Dot plot of the approval lead time of 24 purchase requests on an axis from 0 to 20 working days. Dots with equal values are stacked. A cluster of 15 requests sits between 2 and 6 days. The highest stack is at 4 days. A cluster of 8 requests sits between 9 and 12 days. One isolated request sits at 19 days. The mean of 6.75 days falls in the gap between the two clusters.

Dot plot

A dot plot (also called a strip plot) is a chart that places one dot per value of a measurement on an axis with a numeric scale. Dots with equal values are stacked or shifted so that each one stays visible. The chart shows the centre, the spread, the clusters, the gaps and the isolated values of a small data set without summarising them. Each dot remains an observation that the analyst can trace back to the source. With a few dozen values, the dot plot replaces the histogram and the box plot. It loses the order of the measurements, which the run chart follows.

Goal

The dot plot is a chart with a single axis. Each observation becomes a dot placed at its value. Leland Wilkinson notes that such charts have shown distributions in detail for more than a hundred years. In its Dataplot reference manual, the National Institute of Standards and Technology (NIST) presents the dot plot as an alternative to the histogram for small data sets. The dot plot is one of the charts of exploratory data analysis.

The dot plot checks whether a mean describes the units: it shows whether the values form one cluster, two clusters with a gap between them or one cluster with a few isolated values. Each dot is an observed unit: a case file, a part, a call.

The deliverable is the chart with the number of values, the period and the source. A written comment goes with it: what the chart shows and the decision that follows from it. The analyst may decide to separate two populations, open an unusual case file, compare the situation before and after a change or collect enough values for a histogram.

Usage

When to use it

  • A few dozen values: show each value on the axis instead of drawing a histogram.
  • A mean to publish: check that the mean does not fall between two clusters before it is published.
  • Small groups to compare: two teams, two sites or the periods before and after a change are read on the same axis.
  • Pilot or first data collection: read the first values of a new process before there are enough for a histogram.
  • An unusual value to trace: each dot leads to a case file, a part or a call that the analyst can reopen.
  • Workshop without software: the team draws the axis on the whiteboard and marks one cross per value.

When not to use it

  • Large data set: the dots merge into a continuous band. Use the histogram.
  • A question about change over time: the dot plot loses the order of the measurements. Use the run chart or the control chart.
  • Data by category: complaint reasons are counted and sorted in a Pareto chart.

Description

The elements

The axis carries the measurement in days, Swiss francs or millimetres. Its scale has evenly spaced tick marks and covers all the values. A dot stands for one observation and sits at its value on the axis.

Equal values would fall on the same spot. The chart separates them vertically by stacking or by random jitter. The height carries no scale.

A row carries one group. Several rows share the same axis when the analyst compares groups. The annotation below the chart gives the number of values, the period, the source and the written comment.

English also calls William Cleveland's dot chart a dot plot. That is a different chart: it places one dot per labelled category on a common scale and replaces the bar chart. Some French-language guides call the points of a scatter diagram diagramme par points. That chart crosses two measurements.

Building the dot plot

  1. Define the population. The analyst sets the measurement, the observed units and the period. The analyst requests an extract of the individual values with the identifier of each unit (case, part or call number) and the grouping variables (team, approval route, period). A report that gives only means is not enough. The identifier lets the analyst reopen the case file of an isolated value. The analyst uses the grouping variables to stratify.
  2. Sort the values. Sorting brings equal values together and gives the smallest and the largest value.
  3. Set the axis scale. The axis covers the range with a margin and a readable tick interval: 1 day, CHF 100, 0.1 mm. If a target lead time or specification limits exist, the analyst draws them as vertical lines.
  4. Place one dot per value. The analyst places each dot at its value with the precision of the measurement.
  5. Separate equal values. The analyst stacks the dots or jitters them at random.
  6. Count the dots. Their number equals the number of values. A difference signals overlapping dots or a lost value.
  7. Read and decide. The analyst names the clusters, the gaps and the isolated values. Below the chart, the analyst writes the decision.

Separating equal values

Overplotting (the overplot method) draws equal values at the same spot. The R function stripchart overplots by default. One visible dot then hides several values.

Stacking (the stack method) raises each repeated value one fixed step above the previous one. NIST makes stacking its default method and notes that it gives the chart the look of a histogram. According to the R documentation, stacking makes sense only for values that repeat: whole days, grades, counts.

Random jitter (jitter in NIST Dataplot and in R) adds a small vertical offset to each dot. Jitter also separates close values that would overlap without being equal. A new draw moves the dots. The analyst therefore sets the random seed so that the chart stays the same from one version of the report to the next.

Overplotted 10 dots visible
Stacked 24 dots
Jittered 24 dots
The 24 lead times from the example drawn with the three methods for separating equal values. Overplotting leaves only 10 dots visible. Stacking and jitter show all 24.

Wilkinson starts from hand-drawn dot plots. Their authors placed each symbol as close as possible to its value without the symbols hiding one another. He criticises the software of his day for falling back on the plain binning of the histogram. He proposes an algorithm that follows the hand drawings. The dotdensity method of ggplot2 implements this algorithm. The histodot method places the dots on fixed bins instead. The dot plot then inherits the binning it was meant to avoid.

With whole-number values, the analyst stacks. With finely measured values, the analyst applies random jitter or chooses Wilkinson's method.

Reading the dot plot

  • The centre: the zone where most dots sit. Descriptive statistics compute the median and the mean. The analyst locates where they fall relative to that zone. A mean that falls in a gap describes no unit.
  • The spread: the width of the main cluster and the range from the smallest to the largest value.
  • The clusters: two separate clusters often point to two mixed populations, for example two teams, two approval routes or two types of request.
  • The gaps: an interval without values between two clusters or before an isolated value.
  • The isolated values: for each isolated dot, the analyst finds the unit in the source and checks the data entry before looking for a cause.

