Definition of Ready
The Definition of Ready (DoR) is the list of criteria a Product Backlog item meets before the team accepts it into a sprint. The team agrees on these criteria and displays them. It applies them to the items at the top of the backlog during refinement and at Sprint Planning. The Scrum Guide requires the Definition of Done, which decides whether an item enters the increment.
Goal
The Definition of Ready deals with one problem: the item a team accepts without knowing how to build it. The business rule is missing. Another team has not delivered its service. The item exceeds the capacity of one sprint. The team finds out mid-sprint, when the developers have already committed to the sprint goal.
It supports one decision per item: the team selects it now or sends it back to refinement. The deliverable is the displayed list. The output is the set of items at the top of the backlog that meet it.
According to the ISTQB Certified Tester syllabus, the business analyst takes part in refinement with the testers, the Product Owner and the developers. Together they check that the user stories meet the Definition of Ready. The business analyst proposes the lines that come from the business (documented business rule, test data available, compliance checked) and prepares the items so that they meet them.
Rubin holds that a strong Definition of Ready improves the Scrum team's chances of reaching its sprint goal. According to the Agile Alliance, it keeps the team from starting a feature without clear completion criteria. It gives the team an explicit basis for refusing a poorly defined item.
Usage
When to use it
- A Scrum team that is starting out: spell out what "ready" means before the first Sprint Planning.
- Items blocked mid-sprint by missing information: add to the list the criterion that would have stopped them.
- A dependency on another team or a supplier: require that it is cleared before selection.
- A long backlog whose state of readiness is unclear: see which items at the top are ready without rereading them all.
- Developers who hesitate to send an item back to the Product Owner: give them a written basis for doing so.
- Testers embedded in the team: set the entry criteria for testing a user story.
- A team spread over several sites: the written list replaces the spoken agreement on what "ready" means.
- A project task that waits on deliverables from other teams: check before the start that each expected deliverable is available (the PMBOK's "full kit").
When not to use it
- Items that already arrive understood and feasible: keep to backlog refinement and the Scrum Guide's test.
- A condition that belongs to one item only: write it as an acceptance criterion of that item.
- An unknown that only an experiment resolves: plan a spike instead of demanding a ready item.
Description
What the Scrum Guide says about "ready"
In its "Product Backlog" section the 2020 Scrum Guide defines "ready" in one sentence. Items that the Scrum team can bring to Done within one sprint are deemed ready for selection at Sprint Planning. They usually reach this degree of transparency after refinement.
So the Guide sets a single test: the item can meet the Definition of Done within one sprint. It also allows the Scrum team to refine items during Sprint Planning. A team that forbids all refinement at Sprint Planning goes further than the Guide.
The Definition of Ready expands this test into a list of the team's own. The Guide presents Scrum as a framework that accommodates other techniques and practices.
The Guide requires a Definition of Done and binds the developers to it. Work that does not meet it does not enter the increment. The organisation or the Scrum team sets the content of the Definition of Done. The team chooses whether to keep a Definition of Ready and sets its content.
- Value stated
- Details understood
- External dependencies cleared
- Estimated and feasible within one sprint
- Testable acceptance criteria
- Demonstration planned
- Quality measures required for the product
The Agile Extension to the BABOK Guide names the technique and makes it part of backlog refinement. Its glossary defines it as a list of criteria that the team agrees on and displays prominently. The ISTQB syllabus counts it among the entry criteria for testing. The PMBOK Guide mentions it once as another name for the checklist that verifies a project or a task is ready to start.
According to the Agile Alliance, the first allusions date from early 2008. The first formal description seems to date from October of that year, when Richard Kronfält published a list of six criteria under the name "ready-ready". The Agile Alliance links the idea to the entry criteria of older models such as the ETVX model (1985).
Acceptance criterion, Definition of Ready, Definition of Done
All three carry criteria but differ in scope and timing. An acceptance criterion belongs to one item and says when it is acceptable. According to the Agile Extension to the BABOK Guide, acceptance criteria set the boundaries of a user story. The Definition of Ready applies to every item and says when it can enter a sprint. The Definition of Done applies to every item and says when it can enter the increment. The Scrum Alliance distinguishes the Definition of Ready from the Definition of Done and from acceptance criteria.
| Acceptance criterion | Definition of Ready | Definition of Done | |
|---|---|---|---|
| Applies to | One item | Each item | Each item |
| Question | Does this item do what is expected? | Can the team take this item into the sprint? | Can this item enter the increment? |
| When it is checked | Written before selection. Verified at the end of the work on the item. | Before selection at Sprint Planning | At the end of the work on the item, before it enters the increment |
| Example | The form rejects a three-digit postcode. | No external dependency blocks the item. | The interface text is reviewed in French and German. |
Rubin presents the Definition of Ready and the Definition of Done as two states of an item over the course of the sprint. His example list contains the line "Acceptance criteria are clear and testable". So acceptance criteria are one of the lines of the Definition of Ready. An item can meet the Definition of Ready and then fail the Definition of Done. The first judges the preparation. The second judges the result.
