Darnall-Preston Complexity Index
The Darnall-Preston Complexity Index (DPCI) is a grid that rates a project's complexity on thirteen attributes. The attributes fall into four categories: external, internal, technological and environmental. Each attribute receives a rating from 1 (least complex) to 5 (most complex). The assessor rounds the average of each category to a whole number. The rounded average is the category rating. The four ratings form the project code, for example 3.3.4.2. The profile informs the choice of project manager, the make-up of the project leadership team and the project setup. Russell Darnall and John Preston describe the index in their textbook Project Management from Simple to Complex (2010).
Goal
The DPCI rates a project's complexity attribute by attribute before the team writes the execution plan. From the ratings it draws a profile: four category ratings that show where the project will be hard. Management uses the profile to choose the project manager, form the project leadership team and size the start-up. The authors also use it to compare a project with past projects and judge its chances of success.
The textbook observes that a project manager who has succeeded on several projects can fail on the next one. The authors cite a Construction Industry Institute study in which availability was the first criterion for assigning a project manager. The DPCI bases the assignment on the skills that the project profile demands.
Darnall and Preston assume that every project is unique, that projects still share characteristics and that these characteristics form a profile. In their view, each profile has an optimal way to run the project. That way demands specific skills from the project manager and the team.
The technique produces a rating sheet. It holds thirteen ratings with the facts behind them, the 1 and 5 scenarios for the attributes without anchors, four category ratings and the project code.
Usage
When to use it
- Appointing the project manager: compare the skills that the profile demands with those of the candidates.
- A project of unusual size: measure how much larger or smaller it is than the projects the organisation knows how to run.
- Preparing the start-up: size the project office, the tools and the kick-off meetings to the profile.
- Analogous estimating: find past projects with the same code and compare their estimates with their final costs.
- Project portfolio: compare the profiles to allocate the experienced project managers.
When not to use it
- Choosing how to act in a situation: the DPCI rates a project and does not classify a situation; use Cynefin.
- Choosing between projects or options: the code does not say which project to launch; use multi-criteria decision analysis or a business case.
- Risk inventory: the profile does not replace risk analysis; use risk analysis and management.
Description
Categories and attributes
The parent organisation sets the external attributes when it authorises the project: size, schedule and resources. The project team usually has little control over them. The project manager controls or influences the internal attributes. The technological attributes concern the technology of the product. The environmental attributes cover what surrounds the project and bears on its plan.
| Category | Attribute | What the rating measures |
|---|---|---|
| External | Size | How much larger or smaller the project is than the usual projects of the organisation and the team |
| Duration | The gap between the imposed deadline and the duration of the work at a normal pace | |
| Resource availability | The scarcity of people, skills and equipment at the moment the project needs them | |
| Internal | Clarity of objectives | How far the team knows the objectives and uses them to make decisions |
| Clarity of scope | How sharp the boundary is between what the project delivers and what it leaves to others | |
| Organisational complexity | The number of people and levels, their links and the client's decision structure | |
| Stakeholder agreement | The number of stakeholders, their stake in the project, their influence and their disagreement | |
| Technological | Newness of the technology | The maturity of the product's technology or a combination of technologies never brought together before |
| Team familiarity | The team's experience with this technology | |
| Environmental | Legal | The permits, labour law, taxes and customs that the project must handle |
| Cultural | The cultural gaps between the team, the parent organisation and the communities where the project takes place | |
| Political | The number of leaders with a stake in the project and their influence on its resources | |
| Ecological | The project's effect on its surroundings (soil, water, air, noise, odours) and the effect of the surroundings on the project (weather) |
Rating an attribute
Each attribute receives a whole-number rating from 1 to 5. The textbook's method holds for every attribute. For each one, the assessor first describes the simplest scenario for this organisation and rates it 1. The assessor then describes the most complex scenario and rates it 5. Finally the assessor places the project between the two. A project close to the simplest without reaching it receives 2. A project halfway receives 3. A project close to the most complex without reaching it receives 4.
The textbook provides anchors for only four attributes. They describe what ratings 1 and 5 mean and the steps between them.
| Attribute | Rating 1 | Rating 5 |
|---|---|---|
| Size | The size that the organisation runs most often; proven tools | Several times larger or smaller than any earlier project; the team's tools no longer fit |
| Organisational complexity | A small group that has already worked together in these roles | A very large number of people who do not know each other; one full-time person per function and frequent coordination meetings between managers |
| Newness of the technology | A technology established for years | A technology still in testing; the organisation is a pilot site |
| Team familiarity | The whole team has worked with this technology before | Nobody knows it; a specialist may be needed |
For size, the anchors put a number on the gap. A project about 20% larger or smaller than the usual projects receives 3. A gap of about 50% gives 4. For the nine attributes without anchors, the assessor writes their own 1 and 5 scenarios on the rating sheet: a reader who picks it up a year later understands each rating.