With a few dozen values, chance alone can form a cluster of three dots. The analyst therefore treats a cluster as a hypothesis. Stratification by team, approval route or period confirms or rejects it.

Comparing groups

NIST and R place each group on its own row above a common axis. The reader compares the positions at a glance. Has the centre moved? Has the spread narrowed? Does a value of one group fall in the middle of the other?

Before Median 8.5 n = 12
After Median 5 n = 12
Processing time (days)
Processing time of 12 requests before and 12 requests after the switch to a single signature. The two rows share one axis. The median falls from 8.5 to 5 days. One request processed in 13 days after the change sits among the requests from before.

The analyst states the number of values in each row. A row of 30 values carries more dots than a row of 12, even if its lead times are no longer. The reader therefore compares the position of the dots and of the medians, never their number.

The R documentation presents the dot plot as a good alternative to the box plot when samples are small. The box summarises a few points as quartiles. The dot plot shows the points themselves.

What the dot plot does not show

The dot plot sorts the values and loses their order. A drift during data collection looks like a stable spread. The run chart follows the order of the same values.

The height carries no measurement. In a stacked dot plot, the height of a stack counts equal values. In a jittered dot plot, it counts nothing. The ggplot2 function geom_dotplot stacks the dots. Its documentation nevertheless warns that a technical limitation of ggplot2 makes the numbers on its vertical axis meaningless. It suggests hiding that axis.

AI considerations

An assistant writes the code that draws the chart: stripchart in R, geom_dotplot with ggplot2, stripplot or swarmplot with seaborn in Python. The analyst checks the method chosen for equal values. Code that keeps the default method of stripchart overplots the dots and hides some of them. Code that chooses histodot places the dots on fixed bins. The analyst also asks the assistant to hide the vertical scale that geom_dotplot draws.

A language model can drop or duplicate a value pasted into the conversation without saying so. The analyst counts the dots on the chart and compares that number with the number of rows in the extract.

The model sees two clusters and suggests two causes. It does not know that the department applies an amount threshold or that a staff member was absent in March. Its causes remain hypotheses that the analyst checks against the source.

Lead times linked to requesters or staff members are personal data under the Federal Act on Data Protection (FADP). Before passing them to an external AI service, the analyst removes the names: the dot plot needs only the measurement and the group.

Examples

The dot plot shows what a mean hides in a few dozen values. The purchasing department of a municipality records the approval lead time in working days for the 24 purchase requests of one quarter.

Lead time (days)23456910111219
Requests1453223211
Approval lead time of 24 purchase requests in working days: number of requests per lead time.
Median 5 Mean 6.75 n = 24
Approval lead time (working days)
Approval lead time of purchase requests in working days. Dots with equal lead times are stacked. The orange line marks the mean. The blue line marks the median.

Reading: 15 requests between 2 and 6 days, 8 requests between 9 and 12 days and one isolated request at 19 days. The mean of 6.75 days falls in the gap between the two clusters. The median of 5 days sits in the first cluster and says nothing about the second.

Decision: ask the department whether an amount threshold or another criterion separates the two clusters. Open the case file of the request at 19 days.

Visualisations

The example chart, the methods for separating equal values and the before-and-after comparison are drawings: the position of the dots on the axis carries the information. The example data and the cost consist of rows and columns, so they are tables.

Cost

DimensionLevelJustification
PreparationLow to mediumLow when the system exports the individual values. Medium when the extract requires a request to IT. A few dozen values are enough.
ExecutionLowA spreadsheet or one line of code draws the chart in a few minutes. Reading it takes less than an hour.
DocumentationLowThe chart, its source, its period and the decision written below it.

Tooling

On paper or on a whiteboard, the analyst draws the axis and marks one cross per value above its tick mark. Crosses with equal values stack up. A check sheet with one axis value per column produces the stacked dot plot during data collection.

Excel and LibreOffice Calc offer no "dot plot" chart type. The analyst draws a scatter chart that carries the value on the horizontal axis and its rank among equal values on the vertical axis. In the column next to the values, the analyst enters =COUNTIF($A$2:A2,A2) and copies it down. The formula gives this rank. The analyst then hides the vertical axis.

R draws the chart with stripchart, whose method argument chooses between overplot, jitter and stack. With ggplot2, geom_dotplot offers the dotdensity and histodot methods. In Python, seaborn jitters the dots with stripplot and spreads them without overlap with swarmplot. Minitab offers the dot plot in its graph menu. It groups the values into small intervals: in a large data set, one dot can stand for several observations.

Sources

The dot plot belongs to statistical graphics. An article by Leland Wilkinson and the NIST Dataplot manual describe it. The R and ggplot2 documentation describes the methods of the software.

  • Wilkinson, Leland, "Dot Plots", The American Statistician, 1999, 53(3), pp. 276-281, doi:10.1080/00031305.1999.10474474: one symbol per observation, the century-old use of the chart, the critique of binning and the algorithm that follows hand drawings.
  • NIST, Dataplot Reference Manual, "Strip Plot": the definition, the sorting of the values, random jitter and stacking, the preference for small data sets and the grouped version.
  • Cleveland, William S., "Graphical Methods for Data Presentation: Full Scale Breaks, Dot Charts, and Multibased Logging", The American Statistician, 1984, 38(4), pp. 270-280, doi:10.1080/00031305.1984.10483224: the dot chart that replaces the bar chart.
  • R Core Team, documentation of stripchart: the three methods for separating equal values and the advice to prefer the dot plot to the box plot for small samples.
  • ggplot2, documentation of geom_dotplot: the dotdensity and histodot methods and the meaningless vertical axis.