The reaction plan of one line of the control plan. A reading within the limits leaves the process as it is. A signal on the control chart with a result within tolerance starts the search for the cause and the correction of the process. A result out of tolerance stops the process or isolates the product, then has the product sorted back to the last conforming reading. The owner records each reaction in the log. A reaction that repeats triggers a root cause analysis and a revision of the plan.

Control plan

A control plan is a table that sets, for each characteristic of a product or a process, the limit the result must stay within, the measurement and its frequency, the person responsible and the planned reaction when the result crosses the limit. This last column is the reaction plan. The plan comes from the automotive industry, where the Automotive Industry Action Group (AIAG) publishes its reference manual and the International Automotive Task Force (IATF) requires it from suppliers in its IATF 16949 standard. Six Sigma makes it the deliverable of the Control phase of a DMAIC: the project team hands it to the process owner, who holds the gain after closure.

Goal

The control plan holds a process at the intended level of performance. It tells each person in the process what they measure, when and with which instrument. The reaction plan tells them what to do when the measurement crosses the limit.

Without a plan, the gain of an improvement project fades once the team has left. Nobody records the indicator any more. Where it is still recorded, nobody knows who acts if it drifts. According to the ASQ Black Belt Body of Knowledge, the plan maintains the improved performance, enables continuous improvement and transfers responsibility from the project team to the process owner.

The technique prepares a decision that repeats at every reading: leave the process as it is or react. The authors of the plan take it once, in advance. The operator no longer has to take it alone when the signal appears. The deliverable is the plan: a table with one line per characteristic. The process owner signs it. Once the plan is in use, the reaction log joins it.

Usage

When to use it

  • Closing an improvement project: hand the process owner the measurements and the reactions that hold the gain.
  • Launching a product or a process: set the controls before the first production run, as an automotive customer requires.
  • After an FMEA: turn the high-risk failure modes into controls that each carry a reaction.
  • A characteristic tied to safety or to the law: write down in advance who stops the process and what happens to the suspect product.
  • An indicator tracked without an agreed reaction: attach to the indicator a limit and the person who acts when it is crossed.
  • A process taken over by another team or another site: pass on in writing what the people who ran it before did from memory.
  • An organisation where nobody stops a process without a manager's approval: give the operator the written right to stop when the limit is crossed.

When not to use it

  • A process that is still unstable or poorly described: a plan would freeze a way of working that nobody controls. Stabilise it first with a DMAIC or describe it with a flowchart.
  • Work done only once: nothing repeats that could be monitored. Check the result with a review or an inspection.

Description

The header and the columns

The header identifies the process, the product or the service, the process owner, the version number and the date of the last revision. Each line deals with one characteristic. The columns answer the questions an operator asks at the workstation.

The columns of one line of the control plan and what each one sets.
ColumnWhat it sets
StepThe process step where the reading takes place, under the number it carries in the flowchart.
EquipmentThe machine, the device or the tooling of the step. In a service: the application or the form.
CharacteristicThe quantity under control. A product characteristic describes the result: a weight, a lead time, an error rate. A process characteristic describes a setting or an input that acts on the result: a temperature, a document present in the file.
ClassThe marking of the special characteristics, which concern safety, a legal requirement or a requirement the customer has designated.
Specification or limitThe target and the tolerance. When a control chart tracks the characteristic, the control limit is added to the tolerance.
Measurement techniqueThe instrument, the gauge or the query that produces the value.
SampleThe number of units measured at each reading and the frequency of the readings.
Control methodThe way the value is used: control chart, 100% inspection, attribute inspection, error-proofing device.
ResponsibilityThe person who measures and the person who reacts, when they are not the same.
Reaction planThe trigger, the action on the product, the action on the process, the person who acts and their deadline, the escalation, the record.

In a DMAIC, the product characteristic corresponds to the project's Y indicator. The process characteristics correspond to the X causes that the analysis verified. A line on an X detects the drift before Y shows it.

