Timeline over the life of a product: build, go-live, operation. The delivery line separates build from go-live. Prevention costs sit in build. Appraisal costs sit at the checks before delivery. Internal failures sit before delivery under the marker "The team finds the defect". External failures sit after delivery under the marker "The customer finds the defect". One brace groups prevention and appraisal under the cost of conformance. Another brace groups both failures under the cost of nonconformance. A band below the axis names who pays: the project budget up to delivery, then operations, support and sales.

Cost of Quality

The cost of quality (CoQ) is the sum of what an organisation spends to make a product conform to its requirements and what it loses when the product fails to conform. The technique sorts these costs into groups: prevention, appraisal, internal failures that the team finds before delivery and external failures that the customer finds. The report shows where the quality money goes and where to move it so that the total falls. The PMBOK Guide lists the technique as a data analysis tool of the Estimate Costs process and defines it over the whole life of the product.

Goal

The PMBOK Guide defines the cost of quality as all costs incurred over the life of the product to prevent nonconformance to requirements and to appraise the product or service for conformance. It adds the costs of failing to meet requirements.

The deliverable is a report of costs by group with a total and the share of each group. It justifies a prevention budget, ranks failures by cost and checks after a change that the total has fallen. The project manager takes the cost of testing, reviews and fixes from it for the estimate. The quality manager uses it to pick improvement projects. Senior management tracks the total as a share of the product's revenue.

Usage

When to use

  • Estimating project costs: put testing, reviews and rework into the estimate as cost lines.
  • A disputed test or review budget: set it against the cost of the failures these activities prevent.
  • Recurring failures in operation: put a figure on support, fixes and warranty work to rank problems by cost.
  • Choosing improvement projects: select the most expensive failures that affect an organisational objective.
  • After a quality audit or a process change: measure again and check that the total has fallen.
  • Suspected "excess quality": check whether the effort exceeds the customer's requirement.

When not to use

  • No time or defect records: the figures would be guesses; set up measurement first with metrics and KPIs.
  • Judging whether a project is worth its spend: the technique does not measure value; use cost-benefit analysis.
  • Explaining a failure: the technique says what a failure costs, not why it occurs; use root cause analysis.

Description

The cost groups

The project incurs prevention costs to stop poor quality from arising. The PMBOK lists training, process documentation, equipment and the time to do it right. In an IT project, requirements reviews and training the team on a new business rule belong here.

The project incurs appraisal costs to check conformance: measuring, inspecting, auditing, testing. The PMBOK places testing, inspections and destructive testing loss here. Appraisal detects what is already wrong.

Failure costs arise from a product that fails to meet stakeholder needs or expectations. The team finds internal failures before the product reaches the customer: rework, scrap, fixing defects found in acceptance testing. The customer finds external failures: warranty work, liabilities, lost business. For Beecroft, the group depends on who finds the failure: the team or the customer. A calculation error that the test team finds costs a fix. When a user finds it, it costs a ticket, an urgent patch, a reissued document and sometimes a customer.

Cost of quality over the product life
The group depends on who finds the defect
Cost of quality over the product lifeTimeline over the life of a product: build, go-live, operation. The delivery line separates build from go-live. Prevention costs sit in build. Appraisal costs sit at the checks before delivery. Internal failures sit before delivery under the marker "The team finds the defect". External failures sit after delivery under the marker "The customer finds the defect". One brace groups prevention and appraisal under the cost of conformance. Another brace groups both failures under the cost of nonconformance. A band below the axis names who pays: the project budget up to delivery, then operations, support and sales.Cost of conformancePreventionTrainingRequirements reviewAppraisalTestsInspectionsAcceptance testingBuildGo-liveOperationDeliveryThe team finds the defectThe customer finds the defectInternal failuresReworkFixing acceptance-test defectsExternal failuresWarrantyUrgent patchLost businessCost of nonconformanceProject budgetOperations, support, salesCost of quality over the product lifeTimeline over the life of a product: build, go-live, operation. The delivery line separates build from go-live. Prevention costs sit in build. Appraisal costs sit at the checks before delivery. Internal failures sit before delivery under the marker "The team finds the defect". External failures sit after delivery under the marker "The customer finds the defect". One brace groups prevention and appraisal under the cost of conformance. Another brace groups both failures under the cost of nonconformance. A band below the axis names who pays: the project budget up to delivery, then operations, support and sales.BuildProject budgetCost of conformancePreventionTrainingRequirements reviewAppraisalTestsInspectionsAcceptance testingCost of nonconformanceThe team finds the defectInternal failuresReworkFixing acceptance-test defectsDeliveryGo-liveOperationOperations, support, salesThe customer finds the defectExternal failuresWarrantyUrgent patchLost business
Prevention and appraisal make up the cost of conformance. The project pays for them before delivery. Failures make up the cost of nonconformance. The team finds internal failures before delivery. The customer finds external failures after it. Operations, support and sales pay for what occurs after delivery.

