Communication map of a cantonal tax administration that is replacing its online tax return portal. Four concentric rings lie over a grid of four quadrants: group meeting, email, one-on-one meeting (1:1) and instant messaging. At the centre, the core team exchanges information several times a day in group meetings and by instant messaging. On ring 2, the developers and the tax assessment business leads receive information every week. On ring 3, the steering committee meets every month in a group meeting. On the same ring, IT operations and the staff committee receive an email every month. The data protection officer on ring 3 has a one-on-one meeting. On ring 4, the sponsor has a one-on-one meeting every two weeks. On ring 2, the call centre's note has a dashed outline and sits on the vertical axis. It carries the mark "no channel".

Concentric Communications

Concentric Communications is a technique for planning a project's communications with its stakeholders. The team places its stakeholders on concentric rings laid over a grid of four quadrants. The ring sets the priority and the cadence. The core team sits at the centre. The quadrant sets the channel: email, group meeting, one-on-one meeting (1:1) or instant messaging. For each stakeholder the map answers who, when, what and how. It shows the stakeholder that no channel reaches. George W. Anderson describes the technique in Design Thinking for Tech (2023).

Goal

Concentric Communications sets what information each stakeholder in a project receives, how often and through which channel.

On this map the team sets the cadence and the channel of each stakeholder. It spots the stakeholder that no channel reaches.

Anderson links the map to the communication management plan. In chapter 7 his input is the engagement strategy that the power/interest grid sets for each stakeholder. From it he derives how often to communicate, in what format and why. These answers go into the plan. Anderson adds that the plan can take the form of this map. The map gives an overview of the communication plan.

Usage

When to use it

  • Project start: draw the map as soon as the stakeholder list exists and before the first steering committee meeting.
  • Project overseen by several bodies: steering committee, sponsor, staff committee; set a cadence and a channel for each one.
  • After the stakeholder matrix: turn the engagement strategy it sets for each stakeholder into a cadence and a channel.
  • Complaints such as "nobody tells us anything": look on the map for the stakeholder without a channel or the cadence that the team does not keep.
  • Change of strategy or direction: look up on the map the recipients and the channel for the new "why" and the new "when".
  • Team spread over several sites: the map names the channels that corridor conversations no longer provide.

When not to use it

  • Stakeholders not yet identified: the map has nothing to place; draw up the stakeholder list first.
  • Formal communication plan required: the map names neither the sender nor the content of each message; write the communication plan.

Description

Anderson suggests drawing the rings and the grid on the bullseye template. The onion diagram also arranges stakeholders on rings by their distance from the solution. Concentric Communications places them by how much information they receive and how often. The grid adds the channel.

With Anderson's Inclusive Communications technique, the team chooses the channel person by person and words the message. This split between the two techniques is our reading.

The elements of the map

The ring carries a priority and a cadence. The core team sits at the centre. The other rings group people who know less than the core team. Some receive part of the information. Others receive all of it at a slower cadence.

The quadrant carries a channel. Anderson names email, the group meeting, the one-on-one meeting (1:1) and instant messaging. He also names the newsletter, the portal, the website and the blog.

The note (a sticky note) carries the name of a person, a group or a governance body. The note goes on the stakeholder's ring and in the quadrant of the channel that reaches the stakeholder. Anderson allows up to four channels per stakeholder. One stakeholder can therefore have a note in several quadrants of the same ring.

The inputs

The inputs to the map are the stakeholder list and the engagement strategy that the power/interest grid sets. A Stakeholder+ Mapping adds what the team believes each stakeholder expects.

How to communicate with each quadrant of the power/interest grid according to Anderson (chapter 7).
QuadrantCommunication
Manage closelyMeet them regularly in the governance bodies. Take notes on the exchanges and follow up. Give them priority in communications.
Keep satisfiedSend them regular communications. Copy them on important emails and messaging threads.
Keep informedInform and consult them.
MonitorInclude them in a suitable communication cadence. Watch for changes in their role.

A stakeholder's ring follows from two answers: what the stakeholder must know (everything, part of it or basic awareness) and how long the stakeholder can wait (the same day, a week or a month). A stakeholder with high power can therefore sit on an outer ring. This test is our addition.

The core team can draw the map itself: it sends most of the communications and knows the stakeholders. In our view, a session of one to two hours is enough for the core team to place twenty to thirty stakeholders.