To write the conditions that belong to one item, see acceptance and evaluation criteria.
The criteria
Each team writes its own list. Rubin gives an example. Most criteria check the output of another technique.
| Criterion in Rubin's list | Technique that prepares it |
|---|---|
| The business value of the item is articulated. | User stories |
| The team understands the details well enough to judge whether it can complete the item. | Backlog refinement |
| Dependencies are identified. No external dependency prevents the item from being completed. | Agile release planning |
| The team has the people it needs to complete the item. | Staffing decision without a dedicated technique |
| The item is estimated and small enough to fit in one sprint. | Relative estimation and story decomposition |
| Acceptance criteria are clear and testable. | Acceptance and evaluation criteria |
| Performance criteria, if any, are defined and testable. | Non-functional requirements analysis |
| The team knows how to demonstrate the item at the sprint review. | Story elaboration |
Kronfält's list adds a unique priority in the backlog and the user story format of role, feature and benefit. According to the Agile Alliance, the criteria most often follow Bill Wake's INVEST mnemonic: independent, negotiable, valuable, estimable, small, testable.
Writing the list
The list stays short. Rubin's and Kronfält's lists fit in six to eight lines. The Scrum Alliance points to the risk of a list that puts process before people. Each extra line replaces a little conversation with a checkbox.
Guidelines rather than rules. Mountain Goat Software advises against requiring that preparatory work be finished before the item enters the sprint. Its example: the rough mock-ups are started and far enough along for the open questions to be settled during the sprint. The same source allows one exception. A dependency on a team or a supplier that has already missed deliveries can justify a strict rule.
A criterion is answered yes or no. "Item clear" cannot be checked. "Acceptance criteria written and reviewed by a tester" can.
The list marks the blocking lines. A blocking line rules out any item that does not meet it. An item can enter the sprint without meeting a non-blocking line if the team can close the gap during the sprint and reports it at Sprint Planning.
Setting up and applying the list
- Begin with an informal shared judgement. At the start, the Agile Extension accepts that an item is ready when a critical mass of the team judges it ready. The written list comes later.
- Start from a known list. The team takes Rubin's list or Kronfält's. It keeps the lines that address the blockers it has met.
- Display the list. The team puts it on the wall or at the top of its online workspace.
- Apply it at the refinement meeting. According to the Agile Extension, the team confirms that the items at the top are ready for the next iteration. It checks each one against the list. Each unmet criterion becomes a question for the Product Owner or for the team concerned.
- Apply it at Sprint Planning. The developers select the items with the Product Owner. They can still refine them at that point.
- Revise the list. The team adds criteria as it learns from its work. At the retrospective the team reviews the sprint's blockers. It removes a line that has neither ruled out an item nor raised a question for several sprints.
According to the Agile Extension, the Product Owner or a customer representative most often facilitates the refinement meeting. Kronfält also wants a tester there so that the demonstration line is testable.
The item that does not meet the list
Most often the item goes back to refinement. The Product Owner answers the open questions.
An external dependency that is still open blocks selection. The team does not control the date on which the third party delivers. The item stays in the Product Backlog until the other team or the supplier delivers.
When the unknown is technical and only an experiment resolves it, the team plans a spike that makes the item estimable.
The team splits an item too big for one sprint and estimates it again.
When the item fails a non-blocking criterion and the gap closes during the sprint, the team can select it. It reports this gap at Sprint Planning. The Scrum Alliance accepts this: unlike the Definition of Done, the Definition of Ready does not need to be 100% fulfilled.
What makes a Definition of Ready fail
The return to waterfall. The team refuses every item that does not meet every line. The Scrum Alliance and Mountain Goat Software read this as a return to a phased sequence in which analysis finishes before development starts. Mountain Goat Software concludes that most teams do not need a Definition of Ready.
The sprint goal lost from sight. The Scrum Alliance notes that attention can shift from the sprint goal to the list. The team debates an empty box instead of asking whether the item serves the goal.
Preparation left to the Product Owner. According to the Scrum Alliance, the developers may come to expect items to arrive ready. Yet the criterion "the team understands the details well enough" requires the developers to take part in refinement.
The list that keeps growing. Each incident adds a line. In the end the list rules out items that the team could have delivered.
The list imposed by management. A manager who dictates the list strips it of what it rests on: the team's agreement.
The Definition of Ready presented as a Scrum rule. Whoever presents it as one takes away the team's right to adapt it or drop it.
AI considerations
A language model checks the items at the top of the backlog against the written Definition of Ready. For each item it flags the lines that the item's description gives no grounds to tick: no acceptance criteria, a dependency mentioned without a delivery date, a missing estimate. It proposes acceptance criteria. It suggests splits for an item that is too big. In the descriptions it spots mentions of other teams or suppliers that point to an external dependency.