The PMBOK calls the first two groups the cost of conformance. The project spends it to avoid failures. The cost of nonconformance combines internal and external failures. It is spent during the project and after delivery.

The cost of quality groups and the question that places an activity in each.
GroupQuestion to classify an activityPMBOK examplesExamples in software
PreventionDoes the activity stop a defect from arising?Training, process documentation, equipment, time to do it rightRequirements review, training on the new occupational pension (BVG) rules, development guidelines
AppraisalDoes the activity check a product already made?Testing, inspections, destructive testing lossAutomated tests, acceptance testing, certification audit
Internal failureDid the team find the defect before delivery?Rework, scrapFixing defects found in acceptance testing, release withdrawn before distribution
External failureDid the customer find the defect?Liabilities, warranty work, lost businessSupport tickets, urgent patches, reissued documents, lost customers

The project and the product life

The PMBOK definition covers the life of the product. The groups it details cover the project's deliverables.

The project manager pays for prevention, appraisal and internal failures out of the project budget. External failures mostly occur after the product is delivered. Operations, support or sales pay for them. A project that stops its report at delivery can lower its own cost by cutting tests. It then shifts a heavier expense onto operations. The full report covers the life of the product, even when the project budget pays for only part of it. Add a column to the report that names who pays for each line: the project, operations, support or sales.

Two vocabularies for the same costs

Juran treated the cost of quality in his 1951 Quality Control Handbook. Feigenbaum divided quality costs into prevention, appraisal and failure in Total Quality Control. This split is called the P-A-F model (prevention, appraisal, failure). The American Society for Quality Control adopted it in 1970. British Standard BS 6143 Part 2 took it up.

Crosby popularised the subject in 1979 with Quality Is Free. He used only two categories. The price of conformance combines prevention and appraisal. The price of nonconformance combines the failures. In Feigenbaum, in Crosby and in the PMBOK, the two vocabularies name the same amounts.

Running the analysis

  1. Choose the scope. A project, a deliverable, a product or a process. Also fix the period: a financial year or the duration of the project.
  2. List the activities. Start from timesheets, invoices, the defect log and support tickets. For a process, draw its flow first.
  3. Classify each activity into one of the four groups by testing it against each group's question. Write the rule for borderline cases once and apply it at every measurement. A code review can be classified as prevention or as appraisal. Consistent classification from one measurement to the next matters more than the choice. An activity that a defect triggers counts as a failure even if it is a test: testing a patch delivered to the customer belongs to external failures.
  4. Cost each activity and total each group. Cost time at the fully loaded hourly rate.
  5. Cost each failure type at standard cost. List the activities that one occurrence triggers, cost each one and add them up. Multiply by the number of occurrences per year. Beecroft describes this method. Applied to an incorrect payslip delivered to a customer, it gives CHF 1'100 per occurrence and CHF 22'000 a year.
  6. Compare and rank. Calculate the share of each group. Relate the total to a base: the product's revenue, the project budget or the cost of production. Rank failure types by annual cost. Target the ones that affect an organisational objective. The Pareto chart shows the most expensive types.
  7. Shift spending to prevention where failures cost the most. Cost the effort that removes the cause. Beecroft counts this effort as prevention.
  8. Measure again after the change with the same classification rules. Only the new measurement shows the effect on the result. According to the PMBOK, correcting the gaps that a quality audit finds should also reduce the cost of quality.
  9. In a project, carry the result into the cost estimate and the quality management plan.
Standard cost of an external failure: an incorrect payslip delivered to a customer. Amounts in CHF.
Activity triggered by one occurrenceBasisCost
Handle the customer's ticket in support1.5 h at CHF 110165
Analyse and fix the calculation4 h at CHF 130520
Test and deliver the patch2 h at CHF 130260
Reissue the corrected payslipFlat rate155
Cost per occurrence1'100
Occurrences per yearTicket log20
Annual cost20 × CHF 1'10022'000

