Communication calendar of a 20-week project with one row per audience: steering committee, project team, supplier, staff committee and employees. Each mark carries an event, its method (interactive, push or pull) and its sender. A padlock marks the messages whose release needs authorisation: the test data extracts for the supplier and the announcement and reminder to employees. The phases end in weeks 8, 16 and 20.

Communication Plan

The communication plan is the document that sets the recipients, the sender, the date or frequency and the channel of each piece of project information. For confidential information it also names the person who authorises its release. HERMES places it in the project management plan and assigns it to the project manager. The plan turns the stakeholder list into a calendar of dated communications. The team then distributes the information according to the plan and checks that each stakeholder has received what they need.

Goal

The communication plan usually takes the form of a table with one row per planned communication. Each row states which information goes out, to whom, why, when, from whom, by what means and with what expected response. The PMBOK Guide calls it the communications management plan. It defines it as the component of the project management plan that describes how, when and by whom information is administered and distributed. The plan also describes how project communications are planned, structured, implemented and monitored.

The plan fills a common gap: everyone knows that the steering committee "must be kept informed" while nobody knows who sends what on which date. The plan replaces that intention with dated rows: "the project manager sends the report five working days before each committee meeting".

The communication plan complements the stakeholder engagement plan. The engagement plan says how each stakeholder's involvement should change. The communication plan says which information reaches the stakeholder, through which channel and on which date. Choosing the method for a message belongs to communication models and methods, which the PMBOK places in the same process.

Usage

When to use it

  • Project management plan in preparation: from the initiation phase on, HERMES counts the communication plan among the chapters of the project management plan.
  • Recipients spread over several sites or languages: set the language, the channel and the time zone of each message.
  • Remote team: plan the interactive check-ins that corridor conversations no longer replace.
  • Confidential information to distribute: name the person who authorises each release before the first message goes out.
  • Supplier or external partner in the team: define what leaves the organisation, through whom and in what form.
  • Hierarchical organisation: write down the approval paths and the distribution list of each report.
  • Phase change or new stakeholder: review the rows, the recipients and the frequencies.
  • Stakeholder who says they are poorly informed: check whether a row covers them, who sends it and on which date.

When not to use it

Description

The PMBOK Guide describes the Plan Communications Management process in §2.5.2.3, in the Stakeholders performance domain. It lists the items of the plan in Section 4 and the tools of the process in Section 5.

The items of the plan

The PMBOK leaves the list of items open and does not group them. Each item answers a question that a row of the plan raises.

QuestionPMBOK items
What and whyStakeholder communication requirements; information to be communicated with its language, format, content and level of detail; reason for distribution
To whomIndividuals or groups who receive the information and their needs, requirements and expectations
From whomPerson responsible for communicating the information; person who authorises the release of confidential information
WhenTime frame and frequency of distribution; any expected acknowledgement or response
HowMethods or technologies (memos, emails, press releases, social media); glossary of common terms; flow charts of information flow, approval paths, list of reports, meeting plans
With what resources and within what limitsResources allocated in time and budget; constraints from legislation, regulation, technology or organisational policies
When something deviatesEscalation process
How the plan evolvesMethod for updating the plan as the phases and the stakeholders change
The items of the communications management plan according to the PMBOK. Each row groups the items that answer the same question.

The plan can also carry templates and guidelines for project status meetings, team meetings, virtual meetings and emails. The glossary belongs in it because one word travels across several disciplines and several languages. In a payroll project, "statement" means the payslip to the HR department and an account statement to finance.

Inputs and downstream processes

Among the inputs of the process, the PMBOK cites the stakeholder register, which gives the plan the names and the sites. The stakeholder engagement plan adds the target engagement of each stakeholder. The resource management plan supplies the roles. The requirements documentation states which information the solution must produce. The project charter names the sponsor and sets the milestones.

Manage Communications (§2.5.2.5) produces and distributes the information according to the plan. Monitor Communications (§2.5.2.7) checks against the plan that the information needs of the project and its stakeholders are met. Plan Communications Management also updates the project schedule: a steering committee meeting or a briefing session needs a slot in the calendar and the time of the people who attend.

Inputs and uses of the communication plan
Processes of the PMBOK Guide, 8th edition
Main inputs
Project charterResource management planStakeholder engagement planRequirements documentationStakeholder register
Plan Communications ManagementPMBOK §2.5.2.3
Updates: stakeholder engagement plan, project schedule, stakeholder register
Communication plan
Manage CommunicationsPMBOK §2.5.2.5produce and distribute according to the plan
Monitor CommunicationsPMBOK §2.5.2.7information needs met?
update at each phase or new stakeholder
The communication plan comes out of Plan Communications Management. It guides Manage Communications and Monitor Communications. It returns for an update when the stakeholders change.

