Critical Path Drag and Drag Cost
Critical path drag is the time a critical activity adds to the project's duration. Drag cost turns that time into money: the value the project loses because this activity delays its finish. Total float is the same for every critical activity and does not rank them. Drag ranks them by the time each one costs the project. Stephen Devaux introduced both measures in 1999 in Total Project Control. The PMBOK Guide defines them in its eighth edition. With these measures the project manager prices a schedule compression before paying for it.
Goal
The drag of a critical activity is the time the project would gain if that activity's duration fell to zero. The PMBOK Guide gives a second formulation: the most the activity can be shortened before it leaves the critical path or its duration reaches zero.
The critical path method calculates the float of each activity. Devaux observes that the usual measure draws attention to the work that does not delay the project. Drag quantifies the work that does.
Drag cost is drag multiplied by the cost of delay. The deliverable is an activity table that lists each activity's duration, drag, resource budget, drag cost and true cost. The project manager uses it to rank the candidates for compression and to price each option.
Usage
When to use it
- Calculated finish after the target date: identify the critical activities to shorten first.
- Delay observed during execution: target the activities whose shortening gains the most time.
- Project value sensitive to its date: put a figure in francs on the delay each critical activity causes.
- Compression awaiting approval: compare the extra cost of each option with the drag cost it removes.
- Optional element now on the critical path: compare its value with the cost of the delay it causes.
- Interim deliverable to bring forward: calculate drag on the part of the network that leads to that deliverable.
- Network of several hundred activities: limit the review to the activities with the highest drag.
- Multi-project organisation: rank resource types by true cost to decide on hiring.
When not to use it
- No up-to-date logic network: wrong links or missing progress data give wrong drags; first bring the network back into shape with the critical path method.
Description
Float and drag
An activity's total float is the delay it can take without pushing back the project finish. Without a date constraint every critical activity shows zero float, whether it lasts two days or two months. Devaux sets the two measures against each other. Float always sits off the critical path; drag always sits on it. Float usually costs the project neither time nor money; drag nearly always does.
A long critical activity may add only a few days to the project when a parallel activity has little float. A short activity with no parallel activity adds its whole duration. In Devaux's network a 20-day activity adds three days to the project; a five-day activity adds five. Ranking the critical activities by duration can therefore point at the wrong one.
Calculating drag
The calculation starts from a network processed by the critical path method: forward and backward passes, total float for each activity, critical path. An activity is parallel to a critical activity when it sits on a branch that leaves the critical path before that activity and rejoins it after. For a network whose links are all finish-to-start, Devaux calculates drag as follows:
- Only critical activities have drag. The others have float.
- The drag of a critical activity with no parallel activity equals its duration.
- The drag of a critical activity with parallel activities is the smaller of two values: its duration or the lowest total float of its parallel activities.
Rule 3 comes from a limit. Shortening the critical activity shortens the project week for week until the parallel branch with the least float becomes as long as the critical path. That branch then sets the finish. Each further week removed gains nothing. When the activity lasts less than that float, its duration reaches zero before the limit: its drag equals its duration.
An imposed finish date earlier than the calculated finish makes the total float of the critical path negative. The float of the parallel branches drops by the same amount. Rule 3 then takes the float of the parallel branch minus that of the critical path.
On a network that carries start-to-start links, finish-to-finish links or lags, the three rules no longer apply as they stand. Devaux finds the manual calculation long and arduous on a large network with complex dependencies. The planner then falls back on the definition of drag. In a copy of the schedule the planner sets the critical activity's duration to zero, recalculates the network and reads how far the project finish moves forward. The planner repeats this calculation for each critical activity.
The cost of delay
Drag cost needs the cost of delay: what a finish one day or one week later costs the project. For Devaux this cost comes first from the value the project loses when its delivery slips: missed sales, savings that start later, a falling expected monetary value. It comes next from higher overheads and opportunity costs. The PMBOK Guide also counts the bonus the project forgoes when a contract rewards early delivery.
The PMBOK Guide states that the value estimates of the value breakdown structure also serve to estimate the drag cost of each element on the critical path (§2.2.1). The project manager sets the cost of delay with the sponsor and records the assumption behind it. A constant cost per week assumes that each week of delay removes the same value.
When delay costs money only after a date S, an activity's drag cost is min(drag; calculated finish − S) × cost of delay per week. It is zero when the calculated finish falls before S. A compression therefore pays only up to date S. A project calculated at 18 weeks loses CHF 20'000 per week beyond week 16. In this project an activity with 3 weeks of drag costs min(3; 2) × 20'000, that is CHF 40'000. Shortening this project by more than 2 weeks earns nothing.