Where is the optimum?

The P-A-F model assumes that more prevention and appraisal reduce failures. More prevention also reduces the appraisal needed. The aim is the quality level that minimises the total.

The PMBOK derives an optimum from this: the cost of quality that balances the investment in prevention and appraisal against the failures it avoids. Beyond the optimum, extra prevention or appraisal returns less than it costs.

The cost of quality optimum in the PMBOK
The cost of quality optimum in the PMBOKCurves on two axes without scale. Prevention and appraisal rise with the level of conformance. Failures fall. Total cost forms a U whose minimum is the Optimum point. A dotted line joins this point to the horizontal axis. The figure follows the PMBOK reading.CostLevel of conformanceOptimumPrevention and appraisalFailuresTotal costPMBOK readingThe cost of quality optimum in the PMBOKCurves on two axes without scale. Prevention and appraisal rise with the level of conformance. Failures fall. Total cost forms a U whose minimum is the Optimum point. A dotted line joins this point to the horizontal axis. The figure follows the PMBOK reading.CostLevel of conformanceOptimumPrevention andappraisalFailuresTotal costPMBOK reading
Prevention and appraisal rise with the level of conformance. Failures fall. Total cost reaches its minimum where extra prevention or appraisal returns less than it costs.

Crosby and Beecroft take another position. Crosby sums it up in his title: quality is free. Beecroft wants to bring failure costs down to zero and calls appraisal a non-value-added activity. The two positions differ on whether a level of prevention exists beyond which the remaining poor quality costs less than its removal. The report settles it case by case. A prevention expense that cuts failures by more than it costs is justified under both readings.

Variants of the model

The process cost model (BS 6143 Part 1) starts from a process. The analyst draws the flow, classifies each activity as a cost of conformance or nonconformance and then costs it. In this model, the cost of conformance covers all work done correctly. It goes beyond prevention and appraisal. The same term therefore covers a different amount than in Crosby. This model applies to any process and ties each cost to its source. A full process analysis takes longer than a P-A-F report.

The process cost model
One year of payroll software releases
The process cost modelActivities classed as conformance: Specify CHF 40'000, Develop CHF 260'000, Test CHF 75'000, Deploy to customers CHF 20'000. Loops classed as nonconformance: Fixing defects found in acceptance testing CHF 54'000 between Test and Develop, Deliver an urgent patch CHF 36'000 after Deploy. Totals: process cost CHF 485'000, conformance CHF 395'000, nonconformance CHF 90'000.Deliver a release of the softwareSpecifyCHF 40'000ConformanceDevelopCHF 260'000ConformanceTestCHF 75'000ConformanceDeploy tocustomersCHF 20'000ConformanceFixing defects found in acceptancetestingCHF 54'000NonconformanceDeliver an urgent patchCHF 36'000NonconformanceProcess costCHF 485'000ConformanceCHF 395'000NonconformanceCHF 90'000=+The process cost modelActivities classed as conformance: Specify CHF 40'000, Develop CHF 260'000, Test CHF 75'000, Deploy to customers CHF 20'000. Loops classed as nonconformance: Fixing defects found in acceptance testing CHF 54'000 between Test and Develop, Deliver an urgent patch CHF 36'000 after Deploy. Totals: process cost CHF 485'000, conformance CHF 395'000, nonconformance CHF 90'000.Deliver a release of the softwareSpecifyCHF 40'000ConformanceDevelopCHF 260'000ConformanceTestCHF 75'000ConformanceFixing defects found inacceptance testingCHF 54'000NonconformanceDeploy to customersCHF 20'000ConformanceDeliver an urgent patchCHF 36'000NonconformanceProcess costCHF 485'000=ConformanceCHF 395'000+NonconformanceCHF 90'000
The model classifies each process activity as conformance or nonconformance. Testing itself counts as conformance. Fixing the defects that testing finds and the urgent patch count as nonconformance. Amounts in CHF.
What conformance and nonconformance cover in each model.
ModelThe cost of conformance coversThe cost of nonconformance covers
P-A-F (Feigenbaum, ASQC, BS 6143 Part 2)Prevention and appraisalInternal and external failures
Crosby (price of conformance)Prevention and appraisalFailures
PMBOK Guide Figure 5-3Prevention and appraisalInternal and external failures
Process cost (BS 6143 Part 1)All work done correctlyFixing failures