Building the plan with the PMBOK and HERMES

  1. Start from the stakeholder list. The register gives the name, role, site and influence of each stakeholder. HERMES bases communication planning on the stakeholder list. A stakeholder missing from the register has no row in the plan.
  2. Analyse the communication requirements. The project manager or the analyst questions the recipients in interviews or workshops and rereads the lessons learned from earlier projects. According to the PMBOK, a requirement combines the type and format of the information with its value to the recipient. As sources it cites organisation charts, responsibilities and dependencies, the development approach, the disciplines involved, the number of people and sites, internal and external needs and legal requirements.
  3. Classify the information. The PMBOK distinguishes internal or external, sensitive or public, general or detailed information. Sensitive information calls for a named approver. External information calls for a spokesperson.
  4. Choose the method and the technology of each row. What the recipient must do with the information decides whether the method is interactive, push or pull. The PMBOK makes the choice of technology depend on urgency, on the availability and reliability of the tools, on their ease of use, on the project environment and on confidentiality. The environment covers on-site or remote work, time zones, languages and culture.
  5. Assign the roles. Each row names a sender. A row that carries confidential information also names the person who authorises its release. A RACI matrix of the communications makes these roles visible when there are many rows.
  6. Set the date and the expected response. Each row receives a date, a frequency or a trigger event. It states whether the recipient acknowledges receipt, replies or decides. The dates go into the project schedule.
  7. Write the escalation. The row says whom to alert, within what time and through which channel when a report is missing, when an expected decision does not come or when a variance exceeds a threshold.
  8. Budget the resources. Meetings, translations, licences and writing cost time and money.
  9. Coordinate and keep the plan current. HERMES asks the project manager to coordinate the communication measures with the sponsor. The project manager then keeps the plan up to date and refines it during the detailed planning of each phase. HERMES integrates decision planning into it: the plan says which decision the sponsor or the committee takes and at which meeting.

The tools of the process complement these steps. Communication styles assessment identifies the method, the format and the content that a stakeholder prefers. The PMBOK often recommends it for unsupportive stakeholders. It can follow the stakeholder engagement assessment matrix, which the PMBOK also counts among the tools of the process. Political and cultural awareness guides the choice of sender and tone.

Pitfalls

Writing an intention. "Inform users regularly" names no content, no sender and no date. Nobody can establish that the row was not honoured. A verifiable row carries an event, a person and a date: "announcement of the cutover date to the 600 employees by the HR director in week 13".

Duplicating the engagement plan. A "strategy" column per stakeholder turns the communication plan into a second engagement plan. The two documents diverge at the first update. The communication plan sticks to the messages. The strategy stays in the engagement plan.

Forgetting the approver. An analyst sends an extract of salary data to the supplier to prepare the tests. Nobody has said who authorises this transfer. The supplier processes the data on behalf of the company. Art. 9 of the FADP (SR 235.1) governs this case of processing by a processor.

Confusing sent with received. An email that has gone out proves neither reading nor understanding. The plan sets the expected response for each row that calls for one. Communication models and methods cover the proof that each method provides.

Freezing the plan after initiation. Stakeholders change from one phase to the next. The staff committee joins the register when the new payslip is ready for consultation. The key users arrive in the implementation phase. The project manager therefore rereads the plan at the end of each phase and each time a stakeholder joins the register.

Ignoring language. In Switzerland a project that covers two language regions produces two versions of each message to employees. The plan says who translates, who reviews and how many days the translation adds. Otherwise the German version goes out three days later. Sometimes it announces a different cutover date.

AI considerations

A language model produces a first draft of the plan from the stakeholder register and the project schedule: one row per audience, one frequency per type of report. It checks an existing plan and flags the rows without a sender, a date, an expected response or an approver for information classified as sensitive. It converts the table into a calendar and spots the weeks in which the same audience receives four messages. It drafts the French and German versions of a message that the plan provides for. During monitoring it groups the questions received by audience to show which rows fail to cover the need.

The tool does not decide who authorises a release or what is confidential. It knows nothing of the tensions between two departments or of the weight that a sender carries with a given audience. The stakeholder register contains names, job titles and sometimes judgements about people. The project manager submits it to a hosted service only with the organisation's approval. If necessary the project manager first removes the names and the judgements. A German-speaking colleague from the department reviews each translation meant for employees.

Examples

A company with 600 staff replaces its payroll software at its Fribourg and Bern sites. Go-live falls in week 20. The HR director is the sponsor. The project manager is Claire Rey (CR). The business analyst is Jonas Meier (JM).