Drag cost and true cost
In Devaux's definition, the delay that an activity adds causes a drop in the project's net value. Drag cost is that drop:
drag cost = drag × cost of delay per week
He distinguishes it from the activity's true cost, which adds the cost of its resources to its drag cost. Off the critical path drag cost is zero: true cost comes down to the budget.
The PMBOK Guide merges the two concepts in one entry. Its first sentence defines drag cost as the reduction in the project's expected return due to the drag of a critical activity. Its second sentence makes it the activity's true cost: resource cost plus cost of delay. Adding the budget to drag cost as the second sentence defines it counts the budget twice.
True cost can reverse the order of the budgets. In Devaux's network an activity off the critical path budgeted at 30'000 dollars costs 30'000 dollars. A critical activity budgeted at 20'000 dollars, whose drag is 15 days at 10'000 dollars a day, costs 170'000 dollars. Devaux concludes that a week of low-skilled work on the critical path can cost the project more than a week of expert work on an activity with float.
Ranking and deciding
Crashing and fast tracking shorten the critical path, one through added resources, the other by overlapping activities planned in sequence. Drag caps their gain. Drag cost prices that gain: each week of drag removed returns the cost of one week of delay.
- Calculate the drag of each critical activity.
- Calculate the drag cost and true cost of each.
- Rank the critical activities by decreasing drag and keep the top ones.
- For each one, price an option: weeks removed, extra resource cost, added risk.
- Cap the weeks removed at the drag. A week beyond it costs money and gains nothing.
- Keep the option if the drag cost removed exceeds its extra cost. Between two profitable options, start with the one with the lower cost per week gained.
- Apply the chosen option, recalculate the network and the drags, then go back to step 3.
In Devaux's case, doubling the resources of the activity with a true cost of 170'000 dollars brings its drag down from 15 to 10 days. Its budget rises from 20'000 to 26'700 dollars. Its drag cost falls by 50'000 dollars. Its true cost drops to 126'700 dollars, that is 43'300 dollars less.
Drag identifies the candidates without measuring how they respond to compression. Devaux notes that added resources shorten some activities only slightly. Shortening an activity can raise risk beyond what is acceptable, degrade quality or reduce the project's value.
Recalculating after each change
An activity's drag depends on the float of its parallel activities. Each shortening changes those floats. Devaux therefore recalculates the drags at every change in the critical path. When an activity's drag comes from the float of a parallel branch, shortening it by its full drag makes that branch critical. Over the stretch where the two branches run in parallel, their activities then have zero drag. None of them shortens the project on its own any more.
Drags do not add up. Two critical activities in series with the same parallel branch each have a drag bounded by that branch's float. Shortening both gains that float only once. A table of options priced on the initial network therefore overstates the gain of any combination that touches two activities in the same stretch of the critical path.
During execution the critical path also changes without compression. An activity that finishes late or early shifts the floats. The project manager recalculates the drags at each progress update.
Optional elements
Devaux observes that optional elements often delay a project by more than they are worth. An optional element that moves onto the critical path takes on a drag cost. The sponsor and the project manager then compare that cost with the element's value. The PMBOK Guide proposes the same check for an element of the value breakdown structure: accelerating or removing an element on the critical path can return more than the operation costs. The sponsor can remove an optional element. The project then loses only that element's value. In the value breakdown structure a mandatory element carries 100% of the project's value: removing it is never an option. Devaux calls for repeating this analysis whenever the critical path changes, since new activities then take on a drag cost.
Bringing forward a deliverable off the critical path
A client may ask for an interim deliverable to arrive earlier. Its early finish date falls after the requested date even though the deliverable still has float against the project finish. Devaux describes a component to be delivered five weeks early on a three-year project. The component had more than 200 days of float. Drag applies to the network that leads to that deliverable:
- Bring the schedule back into shape: progress up to date, correct links, no activity performed out of sequence.
- Make the deliverable the last activity of the network.
- Keep its direct and indirect predecessors.
- Calculate the critical path up to the deliverable and the drags of its activities.
- Shorten the activities with the highest drag by crashing or fast tracking.
- Recalculate the drags after each change.
AI considerations
A language model writes the spreadsheet formulas that apply the three rules and calculate drag cost and true cost. It writes the script that sets each critical activity to zero duration in a copy of the schedule and records how far the finish moves forward. In a schedule export it spots activities without links, lags and start-to-start or finish-to-finish links, which call for this calculation instead of the rules. It formats the options table and the decision note for the sponsor. It prepares the questions that the project manager asks the sponsor about the cost of delay.
The calculation belongs to the spreadsheet, the script or the scheduling tool. A misread float on a parallel branch distorts a drag without the table showing it. The sponsor sets the cost of delay. Only the team knows whether added resources shorten an activity. A prompt sent to a hosted service takes the budgets, the rates and the penalty clauses outside the organisation.
