Ladder of the routes for resolving a dispute, from least to most formal: negotiation, mediation, expert determination, arbitration, litigation. In negotiation and mediation the parties decide. From expert determination upward a third party decides for them. The dispute review board stands beside the ladder. It follows the project from its start.

Claims Administration and Dispute Resolution

Claims administration manages the requests that one party to a contract makes to the other for time, money or both. Alternative dispute resolution (ADR) covers the routes that resolve a disagreement over a claim. The PMBOK Guide counts among them negotiation, mediation, arbitration, the dispute review board, expert determination and litigation, which it treats as the last resort. The project manager keeps the evidence, notifies within the time limits and chooses the least costly route that resolves the disagreement.

Goal

A claim is a request by a party to a contract that holds the other party responsible for an event costing it time or money. It invokes a clause of the contract or the law. Claims administration establishes whether the request is well-founded, what it is worth and by which route to settle it when the other party contests it.

The PMBOK Guide covers the technique in its appendix on procurement (§X4.9). It notes that claims and disputes are frequent in every sector. For construction it puts the direct cost of a dispute at between 0.5% and 5% of the contract value. Schedule and cost overruns are among the main causes of disputes. They often follow change orders. The more complex a project is and the more stakeholders it brings together, the more likely a dispute becomes. The PMBOK Guide therefore expects the project manager to master claims administration and to know the alternative dispute resolution routes.

The technique produces a claims register, a file for each claim and a dispute resolution clause in the contract. The clause sets the order of the routes and their time limits.

Usage

When to use it

  • Drafting a contract: write the dispute resolution clause while the parties are still on good terms.
  • An event the contract assigns to the other party: late delivery by the client, wrong data, ground conditions that differ from the survey; open a file the same day.
  • Fixed price and unforeseeable circumstances: the law excludes a price increase unless a court grants one; document the extraordinary nature of the circumstances.
  • Change request refused or not priced: the disagreement concerns the entitlement or the amount; open a claim.
  • Project with many contractors: the interfaces between lots multiply the events attributable to a third party; open the register when the contract is signed.
  • Counterclaim received: assess the other party's request with the method applied to the organisation's own claims.
  • Foreign partner: provide for arbitration seated in Switzerland rather than the courts of either party.

When not to use it

  • Disagreement between departments of the same organisation: no contract grounds a claim; handle the conflict with the Thomas-Kilmann conflict modes and hierarchical escalation.
  • Change wanted by both parties: there is no dispute to resolve; go through change control.
  • Suspected fraud or offence: the route is criminal law; pass the file to the legal department.

Description

Change, claim, dispute

A change whose price the parties cannot agree on becomes a claim. A rejected claim becomes a dispute.
ConceptWhat defines itHandling
ChangeThe parties want to change the scope, the schedule or the price. They agree on an offer.Change control, contract amendment
ClaimOne party asks for time or money for an event it attributes to the other. The entitlement or the amount remains to be established.Notification, file, negotiation
DisputeThe other party rejects the claim or contests its amount.Escalation to a resolution route

A claim often starts as a change request that the client refuses or that the parties cannot price. The project manager then keeps two registers. The change log shows what the parties have accepted. The claims register shows what they still contest.

The same events recur from one project to the next: a late, incomplete or defective delivery by the client or a subcontractor, an imposed change in the working method, a scope description that each party reads to its own advantage, an assumption in the offer that reality contradicts.

The project manager's duties under the PMBOK Guide

The project manager knows the terms of the contract well enough to spot where a dispute can arise. They keep a detailed record of the project's activities, changes and communications, which later supplies the evidence for a claim. They communicate openly with the stakeholders to reduce misunderstandings. They identify a conflict early and deal with it before it escalates (§X4.9.1).

Negotiation is the first route a claim goes through. The PMBOK Guide therefore recommends that the project manager develop negotiation and conflict resolution skills. It also recommends learning about contract law and claims management from the start of the project, then working closely with the organisation's legal department.

§X4.9.2 adds precautions for possible litigation. Any written document can become evidence: an email sent in anger may one day be produced before an arbitrator. The project manager weighs the consequences for the relationship and decides in advance when and how a dispute moves to legal proceedings. They keep the details of the dispute confidential. They remain impartial and stick to the facts.

What Swiss law requires

The contract governs the claim first: the notification deadlines, the form, the route to follow. The general terms and conditions of the contract often set these deadlines in days. The project manager enters them in the register when the contract is signed.

For a contract for work and services, two articles of the Code of Obligations (CO) govern the contractor's claims. If, during the work, the material supplied by the customer (here the client) or the site the customer designated proves defective, the contractor informs the customer immediately. The contractor gives the same notice of any circumstance that jeopardises the proper or timely performance of the work. Without that notice the contractor bears the harmful consequences (CO, Art. 365 para. 3). A late notification can therefore extinguish the claim before any discussion of the merits.