Where the lines come from

The process flowchart supplies the steps. The process FMEA supplies the failure modes whose risk justifies a control. Each selected failure mode becomes a line. The control method of the plan copies the detection rated in the FMEA. The customer's requirements and the regulations supply the special characteristics.

The inputs and outputs of the control plan
Where the lines come from and where they are used
The inputs and outputs of the control planThe flowchart supplies the steps. The FMEA supplies the failure modes to control and their detection. The customer's requirements and the regulations supply the special characteristics. The measurement system analysis checks the instrument. The plan feeds the readings, the work instructions and the reaction log. A change or a repeated reaction leads back to the revision of the FMEA and the plan.Control planProcess owner, version, revision dateStepEquipmentCharacteristicClassSpecification or limitMeasurement techniqueSampleControl methodResponsibilityReaction planFlowchart:the stepsProcess FMEA:the selected failure modes andtheir detectionCustomer requirements andregulations:the special characteristicsMeasurement system analysis:the verified instrumentReadings and control chartsWork instructionsReaction logRevision: change or repeated reaction
Flowchart: the steps→ Step
Process FMEA: the selected failure modes and their detection→ Characteristic / Control method
Customer requirements and regulations: the special characteristics→ Class
Measurement system analysis: the verified instrument→ Measurement technique
Control planProcess owner, version, revision dateStep, Equipment, Characteristic, Class, Specification or limit, Measurement technique, Sample, Control method, Responsibility, Reaction plan
Readings and control charts
Work instructions
Reaction log
↺ Revision: change or repeated reaction
The flowchart supplies the steps. The FMEA supplies the failure modes to control and their detection. The customer's requirements and the regulations supply the special characteristics. The measurement system analysis checks the instrument. The plan feeds the readings, the work instructions and the reaction log. A change or a repeated reaction leads back to the revision of the FMEA and the plan.

A measurement whose error approaches the tolerance makes the operator react to the error of the instrument. The measurement system analysis checks the instrument before the line comes into force. The AIAG manual on measurement systems analysis (MSA) accepts an instrument whose repeatability and reproducibility error (%GRR) stays below 10% of the tolerance. Between 10 and 30%, acceptance depends on the use. Above 30%, the manual rejects the instrument. In the Control phase, the ASQ Black Belt Body of Knowledge provides for a new measurement system analysis.

The reaction plan

English-language Six Sigma literature also calls the reaction plan a response plan. A complete reaction sets these elements:

  • The trigger: the limit crossed or the pattern on the control chart.
  • The action on the product: isolate and sort what was produced since the last conforming reading.
  • The action on the process: stop, adjust or switch to degraded mode, then confirm with a new reading that the process is back within the limit.
  • The owner and the deadline: a person named by role, with the hour or the day by which the action must be done.
  • The escalation: the person who takes over the case when the immediate action does not bring the process back within the limit.
  • The record: the log records the date, the reading, the cause found and the action taken.

A result out of tolerance signals a nonconforming product. The reaction stops the process or isolates the suspect product, sorts it, then looks for the cause. A signal on a control chart with a result still within tolerance signals a process that has changed. There is no product to sort. The reaction looks for the cause before the drift reaches the tolerance. The IATF 16949 standard names both cases: it requires the reaction plan to be applied when a nonconforming product is detected and when the process becomes statistically unstable or not capable.

The frequency sets the quantity of suspect product when a reading crosses the tolerance: everything produced since the previous reading. One reading per eight-hour shift exposes eight hours of production to sorting. The authors of the plan set the frequency according to what this suspect production costs. The sample size sets the chance of seeing the defect at each reading.

A reaction that repeats shows that the action on the product treats the effects and leaves the cause in place. The escalation then opens a root cause analysis. Its result changes the process, the FMEA and the line of the plan. Each line of the plan defines what "repeats" means, for example two reactions on the same line within a month. Line 2 of the example sets this threshold at more than five cases in the week.