Examples
A regional public transport company replaces its ticketing app. The project manager draws up the activity network. The critical path takes 18 weeks. Each week of delay costs CHF 20'000: the old system's licence runs longer and both systems run in parallel.
The drag table applies the three rules and adds each activity's budget.
| Activity | Duration (weeks) | Total float (weeks) | Drag (weeks) | Rule applied | Budget | Drag cost | True cost |
|---|---|---|---|---|---|---|---|
| A Requirements | 3 | 0 | 3 | No parallel activity: the duration | 45'000 | 60'000 | 105'000 |
| B App development | 9 | 0 | 3 | Float of the D-E branch (3) below the duration (9) | 180'000 | 60'000 | 240'000 |
| C App testing | 2 | 0 | 2 | Duration (2) below the float of the D-E branch (3) | 30'000 | 40'000 | 70'000 |
| D Interface with the fare system | 5 | 3 | – | Off the critical path | 75'000 | 0 | 75'000 |
| E Interface testing | 3 | 3 | – | Off the critical path | 30'000 | 0 | 30'000 |
| F Season-ticket migration | 2 | 9 | – | Off the critical path | 15'000 | 0 | 15'000 |
| G User acceptance testing (UAT) | 3 | 0 | 3 | No parallel activity: the duration | 36'000 | 60'000 | 96'000 |
| H Go-live | 1 | 0 | 1 | No parallel activity: the duration | 12'000 | 20'000 | 32'000 |
Acceptance testing has less than half the budget of the interface with the fare system (D) and costs the project more. The options table prices each compression in order of cost per week gained.
| Activity | Drag at the time of review | Option | Weeks removed | Extra cost | Drag cost removed | Balance | Decision |
|---|---|---|---|---|---|---|---|
| B App development | 3 | Two extra developers at 12'000 per week removed | 3 | 36'000 | 60'000 | +24'000 | Shorten by 3 weeks. A fourth week would cost 12'000 and gain nothing. |
| G User acceptance testing (UAT) | 3 | Second team of business testers: 1 week at most | 1 | 14'000 | 20'000 | +6'000 | Shorten by one week |
| C App testing | 0 | Test automation at 18'000 per week removed | 0 | – | 0 | – | Drop. On the initial network this option alone would have removed 2 weeks for 36'000 and returned 40'000. |
| A Requirements | 3 | None: the business experts are available only one day a week | 0 | – | – | – | Keep the duration |
| Total | 4 | 50'000 | 80'000 | +30'000 | 18 weeks cut to 14 |
Row C shows why the project manager recalculates. On the initial network B and C total 5 weeks of drag. Together they gain only the 3 weeks of float of the D-E branch.
Visualisations
After the two compressions, branches B-C and D-E are critical at 8 weeks. B, C, D and E have zero drag. Only A, G and H still shorten the project.
Each bar in the chart stacks an activity's budget and its drag cost. Activities off the critical path have their budget only.
Cost
| Phase | Level | Justification |
|---|---|---|
| Preparation | Medium | An up-to-date calculated network with no activity out of sequence, then the cost of delay set with the sponsor. |
| Execution | Low | The three rules for each critical activity on a finish-to-start network; otherwise the duration set to zero in a copy of the schedule for each critical activity. |
| Documentation | Low | A drag table and an options table to redo at each change in the critical path. |
Tooling
Scheduling software such as MS Project, Primavera P6 or ProjectLibre holds the network and calculates the floats. To get the drag of a critical activity, the planner copies the project, sets the activity's duration to zero and reads the new finish date. The difference from the original finish gives the drag. The same software recalculates the critical path after each compression.
A spreadsheet is enough for the drag table and the options table. On a finish-to-start network it applies rule 3 to the exported floats with one formula per critical activity: =MIN(duration; lowest float of the parallel activities).
Sources
- Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., PMI: the definitions of critical path drag and of its cost (Section 5, entries "Critical path drag" and "Critical path drag cost"); the use of the value estimates of the value breakdown structure to estimate drag cost (§2.2.1); the check for another plan that returns more for an element on the critical path (Section 5, entry "Hierarchical charts"); schedule development, which covers network analysis and schedule compression (§2.3.2.2).
- Stephen A. Devaux, "The Drag Efficient: The Missing Quantification of Time on the Critical Path", Defense AT&L, January-February 2012, pp. 18-24, Defense Acquisition University: the zero float of critical activities, the rules for calculating drag, the sources of the cost of delay, drag cost and true cost, the ranking of resource types by true cost, the limits of compression, recalculation when the critical path changes, optional elements and the procedure for bringing forward a deliverable off the critical path.
- Stephen A. Devaux, Total Project Control: A Practitioner's Guide to Managing Projects as Investments, 2nd ed., CRC Press, 2015: the book whose first edition (John Wiley & Sons, 1999) introduced drag and drag cost with calculation exercises.