When the price is fixed in advance, the contractor completes the work for that price even if the work costs more (CO, Art. 373 para. 1). The court may increase the price or terminate the contract only if extraordinary circumstances prevent performance or make it excessively difficult. These circumstances must have been unforeseeable or excluded by the assumptions that the parties made (para. 2). The fixed price covers the agreed work. A change that the customer orders falls outside it. Under a fixed price, a claim holds if the contractor proves an event attributable to the customer or circumstances of this kind. The choice among contract types (fixed price, time and materials, unit prices) therefore determines which claims the contractor can assert.

Handling a claim

The steps for handling a claim summarise common practice. They order the duties that the PMBOK Guide lists and add the requirements of Swiss law.

The steps order the duties that the PMBOK Guide lists in §X4.9.1 and add Swiss law. Their order follows common practice. The notification goes out before the full file. A failed negotiation moves the dispute up one tier. An agreement goes through change control before closure.
  1. Detect and notify. The project manager spots the event: a plan delivered late, client data that proves wrong, an instruction that changes the working method. They notify the other party in writing within the time limit of the contract. Where the contract sets none, they notify immediately. The notification names the event, the clause invoked and the expected effect on time and cost. The full costing can follow.
  2. Document. The file brings together the chronology, the contractual basis, the cause-and-effect link and the evidence: meeting minutes, emails, project or site diary, dated versions of the schedule. The project manager demonstrates the impact on time in the schedule. As long as an event stays within the activity's total float, it does not touch the critical path and justifies no extension. The project manager costs the event separately from the rest of the work.
  3. Assess internally. A small team reviews the file: the project manager, a lawyer, a finance representative and an expert if the cause is technical. It estimates the merit, the probable amount and the exposure to counterclaims. It sets the negotiating mandate: the target amount and the threshold below which the negotiator goes back to management.
  4. Negotiate. The project manager opens the discussion with their counterpart on the basis of the file. The principled negotiation of Fisher and Ury separates the people from the problem and looks for objective criteria: a unit price from the contract, an expert report, an industry rate schedule. The signed agreement sets the time and the amount granted. It extinguishes the claim for the event it names.
  5. Escalate. If negotiation fails within the agreed time, the dispute moves up one tier under the contract clause: to the senior management of both parties, then to a route that brings in a neutral third party. The clause and the internal protocol that §X4.9.2 calls for set the tiers, their time limits and the person who decides to move to the next one. A party that escalates at the first refusal damages the relationship for an amount that a second meeting would often have settled.
  6. Implement and close. The project manager carries the time and the amount granted into the schedule and the cost baseline through change control. They check that each party implements the agreement. If nobody carries the agreement over, the schedule keeps a wrong deadline. The project manager then closes the file in the register and draws lessons learned from it for the next contract.

Offensive or defensive stance

Before the first file, management chooses a stance for the contract. The offensive stance opens every claim early, asserts every right the contract grants and contests every counterclaim. It suits a tight fixed price where the client keeps issuing instructions. The defensive stance reserves claims for serious breaches, accepts well-founded counterclaims and relies on prevention. It suits a client that the company wants to keep. A project manager who claims everything one month and concedes everything the next loses credibility under either stance.

The claims register and the claims manager

The claims register lists every claim issued or received. For each one it gives the date of the event, the date of notification, the contractual basis, the amounts claimed and granted, the tier reached and the next deadline. The steering committee reviews it at every meeting.

On a large contract, a claims manager keeps the register and the files. They check the contractual basis of each request and record its effect on cost, time and quality. They review the status with the other party at least once a month. They negotiate within the limits of a written mandate from management.