Building the plan

  1. List the characteristics. The team starts from the flowchart and the process FMEA. It selects the steps, the product characteristics and the X causes whose risk justifies a reading.
  2. Set the limits. For each characteristic, the team writes the target and the tolerance. When a control chart tracks the characteristic, the team calculates the control limits from the data of the stable process.
  3. Choose the measurement technique. The team names the instrument or the query and checks the measurement system before relying on it.
  4. Set the sample. The team bases the frequency of the readings on the cost of the suspect production between two readings. It bases the number of units measured on the chance of seeing the defect at each reading.
  5. Choose the control method. An error-proofing device prevents the defect. An inspection finds it afterwards. A control chart detects the drift before the defect. The line records the method chosen.
  6. Name the people responsible. The team names by role the person who measures and the person who reacts. Each accepts their role before the plan comes into force.
  7. Write the reaction plan. The team writes a complete reaction for each line.
  8. Hand over the plan. The process owner signs the plan. They train the people named on their line and their reaction. The work instructions of standardised work copy the line that concerns each workstation.
  9. Revise the plan. The owner revises it at every change of the process, the product, the measuring instrument or the FMEA. A reaction that repeats also triggers a revision.

IATF 16949 distinguishes three versions of the plan, which follow the product through advanced product quality planning (APQP). Where the customer requires it, a prototype version describes the measurements on the prototypes. The pre-launch version tightens the controls during the launch. The production version describes the control of series production.

Outside industry, the plan usually describes only the process in operation. The columns stay. The equipment becomes the business application. The characteristic becomes a lead time, an error rate or a share of complete files. The instrument becomes a query in the business application.

The control plan and its neighbours

The metrics and KPIs technique defines the indicator, its target, its collection and its reporting to stakeholders. The control plan adds to each characteristic a limit and the agreed reaction when it is crossed. It is written for the people who run the process.

A line of the plan can use the control chart as its control method. The chart detects the signal. The plan says who responds to it and how.

In French, the control plan is called plan de contrôle. The French edition of HERMES gives this name to a document of its own. The English edition names it the review plan. It is a chapter of the project management plan. It sets the project outcomes to be checked, their checking procedures and the role that carries out each check. The checks take place during the project, before the outcomes are accepted. The control plan of the AIAG and of Six Sigma monitors a process in operation. A HERMES project that delivers a changed process keeps both.

Common mistakes

A reaction without an actor. "Inform the team leader" or "adjust the process" says neither who acts, nor on what, nor by when. The operator improvises at the first signal. The plan was meant to spare them this decision.

Sorting without correcting. The reaction isolates the suspect product and stops there. The defect comes back the following week. The same reaction comes back with it.

The plan left with the project team. The team writes the plan and keeps it. The process owner has not signed it. The people named do not know they have been named. The plan stops working when the project closes.

An instrument never checked. The line reacts to the measurement error as much as to the process. The team sorts conforming product and adjusts a process that had not moved.

A plan that describes the intended process. The plan prescribes one reading per hour. The team takes two a day. At each revision, the owner compares the plan with what is done at the workstation.

A frozen plan. The process changes and the plan stays. Its lines control a step that was removed and ignore the step that was added.

AI considerations

An assistant drafts a first version of the lines from the FMEA export: one line per selected failure mode, with the step, the characteristic and the rated detection. The analyst checks that each line matches a real failure mode and that the model has not added a characteristic absent from the FMEA.

The model reads the plan back as a checklist. It flags the lines without an owner, without a frequency or with a reaction that names no action.

The limits do not come from the model. The tolerance comes from the customer, the law or the drawing. The analyst calculates the control limit from the process data in the spreadsheet or the statistics package. The team negotiates their role and their deadline with the people named. The model does not know who has the authority to stop the process.

On a reaction log kept over several months, the model groups the entries by cause and spots the reactions that repeat. It suggests leads. The root cause analysis confirms or rejects them.

The plan of a service process often carries personal data: patient files and employee names in the log. Health data are sensitive personal data within the meaning of art. 5 let. c FADP. The analyst removes the identifiers before handing an extract to an external AI service.

Examples

The head of the benefits department of a health insurer in French-speaking Switzerland takes over the plan below at the close of a DMAIC project on the reimbursement of physiotherapy invoices.