Opportunity cost models add the margin lost when customers leave. Models based on activity-based costing separate the activities that add value from those that do not.

Pitfalls

One term for two scopes. Authors do not agree on a definition of quality costs. The term cost of poor quality sometimes means the whole cost of quality and sometimes only the failures. Beecroft notes this looseness. Write the chosen definition at the top of the report.

Hidden costs. Most measurement systems ignore the costs the customer bears, the customer's dissatisfaction and lost reputation. These costs add to external failures. Most of the report's underestimate therefore falls on the heaviest group. The PMBOK lists lost business without putting a figure on it. A line marked as an estimate is better than a missing line.

Overheads. The P-A-F model offers no recognised method for allocating overheads across the groups. Nor does it tie a cost to its source. Set an allocation basis and keep it from one measurement to the next. The process cost model handles the tie to the source.

Freed capacity left idle. Less rework frees hours. They yield nothing until management assigns them to other work. Beecroft adds that laying off the people whose time the improvement frees destroys the effort.

"Excess quality". Beecroft finds that excess quality most often turns out, on examination, to be work beyond the requirement. This overshoot is waste. The team revisits the requirement or reduces the effort.

AI considerations

An assistant reads the labels in timesheets, tickets and the defect log, then proposes a group for each line. On an export of several thousand lines, this sorting replaces the first manual classification. It groups tickets by failure type, counts occurrences and drafts the list of activities that one occurrence triggers. It also flags to the team the lines that no rule classifies.

It does not set the rule for borderline cases. The team decides that rule, writes it down and checks a sample of the assistant's classifications. Nor does the assistant estimate lost business: sales management owns that figure and answers for it. Support tickets for payroll software contain personal data and salaries. Before it loads these tickets into an online service, the team checks the organisation's policy and the FADP.

Examples

Concept illustrated: the report by group shows each group's share of the cost of quality. A Fribourg vendor of payroll software for SMEs records one year of cost of quality for its product.

Cost of quality of a payroll software product over one year. Amounts in CHF. Product revenue: CHF 2'400'000.
GroupItemAmountShare of total
PreventionTraining the team on the new BVG rules12'000
Requirements reviews with a partner accounting firm18'000
Documenting the release process6'000
Subtotal36'00010.8%
AppraisalAutomated tests and their maintenance45'000
Acceptance testing of each release30'000
Swissdec certification audit15'000
Subtotal90'00026.9%
Internal failuresFixing defects found in acceptance testing54'000
Release withdrawn and re-tested before distribution8'000
Subtotal62'00018.6%
External failuresSupport tickets caused by defects48'000
Urgent patches delivered to customers36'000
Incorrect payslips corrected and reissued (20 × CHF 1'100)22'000
Lost customers (estimated annual margin)40'000
Subtotal146'00043.7%
Total cost of quality334'000100%
Share of product revenue13.9%

External failures weigh four times as much as prevention. The lost-customers line is an estimate from sales management. Without it, external failures remain the largest group.