The steps

  1. Choose the channels. The team picks four main channels and assigns a quadrant to each. With six or eight channels, it cuts the grid into as many sectors.
  2. Fill the core. Ring 1 brings together the people who lead the project day to day: the person who steers it (project manager, product manager or Scrum Master), the enterprise architect, the lead solution architect, the lead business analyst or functional lead, the development lead and the test lead. This core keeps control of the project. Its members exchange information in real time several times a day in meetings, by email or by instant messaging.
  3. Draw ring 2. The wider team needs part of what the core knows. Or it needs to know everything at a slower cadence: every two or three days or once a week instead of every day. The team assigns named people and governance bodies to this ring. It sorts them by channel into the quadrants. The progress report goes out by email. The weekly status meeting sits in the group meetings quadrant.
  4. Draw ring 3. A wider group needs basic awareness. Or it needs to know everything but can wait a few weeks, a month or more. The team assigns named people and bodies to this ring as well.
  5. Draw ring 4. The sponsor and the other senior executives take their place here. Under normal circumstances, the book recommends an update for them every two weeks. The team sorts these communications by channel into the quadrants.
  6. Add rings. The team adds as many rings as it takes to cover everyone around the project: stakeholders, governance bodies, user communities, specialist contributors, partners, service providers and supporters.

The cadences in the book

Anderson gives ranges. His text and his Figure 15.5 disagree.

The cadences by ring according to Anderson's text and his Figure 15.5.
RingInformation needTextFigure 15.5
1 (core)All the information in real timeIn real time, several times a dayDaily
2 (wider team)Part of the information or all of it less oftenFor "everything, less often": for example every two or three days or once a week2x a Week
3 (wide circle)Basic awareness or all the detail laterFor "everything, later": a few weeks, a month or moreWeekly
4 (sponsor and executives)The book does not say"Biweekly" under normal circumstances2x a Month

The word "biweekly" means either every two weeks or twice a week. The figure puts "2x a Month" on the outer ring. It supports the reading "every two weeks".

According to the text, ring 3 can wait a few weeks or a month. Ring 4 receives an update every two weeks. The outer ring can therefore receive information more often than ring 3. The figure makes the cadence decrease from ring to ring. Each team sets its own cadences and writes each one on its ring.

Reading the map

According to Anderson, the map arranges stakeholders by what they need to know (the what) and by their cadence (the when). It makes visible the forgotten stakeholders (the who) and insufficient or missing communications. It shows how the cadence and the channel (the how) change from the core to the outer rings. The team adjusts them.

The team places the note of a stakeholder without a channel so that it straddles the vertical axis of the stakeholder's ring. The note carries the mark "no channel". The team then rereads the map with these questions.

  • Which note is still on the axis? That stakeholder has a ring but no channel.
  • Which governance body in the project organisation chart is missing from the map?
  • Which ring has only one channel? A failure of that channel cuts off the whole ring.

This convention and these questions are our additions.

Keeping the map up to date

Anderson asks for consistent communications: each ring must be able to rely on their frequency and their accuracy. When the strategy or the direction changes, the team sends the new "why" and the new "when" to the right audience at the right time. Deadlines set in advance (Anderson's Forcing Functions) keep each cadence on schedule.

When a new stakeholder arrives with communication or channel needs of its own, Anderson suggests a dedicated ring. The team can review the map at every milestone and at every change in governance. This rule is our addition.

The pitfalls

The book warns against one pitfall only: irregular communications. The other pitfalls are our judgement.

Letting a cadence slip. An update announced and then skipped leaves a void. In the same chapter, Anderson notes that poorly informed people fill this void with their own ideas and fears.

Confusing less information with later information. On rings 2 and 3, a stakeholder receives either part of the information or all of it at a slower cadence. A team that does not decide sends all the detail to someone who wanted a summary. The opposite error withholds the detail from someone who needed to know everything. A "summary" or "full" mark on each note removes the ambiguity.

Reading the ring as a rank. The outer ring gives a cadence. Anderson places the sponsor there. The book recommends an update for the sponsor every two weeks. A senior executive who finds themselves on the outer ring may read it as being sidelined. Before a team shows the map to management, it explains what the ring measures.

Reading an empty quadrant as a gap. An empty quadrant says that the ring does not use that channel. The gap is the stakeholder that no channel reaches.

Taking the map for the plan. The map says who receives the information, at what cadence and through which channel. The communication plan sets the sender, the content and the date of each message.

AI considerations

A language model proposes a draft allocation from the stakeholder list, the project organisation chart and the power/interest grid. It suggests a ring and channels for each name. The core team corrects this allocation. The model does not know that a head of department never reads email or that a committee sits only once a quarter.

To spot gaps, a model also compares the map with the distribution lists and the recurring meetings in the calendar. A stakeholder who is on the map and absent from every list is a probable gap. The team checks each case: a phone call leaves no trace in these lists.