InformationRecipientsSenderAuthorises releaseMethod, medium, languageScheduleExpected responseEscalation
Project status reportSteering committeeCR–Push: email with the report; FrenchEvery 4 weeks, 5 working days before the committeeWritten questions before the meetingProject delay over 2 weeks: CR calls the sponsor the same day
Steering committee meetingSteering committeeSponsor–Interactive: room in Fribourg and video conference; FrenchWeeks 4, 8, 12, 16 and 20Decisions in the minutes within 2 daysDecision postponed: extraordinary meeting within 10 days
Team check-inProject team, including 2 people from the supplierCR–Interactive: 30-minute video conference; French and GermanEvery MondayBlockers raised in the meetingBlocker over 3 days: entered in the next report
Pseudonymised test data extractsSupplierJMHR directorPush: encrypted upload to the exchange platformWeeks 8 and 14Acknowledgement of receipt from the supplierIdentifiable data found: transfers stop and the HR director is informed the same day
Consultation on the new payslipStaff committeeSponsor–Interactive: meeting in Fribourg; French and GermanWeek 10Written opinion within 5 working daysNegative opinion: item at the week 12 committee
New payslip and cutover date600 employeesSponsorExecutive boardPush: personal bilingual emailAnnouncement in week 13 and reminder in week 18None–
Project pageAll employeesJM–Pull: intranet; French and GermanUpdated in weeks 8, 16 and 20None–
Communication plan for the payroll software replacement: seven rows, each with its recipients, its sender, its method, its schedule, the expected response and the escalation. Two rows name the person who authorises the release.

Two rows carry an approver. The test extracts are pseudonymised and therefore remain personal data. The announcement stays confidential until it is sent because it commits the company to its staff. The staff committee is consulted three weeks before the announcement: a negative opinion can still change the message before it goes out.

Visualisations

Read week by week, the same plan shows the load on each audience and the order of the messages.

Communication calendar of the payroll project
One lane per audience over 20 weeks
interactivepushpullrelease authorised in advance
Go-live
Concept
Implementation
Deployment
Week
1234567891011121314151617181920
Steering committee
Wk 3Report · push CR
Wk 4Meeting · interactive Sponsor
Wk 7Report · push CR
Wk 8Meeting · interactive Sponsor
Wk 11Report · push CR
Wk 12Meeting · interactive Sponsor
Wk 15Report · push CR
Wk 16Meeting · interactive Sponsor
Wk 19Report · push CR
Wk 20Meeting · interactive Sponsor
Project team
Wk 1 to 20Team check-in every Monday · interactive CR
Supplier
Wk 8Test data · push JM
Wk 14Test data · push JM
Staff committee
Wk 10Consultation · interactive Sponsor
Employees
Wk 8Intranet page · pull JM
Wk 13Announcement · push Sponsor
Wk 16Intranet page · pull JM
Wk 18Reminder · push Sponsor
Wk 20Intranet page · pull JM
The communication plan of the payroll software replacement read week by week. The steering committee receives the report in the week before each meeting. The staff committee is consulted in week 10. The announcement to employees follows in week 13. A padlock marks the messages that need authorisation.

Cost

PhaseLevelJustification
PreparationMediumAn up-to-date stakeholder register, then a few interviews on the information needs of the main audiences.
ExecutionLowOne working session to fill in the table, then coordination with the sponsor; the cost of the messages themselves sits in the plan.
DocumentationMediumA table to reread at the end of each phase and with each new stakeholder; two language versions if the audiences require them.

Tooling

A spreadsheet is enough for the plan: one row per communication, one column per item, one filter per audience or per sender. A shared calendar (Outlook, Google Calendar) carries the recurring meetings that the plan provides for. Scheduling software such as MS Project takes the dates into the project schedule.

A team chat (Microsoft Teams, Slack) carries the team check-ins and the short messages. An intranet or a wiki (SharePoint, Confluence) hosts the project page and the reports in pull mode. An encrypted exchange platform transmits confidential files to a supplier. It keeps a record of each upload and each download.

Sources

  • Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., PMI: the Plan Communications Management process, its categories of information and its link to the engagement plan (§2.5.2.3); the Manage Communications (§2.5.2.5) and Monitor Communications (§2.5.2.7) processes; tailoring to the culture of the organisation (§2.5.3); the definition and the items of the communications management plan (Section 4, Communications management plan); communication requirements analysis, the criteria for choosing a technology and communication styles assessment (Section 5, Communication requirements analysis, Communication technology, Communication styles assessment).
  • HERMES 2022, Project Management Reference Manual, Swiss Confederation, Federal Chancellery: task 5.4.3.43 Manage and inform stakeholders with the stakeholder list as the basis of communication planning, the coordination with the sponsor, the continuous updating of the plan and the integration of decision planning; the communication plan as a chapter of outcome 4.4.1.34 Project management plan; refining the communication plan during the detailed planning of each phase (7.4.5.3 Planning in traditional solution development).
  • Swiss Confederation, Federal Act on Data Protection (FADP), SR 235.1, art. 9: the processing of personal data by a processor.