The resolution routes

The ladder ranks the PMBOK Guide's resolution routes from least to most formal. The PMBOK Guide lists them in another order. Up to mediation the parties decide; beyond it a third party decides for them. The dispute review board follows the project from its start.
The resolution routes of §X4.9 of the PMBOK Guide with the framework that applies in Switzerland.
RoutePMBOK Guide definitionWho decidesFramework in Switzerland
NegotiationDirect discussion between the parties without a third partyThe partiesNo form required. The written agreement binds the parties like any contract.
MediationA neutral third party facilitates the discussion so that the parties find a solution acceptable to each of themThe partiesConfidential by agreement of the parties and under the Swiss Rules of Mediation. Before the courts, mediation replaces conciliation at the joint request of the parties (CPC, Art. 213). During proceedings the court may recommend it at any time. Mediation then suspends the proceedings (Art. 214). In both cases the parties' statements may not be used in court (Art. 216). The parties may have the agreement approved. The approved agreement has the effect of a legally binding decision (Art. 217). The Swiss Arbitration Centre administers mediations under the Swiss Rules of Mediation and helps the parties appoint a mediator. The Swiss Chamber of Commercial Mediation accredits mediators.
Expert determinationAn independent expert decides a specific technical or financial questionThe expertArbitrator's opinion: the expert arbitrator establishes disputed facts. The court is bound by these facts if the parties may freely dispose of the matter, if the expert could not be challenged and if the report is impartial and free of obvious error (CPC, Art. 189).
ArbitrationFormal procedure: an arbitrator or a panel hears the parties and renders a binding decisionThe arbitral tribunalDomestic arbitration: agreement in writing or in another form evidenced by text (CPC, Art. 358). Open to any claim that the parties may freely dispose of (Art. 354). Appeal to the Federal Supreme Court on limited grounds (Art. 389 and 393). If at least one party had no domicile, habitual residence or seat in Switzerland when the parties concluded the arbitration agreement, Chapter 12 of PILA applies (CPC, Art. 353; PILA, Art. 176): same form (Art. 178), limited grounds of appeal (Art. 190). Swiss Rules of the Swiss Arbitration Centre.
LitigationLast option when the other routes are exhausted: a court decidesThe state courtConciliation attempt first (CPC, Art. 197). Joint waiver possible from an amount in dispute of CHF 100'000 (Art. 199 para. 1). The plaintiff may waive it alone if the defendant has its domicile or seat abroad (Art. 199 para. 2).
Dispute review boardGroup of neutral experts appointed at the start of the project to prevent and resolve disputes throughout its durationThe board, with the scope that the contract gives itNo statutory rule: the contract creates the board and sets the scope of its opinions.

The PMBOK Guide counts litigation among the alternative routes. The term usually means the routes that avoid the courts: litigation is the route to which the others are the alternative. The list reads better as a ladder, from the least formal route to the most formal.

A dividing line crosses this ladder. In negotiation and mediation the parties decide. An agreement exists only if both sign it. From expert determination upward a third party decides for them: an arbitral award binds even the party that contests it. Cost and duration grow with formality. According to the Swiss Arbitration Centre, a mediation often succeeds within a few weeks and preserves the relationship between the parties.

The dispute review board stands outside the ladder. The parties appoint it at the start of the project. It follows the project over time and deals with a disagreement as soon as it arises. Its cost runs throughout the project, even if no dispute arises. It is justified on a large construction or infrastructure contract. The International Federation of Consulting Engineers (FIDIC) has its headquarters in Geneva. It publishes practice notes on these boards and keeps the list of experts that it approves for dispute boards (President's List of Approved Dispute Adjudicators).

Writing the dispute resolution clause

The parties draft the clause at signature, when they are still on good terms. A tiered clause sets the order of the routes and a time limit for each tier. Without a time limit, one party can block a tier indefinitely.

A tiered clause names for each tier a single route, a time limit and the institution that administers it. The mediation time limit comes from the Swiss Arbitration Centre's model clause "Mediation, followed by Arbitration".
TierRouteWho negotiates or decidesTime limitInstitution and seat
1NegotiationThe project managers10 working daysNone
2NegotiationSenior management20 working daysNone
3MediationThe parties with the mediator60 days from the confirmation or appointment of the mediatorSwiss Arbitration Centre under the Swiss Rules of Mediation
4ArbitrationThe arbitral tribunalNoneSwiss Arbitration Centre under the Swiss Rules; seat in Switzerland

The parties also choose at signature between arbitration and a state court. The parties appoint the arbitrators (CPC, Art. 361; PILA, Art. 179). The award allows only one appeal on limited grounds. Under the Swiss Rules, hearings are private unless the parties agree otherwise (Art. 27 para. 7). The parties keep the award and the documents confidential (Art. 44). A state court sits in public (CPC, Art. 54 para. 1) and starts with conciliation. With a foreign partner, arbitration spares each party from pleading before the other's courts. The Swiss Rules apply to domestic and international disputes alike.

A badly drafted clause creates its own dispute. "Mediation or arbitration at the parties' choice" leaves the parties disagreeing over the route itself. Each tier of the clause names a single route, the institution that administers it and the seat. The clause also sets the language of the proceedings and the number of arbitrators.

AI considerations

The PMBOK Guide notes that AI tools analyse the clauses of a contract, identify areas of dispute and estimate the probability of a claim (§X4.9.1). A language model extracts the notification deadlines, the required forms and the dispute resolution clause from a contract and its general terms and conditions. The project manager fills the register with them at signature. The model reconstructs a chronology from meeting minutes and emails. It writes a first draft of a notification that names the event, the clause and the expected effect.

