overrun affects all three work packages that have started.

Planned value, earned value and actual cost
Status at the end of month 4 of a CHF 100'000 project over ten months
Planned value, earned value and actual cost020'00040'00060'00080'000100'000120'000012345678910Planned finishMonthCumulative CHFBAC CHF 100'000Status datePV CHF 40'000AC CHF 36'000EV CHF 32'000CV CHF −4'000SV CHF −8'000VAC CHF −12'500EAC CHF 112'500Planned value (PV)Actual cost (AC)Earned value (EV)Planned value, earned value and actual cost020'00040'00060'00080'000100'000120'000012345678910Planned finishMonthCumulative CHFBAC CHF 100'000Status datePV CHF 40'000AC CHF 36'000EV CHF 32'000SV CHF −8'000CV CHF −4'000VAC CHF −12'500EAC CHF 112'500Planned value (PV)Actual cost (AC)Earned value (EV)
At the end of month 4, the project has completed CHF 32'000 of work out of the CHF 40'000 planned. That work cost CHF 36'000. If the observed cost efficiency continues, the project will cost CHF 112'500.

Visualisations

The cumulative curves of PV, EV and AC show both variances at the status date and the forecast of the final cost. The TCPI chart places the index required of the remaining work above the CPI achieved. The earned schedule chart reads the same delay first in francs and then in months. It also shows the SPI back at 1 on a project that finished late. The formulas, the progress rules, the estimates at completion and the report per work package are tables.

Cost

PhaseLevelRationale
PreparationHighBreak the project down into budgeted and dated work packages, choose a progress rule per work package, align the definition of actual cost with accounting.
ExecutionMediumAt each status date, record the cost and the physical progress of each work package, then calculate. Time recording by work package must already exist.
DocumentationMediumOne report per period, the analysis of the variances beyond the thresholds and the history of baseline changes.

Tooling

A spreadsheet is enough for a project of a few dozen work packages. One row per work package carries the BAC, the progress rule and the successive reports. The variances, the indices and the EACs of the three formulas recalculate with each report.

Scheduling software calculates earned value from the schedule and the costs entered. Microsoft Project calculates it in its earned value fields (BCWS, BCWP and ACWP). Oracle Primavera P6 calculates it per activity and per WBS element. These tools suit a project whose baseline is already saved in the schedule.

Actual cost comes from the accounting system or from the project module of an ERP, which charges hours and invoices to the work packages. The earned value calculation is only as good as this charging. Programmes that consolidate many control accounts and suppliers use dedicated tools such as Deltek Cobra.

Sources

  • PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., §2.4.2.4 "Monitor and Control Finances": earned value analysis, trend analysis and the TCPI among the tools of the process, the forecasts and the baseline update among its outputs. §2.3.2.3 "Monitor and Control Schedule": the same analysis applied to schedule control. Section 4, financial and schedule management plans: the performance measurement rules, the progress rules, the EAC formulas as a check on the bottom-up estimate, the control thresholds. Section 5, entries "Earned value (EV) analysis" and "To-complete performance index (TCPI)", table 5-1 "Earned Value Calculations Summary" and figure 5-24: the definitions of PV, EV and AC, earned value applied to work measured in story points, the formulas and their interpretation.
  • PMI, The Standard for Earned Value Management, 2019: the PMI standard on the method, to which the PMBOK Guide refers.
  • ISO, ISO 21508:2018, Earned value management in project and programme management: guidance on earned value management for any organisation, project or programme.
  • U.S. Department of Energy, Earned Value Management Tutorial, Module 1: the origin of the method in the C/SCSC criteria of the 1960s, the steps of its implementation, its limits.
  • Walt Lipke, Earned Schedule: Ten Years After: earned schedule, the variance SV(t) = ES − AT and the index SPI(t) = ES / AT.
  • Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management Reference Manual, task 5.4.3.33 Manage and control project: the periodic check of progress, the comparison of planned with actual, the forecast of effort, cost and dates.
Drawing Together