Visualisations

The vendor in the example measures again the following year. It has added CHF 24'000 of prevention: a specification of the BVG rules that it validates with the accounting firm before the development of each release. Fixing defects found in acceptance testing goes down. Internal failures fall from CHF 62'000 to CHF 58'000. External failures fall from CHF 146'000 to CHF 98'000. The drop comes from tickets, urgent patches and reissued payslips, which together fall from CHF 106'000 to CHF 58'000. The lost-customers estimate stays at CHF 40'000. The total falls from CHF 334'000 to CHF 306'000.

The report before and after the shift to prevention
The report before and after the shift to preventionTwo stacked bars on the same scale. Year 1: prevention 36'000, appraisal 90'000, internal failures 62'000, external failures 146'000, total 334'000. Year 2: prevention 60'000, appraisal 90'000, internal failures 58'000, external failures 98'000, total 306'000. Prevention rises by 24'000 and the total falls by 28'000.36'000 · 10.8%Prevention90'000 · 26.9%Appraisal62'000 · 18.6%Internal failures146'000 · 43.7%External failuresYear 1Total 334'00060'000 · 19.6%90'000 · 29.4%58'000 · 19.0%98'000 · 32.0%Year 2Total 306'000Total −28'000Prevention +24'000:BVG rules specificationThe report before and after the shift to preventionTwo stacked bars on the same scale. Year 1: prevention 36'000, appraisal 90'000, internal failures 62'000, external failures 146'000, total 334'000. Year 2: prevention 60'000, appraisal 90'000, internal failures 58'000, external failures 98'000, total 306'000. Prevention rises by 24'000 and the total falls by 28'000.Prevention36'000 · 10.8%Appraisal90'000 · 26.9%Internal failures62'000 · 18.6%External failures146'000 · 43.7%Year 1Total 334'000Prevention60'000 · 19.6%Appraisal90'000 · 29.4%Internal failures58'000 · 19.0%External failures98'000 · 32.0%Year 2Total 306'000Total −28'000Prevention +24'000:BVG rules specification
The vendor adds CHF 24'000 of prevention: a specification of the BVG rules that it validates with the accounting firm before the development of each release. Internal failures fall from CHF 62'000 to CHF 58'000. External failures fall from CHF 146'000 to CHF 98'000. Total cost falls from CHF 334'000 to CHF 306'000.

Cost

PhaseLevelJustification
PreparationMediumSet the scope and the classification rules, then obtain the timesheets, invoices and tickets.
ExecutionHighClassify and cost each activity, then calculate the standard cost of each selected failure. The first measurement takes days.
DocumentationMediumKeep the report by group, the standard costs and the classification rules. Each measurement reuses them unchanged.

Tooling

A spreadsheet is enough for the report by group and the standard cost of a failure. It also draws the Pareto chart of failure types.

The measurement repeats at low cost when time entry carries a code per group. The cost accounting of an ERP such as Abacus or SAP receives these codes. A defect log in Jira or Azure DevOps counts internal failures. A support tool such as Jira Service Management or ServiceNow counts external failures. A dashboard tool such as Power BI tracks the share of each group from one measurement to the next.

Sources

  • Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition, PMI: the cost of quality as a data analysis tool of the Estimate Costs process (§2.4.2.2, Figure 2-28); the definition, the cost groups, Figure 5-3 and the optimum (section 5, Tools and Techniques, entry Cost of quality (CoQ)); the link with quality audits (section 5, entry Audits).
  • G. Dennis Beecroft, Cost of Quality, Quality Planning and The Bottom Line, ASQ Quality Management Division Forum, 2000: the groups with their examples, the distinction between internal and external failures, the history from Juran to Crosby, the standard cost method for a failure, hidden costs and the improvement strategy. A practitioner article without peer review.
  • N. M. Vaxevanidis, G. Petropoulos, J. Avakumovic, A. Mourlas, Cost of Quality Models and Their Implementation in Manufacturing Firms, International Journal for Quality Research, 3(1), 2009: the attribution of the P-A-F model to Feigenbaum, its adoption by the ASQC and in BS 6143, Crosby's model, the process cost model, the other variants and their limits.
Control charts