The model cannot tell whether the team has understood the item. The team checks that criterion in the session, when the developers explain what they will build. An acceptance criterion drafted by the model stays a proposal until the Product Owner adopts it. A dependency that nobody has written down escapes the model. The backlog of a health insurer or a bank holds internal rules and data on policyholders or customers. That content stays out of the prompts sent to a public AI service.
Examples
A Scrum team at a health insurer in French-speaking Switzerland builds the insurer's app for policyholders. Its Definition of Ready has six lines. Two of them block: "External dependencies cleared" and "Estimated and feasible within one sprint". At the refinement meeting the team checks the three items at the top of the backlog against the list.
| Criterion | Type | A. Send a physiotherapist's invoice as a photo | B. View the deductible statement | C. Change the postal address |
|---|---|---|---|---|
| Value to the policyholder stated | Non-blocking | Yes | Yes | Yes |
| Acceptance criteria written and testable | Non-blocking | Yes | Yes | Yes |
| External dependencies cleared | Blocking | No: contract with the document-recognition supplier not yet signed | Yes | Yes |
| Details understood by the developers | Non-blocking | Yes | No: co-payment calculation still to be clarified | Yes |
| Estimated and feasible within one sprint | Blocking | Yes | No: too big for one sprint | Yes |
| Demonstration at the sprint review planned | Non-blocking | Yes | Yes | No: test data set still to be prepared |
| Decision | Stays in the Product Backlog. The Product Owner chases the supplier. | Goes back to refinement to be split. | Ready. The gap is reported at Sprint Planning. |
Item A meets five lines out of six and stays out of the sprint. No work by the team can clear the dependency on the supplier.
Visualisations
The usual form is a one-page list displayed on the team's wall or in its document space. A table with the criteria on one axis and the top backlog items on the other shows their readiness before the refinement meeting. On a Kanban board a "Ready" column separates the items that meet the list from the rest of the backlog.
Cost
| Phase | Level | Justification |
|---|---|---|
| Preparation | Low | One team session to agree on six to eight lines. |
| Execution | Low | A few minutes per item within the refinement meeting the team already holds. |
| Documentation | Low | One page that the retrospective revises. |
Tooling
A poster or a whiteboard is enough for a team on one site. A team wiki (Confluence or equivalent) holds the reference version for a distributed team.
Tracking tools (Jira, Azure DevOps, GitLab) add the list to the item template as checkboxes or a field. A workflow transition condition that stops an item from moving into the sprint while a box is empty makes every line blocking. It suits only the lines that the team has marked as blocking.
Sources
- Kenneth S. Rubin, Essential Scrum: A Practical Guide to the Most Popular Agile Process (Addison-Wesley, 2012), chapter 6 "Product Backlog". Excerpt published by the author: "Definition of Ready (DoR)" (Innolution, 2012). The example list of eight criteria. The Definition of Ready and the Definition of Done as two states of an item.
- Ken Schwaber and Jeff Sutherland, The Scrum Guide (November 2020), sections "Product Backlog", "Sprint Planning", "Commitment: Definition of Done" and "End Note". When the Guide deems an item ready for selection. Refinement during Sprint Planning. The Definition of Done binding on the developers. Scrum as a framework that accommodates other practices.
- IIBA, Agile Extension to the BABOK Guide v2, §7.1.3.3 Refinement Meeting, §7.1.3.4 Definition of Ready, §7.21 User Stories (.4 Confirmation) and glossary. The list that the team agrees on and displays. Readiness judged at first by a critical mass of the team. Criteria added as the work goes on. The refinement meeting that the Product Owner most often facilitates. Acceptance criteria that set the boundaries of a user story.
- Scrum Alliance, "Pros and cons of a definition of ready". The claimed benefits and the risks. The distinction from the Definition of Done and from acceptance criteria.
- Agile Alliance, glossary, "Definition of Ready". The link with INVEST. The claimed benefits. The origins in 2008 and the link to earlier entry criteria.
- ISTQB, Certified Tester Foundation Level (CTFL) Syllabus v4.0.1 (2024), §3.1 and §5.1.3. The Definition of Ready as an entry criterion for a user story. The business analyst's part in checking items at refinement.
- Richard Kronfält, "Ready-ready: the Definition of Ready for User Stories going into sprint planning" (October 2008). A list of six criteria among the first published.
- Mountain Goat Software, "Definition of Ready: What It Is and Why It's Dangerous" (updated 2023). A practitioner's critique: the risk of a return to waterfall, guidelines rather than rules, the exception for external dependencies.
- Bill Wake, "INVEST in Good Stories, and SMART Tasks" (2003). The INVEST mnemonic.
- PMI, PMBOK Guide, 8th edition, Tools and Techniques, "Checklists". The Definition of Ready as another name for a start-up checklist.