From ratings to code
The textbook sets the calculation rule:
- The assessor averages the ratings in each category. All attributes carry the same weight.
- The assessor rounds each average to a whole number. An average halfway between two whole numbers rounds up: 2.5 gives 3.
- The assessor writes the four category ratings in the order external, internal, technological, environmental: 3.3.4.2.
- The assessor sets in bold any category rating that an attribute exceeds by two points or more (as the textbook's exercise applies the rule).
Only an upward gap triggers the bold. In the textbook's example, the internal category is rated 3 and clarity of objectives 1. The two-point gap downwards triggers nothing. The bold signals that a category rating hides a harder attribute. The textbook then asks the assessor to examine the category in detail.
The wording of the rule compares the attribute with the average. The exercise compares it with the rounded average. The two readings diverge when rounding goes down: a category at 4, 2, 2 and 1 has an average of 2.25 and a rating of 2. The attribute rated 4 exceeds the rating by two points and the average by 1.75. An organisation that adopts the wording writes it into its rule and applies it to all its projects.
Reading the profile
The code is read category by category. Its digits are not added together: 3.3.4.2 and 4.2.2.4 both total 12. In the textbook's examples, the first points to a project manager at ease with technical staff. The second points to an outward-facing negotiator.
According to the textbook, a profile high on external factors and medium on technology calls for a project manager who negotiates well, understands those factors and works easily with technical staff. The project manager who assessed the project is not necessarily the best one to run it. A simple project relies on the organisation's accounting, purchasing and IT. A complex project may need its own project office, IT system and support staff. A project that rates high needs more skills and resources during initiation. A project that rates low invests more in execution.
| Category rated high | Risks that the textbook associates | Consequence for the setup |
|---|---|---|
| External | Unknown risks from a lack of experience at this size; foreseeable risks from missing resources | A project manager who negotiates and understands the external factors |
| Internal | Budget, schedule and quality threatened by the organisation; scope changes caused by vague objectives | Specialised resources from initiation onwards to align the stakeholders |
| Technological | Unknown defects in the technology and the team's lack of familiarity | Technical expertise in the team; a project manager at ease with technical staff |
| Environmental | Delays, costly litigation, public opposition, political change, unforeseen ecological effects | Specialised resources from initiation onwards for political and legal issues |
The textbook gives these consequences as examples. Its chapter on profiles shows an organisation that writes its own rule on a single attribute: above one million dollars, the project gets a project manager with at least five years' experience, a vice-president as sponsor and a quarterly report. An organisation that adopts the DPCI writes its rules on the category ratings in the same way.
For an analogous estimate, a less experienced project manager searches the archives for past projects with the same code. The project manager compares their initial estimates with their final costs. The archive gives a basis for comparison even when other people ran those projects.
Complexity and risk
According to the textbook, risk and complexity go together. Risk analysis looks for what can go wrong and how likely it is. The profile looks for what makes the project complex. An execution plan can reduce a risk without changing the rating. The textbook takes the case of a project in which several independent clients share the decisions. The execution plan provides for keeping them aligned. The organisational risk falls. The organisational complexity stays the same because the clients still decide together.
The DPCI and Cynefin
The two tools use the word "complex" in two senses. In the DPCI, complexity is a degree that the assessor rates from 1 to 5 for each attribute. In Cynefin, the complex domain is one where the relationship between cause and effect becomes clear only in hindsight. Cynefin places a situation in a domain to choose a way to act. The DPCI rates a project to prepare how it will be run. A project rated 2 throughout can contain an element that Cynefin places in the complex domain. To classify a situation rather than rate a project, see Cynefin.
Mistakes that distort the profile
Rating the project as it will be. The assessor rates the present state. A scope that the team plans to clarify is still vague on the day of the rating.
Rating the management technology. The technological attribute concerns the product. If the team changes its scheduling software, the newness rating stays the same.
Rating without writing the 1 and 5 scenarios. Without them, each assessor rates an unanchored attribute on a private scale.
Leaving the rating to the prospective project manager alone. The candidate has an interest in a profile that matches their skills. The sponsor, an analyst and someone who knows the organisation's past projects rate separately. They then discuss every gap of two points or more.
Origin and limits
According to the textbook, Russell Darnall presented the rating in 1996. The four-digit code and its calculation rule appear with the 2010 textbook. The profile holds for one date. When the organisation changes its execution approach, the assessor rates the project again: the textbook cites a chemical plant whose profile drops when design moves from an international partnership to a domestic partner.
AI considerations
From the closure reports of past projects, a language model drafts the 1 and 5 scenarios for the nine attributes without anchors. It extracts from the charter, the contract and the organisation chart the facts that support each rating and fills in the justifications. Among past projects with the same code, it compares their thirteen ratings and justifications with those of the project and suggests the ones closest to it.
It does not assign the ratings. Size and familiarity are measured against the experience of the organisation and the team, which the model does not know. Political and cultural ratings often rest on what people say off the record. A rating from the model suggests a precision that no data supports. Tensions between stakeholders and the names of leaders are personal data under the Federal Act on Data Protection (FADP). They stay in the tools that the organisation authorises.