Judgement stays human. The cause-and-effect link, the reading of an ambiguous clause and the stance belong to the project manager and the lawyer. A claim prediction needs a history of contracts and claims that few organisations keep. The documents of a dispute are confidential. The mediation agreement makes those of a mediation confidential. Before the courts the law does so too (CPC, Art. 216). A query to a hosted service takes them outside the organisation. A notification drafted with a model becomes evidence once it is sent: the project manager rereads it as a document that an arbitrator will read.

Examples

An IT company in the canton of Vaud develops a portal for a cantonal office at a fixed price. The contract sets a notification deadline of 10 working days and a tiered clause. The claims register shows for each request where it stands and what it has earned or cost.

Claims register of the portal. R: claim issued by the company. C: counterclaim received from the office. Amounts in CHF excluding VAT.
No.EventOccurredNotifiedContractual basisClaimedGrantedTierStatusNext deadline
R-01Interface to the cantonal register delivered by the office 20 working days late3 March4 MarchAnnex 2 (client's services)20 working days, 38'00015 working days, 24'000NegotiationAgreement on 2 April; amendment 4None
R-02Volume of data to migrate three times larger than the sample supplied with the call for tenders12 May15 MayArt. 6.3 (assumptions of the offer)62'000PendingMediationRejected by the office on 10 June; senior management on both sides reached no agreementMediation on 9 September
R-03Change of hosting server required by the office's IT security2 June18 JulyArt. 9.1 (environment provided)6 days, 11'0000NoneNotified late; abandonedNone
C-01Delay penalty: 25 working days at 1'500 per day30 June1 JulyArt. 12 (penalties)37'50010 working days, 15'000NegotiationPartial agreement: R-01 covers 15 working daysNone

The project manager reads the "Notified" column before the amounts. R-03 may have been well-founded. Notified more than six weeks after the event, it fails before any discussion of the merits. C-01 shows the register at work on a request received: the agreement on R-01 fixes the share of the delay that the office can no longer penalise.

Visualisations

The ladder ranks the resolution routes from least to most formal. It marks the tier at which a third party decides in place of the parties. The diagram for handling a claim follows the file from detection to closure. In it the dispute moves up one tier with each failed negotiation. The register in the example is the tracking deliverable.

Cost

PhaseLevelJustification
PreparationMediumRead the contract, enter the notification deadlines in the register, write the tiered clause with the lawyer.
ExecutionMediumOne file and negotiation meetings per claim. Each tier crossed adds third-party fees and weeks.
DocumentationHighRecord of activities, changes and communications for the whole duration of the contract.

Tooling

A spreadsheet or a list in the project management tool is enough for the register. The project's electronic document management system keeps the file and the dated versions of the schedule. Scheduling software such as MS Project or Primavera P6 compares the baseline schedule with the actual schedule. It demonstrates the effect of an event on the critical path.

The Swiss Arbitration Centre publishes model arbitration and mediation clauses. The lawyer starts from this wording to write the tiered clause.

Sources

  • Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., PMI: the frequency of claims, the direct cost of disputes in construction and the six resolution routes with their definitions (§X4.9); the project manager's duties and the contribution of AI tools (§X4.9.1); care in written communication, the escalation protocol, confidentiality and impartiality (§X4.9.2).
  • Swiss Confederation, Civil Procedure Code (CPC), SR 272: public hearings (Art. 54), the arbitrator's opinion (Art. 189), the conciliation attempt and the joint waiver (Art. 197 and 199), mediation (Art. 213, 214, 216 and 217), domestic arbitration (Art. 353, 354, 358, 361, 389 and 393).
  • Swiss Confederation, Code of Obligations (CO), SR 220: the notice owed by the contractor (Art. 365 para. 3) and the fixed price (Art. 373).
  • Swiss Confederation, Federal Act on Private International Law (PILA), SR 291: the scope of international arbitration (Art. 176), the form of the arbitration agreement (Art. 178), the constitution of the arbitral tribunal (Art. 179) and the grounds of appeal (Art. 190).
  • Swiss Arbitration Centre, Swiss Rules of International Arbitration (Swiss Rules), 2021: private hearings (Art. 27 para. 7) and the confidentiality of the award and the documents (Art. 44).
  • Swiss Arbitration Centre, Mediation: the administration of mediations under the Swiss Rules of Mediation, help in appointing a mediator, the accreditation of mediators by the Swiss Chamber of Commercial Mediation, the duration and the effect on the relationship.
  • Swiss Arbitration Centre, model arbitration and mediation clauses: the clause "Mediation, followed by Arbitration" and its 60-day time limit, the language of the proceedings and the number of arbitrators.
  • FIDIC, Practice Notes and Adjudicators: the practice notes on dispute boards and the list of approved experts for these boards (President's List of Approved Dispute Adjudicators).