For each ring, a model drafts the version of the message that matches the ring's depth: all the detail for the core, a summary for ring 3. The person who sends the message checks each summary. A model sometimes leaves out the decision that the ring was meant to learn.

The team alone decides which ring an executive sits on. That choice affects a relationship that the model knows nothing about.

The map, the distribution lists and the calendar contain personal data within the meaning of the Federal Act on Data Protection (FADP): names, job titles and working habits. For a cantonal administration, the cantonal data protection act applies. The team entrusts the analysis only to a service that the organisation has approved.

Examples

A cantonal tax administration is replacing its online tax return portal. The map shows its communications at the launch of the project. The example is invented.

Map at the launch of the tax portal project. Invented example. The call centre's note sits on the axis of ring 2: no channel reaches it.Communication map of a cantonal tax administration that is replacing its online tax return portal. Four concentric rings lie over a grid of four quadrants: group meeting, email, one-on-one meeting (1:1) and instant messaging. At the centre, the core team exchanges information several times a day in group meetings and by instant messaging. On ring 2, the developers and the tax assessment business leads receive information every week. On ring 3, the steering committee meets every month in a group meeting. On the same ring, IT operations and the staff committee receive an email every month. The data protection officer on ring 3 has a one-on-one meeting. On ring 4, the sponsor has a one-on-one meeting every two weeks. On ring 2, the call centre's note has a dashed outline and sits on the vertical axis. It carries the mark "no channel".Group meetingEmailOne-on-one meeting (1:1)Instant messagingRing 1 · coreseveral times a dayRing 2every weekRing 3every monthRing 4every two weeksDirector of the taxadministration (sponsor)Data protectionofficerSteeringcommitteeStaff committeeTax assessmentbusiness leadsTax assessmentbusiness leadsIT operationsDevelopersDevelopersCore teamCore teamCall centreno channel
Ring 1 · core several times a day
Core teamGroup meetingCore teamInstant messaging
Ring 2 every week
DevelopersGroup meetingDevelopersEmailTax assessment business leadsGroup meetingTax assessment business leadsEmailCall centreno channel
Ring 3 every month
Steering committeeGroup meetingIT operationsEmailStaff committeeEmailData protection officerOne-on-one meeting (1:1)
Ring 4 every two weeks
Director of the tax administration (sponsor)One-on-one meeting (1:1)
Map at the launch of the tax portal project. Invented example. The call centre's note sits on the axis of ring 2: no channel reaches it.

The call centre's note sits on the axis of ring 2. The call centre will answer taxpayers from go-live. Without a channel, it would learn about changes to the portal from the taxpayers. The team therefore invites it to the weekly meeting of the business leads.

The map follows Anderson's text: ring 4 receives information every two weeks and ring 3 every month.

Visualisations

The cadence table sets Anderson's text against his figure. The example map shows the result and the stakeholder without a channel.

Cost

DimensionLevelJustification
PreparationLowThe stakeholder list and the power/interest grid often exist already. The bullseye template provides the background.
ExecutionMediumThe core team places the notes in one session. It then keeps each cadence for the whole project.
DocumentationLowOne map to update with each new stakeholder or each change of cadence.

Tooling

In the room, a whiteboard and sticky notes in one colour per ring are enough. For a remote team, a virtual whiteboard such as Miro, Mural or Microsoft Whiteboard holds the target and the grid. A spreadsheet turns the map into a list that feeds the communication plan. Each row holds one stakeholder and one channel. The shared calendar holds the recurring meetings of each ring. Scheduled reminders in the calendar or the tracking tool flag a missed cadence.

Sources

  • George W. Anderson, Design Thinking for Tech: Solving Problems and Realizing Value in 24 Hours, Addison-Wesley, 2023, ISBN 978-0-13-793303-7. Hour 15 "Cross-Teaming and Communicating for Outcomes", section "Design Thinking in Action: Concentric Communications", pp. 224-226: the definition, the steps, the cadences by ring, Figure 15.5 and the uses of the map. In the same chapter, the section "Design Thinking in Action: Inclusive Communications": the technique that covers the channel per person and the wording of the message, the dedicated ring and the void that a missing communication leaves. Hour 7 "Connecting with the Right People", section "Design Thinking in Action: The Power/Interest Grid for Prioritizing": the link with the power/interest grid and the communication management plan.

The book borrows only the layout of the bullseye template. The tax portal case, the reading of "biweekly", the review questions, the "summary" or "full" mark and most of the pitfalls are our additions.