Examples
The concept: how the thirteen ratings yield the code and its bold digit. A regional hospital replaces its billing software. The rating sheet gives each rating and the fact behind it.
| Category | Attribute | Scale (1 / 5) | Rating | What the rating rests on | Average | Category rating |
|---|---|---|---|---|---|---|
| External | Size | Textbook anchor | 2 | Budget of CHF 2.4 million; top of the range of the hospital's IT projects | 3.00 | 3 |
| Duration | 1: no imposed date; 5: imposed deadline a quarter shorter than the normal schedule | 4 | Go-live imposed for 1 January; the normal 10-month schedule ends in late February | |||
| Resource availability | 1: all specialists available full time; 5: no specialist available | 3 | Two of the three billing specialists shared with operations | |||
| Internal | Clarity of objectives | 1: written objectives that guide every decision; 5: no written objective | 2 | Written objective that everyone knows: bill under the new tariff without payment delays | 3.25 | 3 |
| Clarity of scope | 1: deliverables and boundaries written and accepted; 5: boundaries still to be defined | 3 | Migration of open invoices still under discussion | |||
| Organisational complexity | Textbook anchor | 4 | Finance, IT, twelve medical departments and the vendor; two levels of committee | |||
| Stakeholder agreement | 1: support from all stakeholders; 5: influential stakeholders opposed to the project | 4 | The medical departments dispute recording services at the patient's bedside | |||
| Technological | Newness of the technology | Textbook anchor | 3 | Version released last year; three Swiss hospitals use it | 3.50 | 4 |
| Team familiarity | Textbook anchor | 4 | Software new to the team but close to the vendor's previous product; a vendor consultant supports the project | |||
| Environmental | Legal | 1: no authorisation and no sensitive data; 5: uncertain authorisation that can stop the project | 4 | Health data (sensitive data) and medical confidentiality; the legal department must approve external hosting | 2.00 | 2 |
| Cultural | 1: one region and one language; 5: several countries, languages and working cultures | 1 | Team and departments in one region; a single working language | |||
| Political | 1: no leader with a stake in the project; 5: several leaders competing for its resources | 2 | The board of directors reviews the project every quarter | |||
| Ecological | 1: no effect on the surroundings; 5: works that affect soil or water | 1 | No effect on the site; no dependence on the weather | |||
| Project code | 3.3.4.2 | |||||
Rounding up takes the technological category from 3.5 to 4. The environmental category is rated 2, but the legal attribute rated 4 exceeds it by two points: the 2 appears in bold. Without the bold, the code would present the environment as the simplest part of the project.
Visualisations
The rating sheet is the basic form. It carries one row per attribute: the scale (1 and 5 scenarios or textbook anchor), the rating, the fact behind it, the average and the category rating. The textbook builds it in a spreadsheet.
A bar chart shows the profile at a glance. Each category forms a band. A line in the band marks the category rating. The bar of an attribute that triggers the bold extends two points or more past that line.
For a portfolio, a register gives one row per project with its code. The reader finds the projects with the same profile there for an analogous estimate.
Cost
| Dimension | Level | Justification |
|---|---|---|
| Preparation | Medium | Gather the charter, the budget, the organisation chart and the project history; write the 1 and 5 scenarios for the nine attributes without anchors. |
| Execution | Low | One session of one to two hours is enough to rate thirteen attributes, discuss the gaps and calculate the code. |
| Documentation | Low | One sheet: thirteen justified ratings, the 1 and 5 scenarios for the unanchored attributes, four averages, the code. |
Tooling
A spreadsheet is enough. AVERAGE calculates each average. ROUND(…,0) rounds it to a whole number and gives 3 for 2.5. Conditional formatting sets the category rating in bold when the category's maximum exceeds it by two points or more. Each assessor rates alone in a shared spreadsheet before the session. The session takes place on site or by video call and deals only with the gaps.
A script must reproduce the round-half-up rule. In Python, round(2.5) gives 2 because the function rounds half to even. The script uses math.floor(average + 0.5).
Portfolio management software stores the code in a project field. A project manager who estimates a new project finds the profiles of past projects there. A shared whiteboard is enough for the session where the assessors compare their ratings.
Sources
- Russell Darnall and John Preston, Project Management from Simple to Complex, v1.0, Flat World Knowledge, 2010: the original edition of the textbook.
- Project Management from Simple to Complex, v1.1, open edition from Saylor Academy: section 2.1 for profiling and the Construction Industry Institute study; 2.3 for the uses of the profile; 2.4 for the categories, the attributes and the authors' assumptions; 2.6 for the calculation rule of the code; 3.1 for allocating resources by profile; 3.3 for the scale, the anchors and the two-extremes method; 7.3 for choosing the project manager and the start-up; 9.1 for analogous estimating; 11.4 for the link between profile and risks.