Control plan for the reimbursement of physiotherapy invoices. Version 1 of 10 November. Owner: head of the benefits department.
No.Characteristic (step)LimitMeasurement and sampleControl methodResponsibilityReaction plan
1Share of invoices reimbursed after more than 15 working days (process output)Upper control limit: 12%. Mean after the project: 8%. Target: below 10%.Extract from the benefits application. The roughly 360 invoices of the week. Every Monday.p-chartMeasurement: quality analyst. Reaction: head of the benefits department.Point above 12%: within two working days, the head of department breaks down the late invoices by step. Cause at step 2: see line 2. Other cause: she opens a root cause analysis. Entry in the log.
2Prescription request sent to the physiotherapist on the day the first invoice of a series arrives (step 2, data entry)100% of first invoicesException list from the application. All first invoices of the day. Every evening at 17:00.100% inspectionData entry team leaderList not empty: the team leader sends the missing requests before 10:00 the next day. More than five cases in the week: she has IT check the rule that issues the request. Entry in the log.
3Invoices without a date of receipt (step 1, scanning)1% at mostSame extract as line 1. Every Monday.100% inspectionQuality analystAbove 1%: the analyst marks the week as not interpretable on the chart of line 1. She reports the defect to the scanning service the same day. Entry in the log.

The limit comes from the p-chart: 8% + 3 × √(0.08 × 0.92 / 360) ≈ 12.3%. The plan rounds it to 12%.

A week at 11% misses the target without crossing the control limit. Line 1 triggers nothing: the chart places this point within the ordinary variation of the process. Line 3 controls the measurement of line 1. Without it, a scanning failure would make the head of department react to a false rate.

Visualisations

The reaction plan reads better as a diagram: the reading follows a branch according to the limit it crosses. The inputs and outputs of the plan form a second diagram. The columns of a line, the health insurer's plan and the cost are made of rows and columns, so they are tables.

Cost

DimensionLevelJustification
PreparationMediumThe team gathers the flowchart, the FMEA and the baseline data. It names the people responsible with their agreement.
ExecutionLowThe readings become part of routine work. A reaction costs the time of the action it prescribes.
DocumentationMediumEvery change requires a revision of the plan under a new version number. Every reaction adds an entry to the log.

Tooling

A spreadsheet is enough to keep a control plan. One sheet carries the header and the columns. A second sheet holds the reaction log. The spreadsheet works as long as one person keeps the plan and the lines number in the dozens.

FMEA software such as APIS IQ-RM or Plato e1ns generates the control plan from the process FMEA. The software then carries every change of the FMEA into the plan. These packages suit automotive suppliers, who keep hundreds of lines under several versions.

In a service process, the business application supplies the readings. A scheduled query produces the extract of each period and the exception list. Minitab, JMP or a Python script draw the control charts that the lines use.

At the workstation, a laminated card displays the line of the plan that concerns it: the limit, the frequency and the reaction. The operator does not have to open the plan to know what to do.

Sources

  • AIAG, Quality Core Tools: the Control Plan manual (1st ed., 2024), the Advanced Product Quality Planning (APQP) manual (3rd ed., 2024) and the Measurement Systems Analysis (MSA) manual (4th ed., 2010). The control plan among the quality tools of the automotive industry, beside APQP, FMEA, MSA, statistical process control (SPC) and the production part approval process (PPAP). The acceptance rule for an instrument according to its %GRR.
  • ASQ, Certified Six Sigma Black Belt Body of Knowledge (2022), VIII.C.1, VIII.C.2 and VIII.D.2: the new measurement system analysis in the Control phase, the three purposes of the control plan and its place among the documents that maintain the gain.
  • ASQ, Certified Six Sigma Green Belt Body of Knowledge (2022), VI.B.1: the control plan that documents and monitors the process.
  • IATF, IATF 16949:2016, §8.5.1.1 and Annex A: the control plan required of automotive suppliers, its minimum content and the cases where the reaction plan applies.
  • Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management Reference Manual, task Perform quality assurance: the review plan in the project management plan, which sets the outcomes to be checked and their checking procedures.