Change Control and Change Control Board
Change control is the process by which a project identifies and documents every change to a document, a deliverable or a baseline, then approves, defers or rejects it. The change control board (CCB) is the formally chartered group that reviews and evaluates the requests and decides on them. It then records and communicates its decisions. The PMBOK Guide describes change control in the process Assess and Implement Changes. HERMES describes it in the task Manage changes.
Goal
Change control is the formal process that every change request follows once the baseline is approved. The baseline is the approved version of the scope, the schedule or the costs against which the project measures its progress.
Without it, the baseline changes by email and in meetings. The work changes before anyone decides. Nobody knows which version is authoritative. With it, every change has an author, an estimated cost, a decision and a date.
The decision maker settles each request knowing its impact. According to the PMBOK Guide, the process produces the processed change requests, the project management plan updates and the updated change log.
In step 3 the team uses impact analysis to estimate the effects of a request. Item tracking takes a concern that is not a change request through to closure.
Usage
When to use it
- Approved baseline: from now on every change to the scope, the schedule or the costs goes through the process.
- Deliverables under configuration management: the configuration management plan names the artefacts whose change requires a formal request.
- Project under contract: the contract requirements set how formal the request and the decision must be.
- Request made orally in a meeting: write it down and log it before it changes the work.
- HERMES project with the traditional approach: the change request is the basis for every change in content.
- Agile HERMES project where a change affects the objectives, the budget or the time frame of the overall project: the method then requires a traditional change request.
When not to use it
- HERMES project in the initiation phase: the project sponsor decides on changes to the project initiation order.
- Content change in an adaptive project: the proposal enters the backlog, where backlog management prioritises it.
Description
The trigger: the baseline
According to the PMBOK Guide, formal change control in a predictive approach starts only once the baselines exist. From then on, every change goes through the formal process. The configuration management plan names the artefacts placed under configuration control. Any change to one of them requires a formal change request.
Any stakeholder can propose a change at any point in the life cycle. In the PMBOK Guide, the degree of formality depends on the project's scope, its complexity, the contract requirements and the development approach. A three-month internal project and a multi-year public contract do not fill in the same form.
HERMES provides no formal change management in the initiation phase because the requirements and the solution objectives are not yet defined. In that phase the project sponsor decides on changes to the project initiation order.
From the request to the recorded decision
- Write the request. A change can start as a sentence in a meeting. The requester or the project manager puts it in writing and enters it in the change or configuration management system. The request can come from inside or outside the project. It can target the project's policies or procedures, the project or product scope, the costs or the budget, the schedule or the quality of the results. The PMBOK Guide distinguishes corrective action, preventive action, defect repair and update. Corrective and preventive actions remove or reduce a negative impact later in the project. An update reflects changed or added ideas or content.
- Log it. The change log lists all the requests submitted during the project with the status of each. The request receives a number there before any analysis.
- Analyse the impact. The team estimates the effect of the request on scope, schedule, finances, resources, risks and stakeholders. According to the PMBOK Guide, a request typically carries an estimate of its schedule and cost impacts before it is approved. To inform the decision, the team can produce an alternatives analysis and a cost-benefit analysis.
- Decide. A person designated by the project management plan or by the organisation's procedures decides on each documented request. The PMBOK Guide names the sponsor and the project manager. Where the project provides for one, a change control board or a project board takes part. The decision approves, defers or rejects the request. The PMBOK Guide's example flow adds the outcome "more information", which sends the request back to analysis. To decide, the decision maker can use voting, autocratic decision making and multicriteria decision analysis. While the decision maker deliberates, the project manager carries on with the planned tasks. In parallel the project manager analyses the risks of accepting the request and the risks of refusing it.
- Update the plan. An approved request can require new cost estimates, an adjusted schedule, other resources and a new risk assessment. The project manager updates the project management plan and the affected documents. Depending on the nature of the change, the customer or the sponsor may have to approve it after the board. The team then implements the change.
- Communicate and record. When the decision maker defers or rejects a request, they communicate the decision to the person or group that submitted it. The change log records the decision on every request, whatever the decision is. Once the change is implemented, the project manager checks that it produces the expected result.
The change control board
The change management plan establishes the board. The PMBOK Guide equates it with the steering committee. This plan sets the extent of the board's authority and describes its roles and responsibilities. It also states how the change control system works. If the plan seats the customer or the sponsor on the board, no second approval follows the board's. Change control tools support the board in its duties.
The change request in HERMES
In the Project management module, HERMES assigns the task Manage changes to the project manager. The project manager makes sure that the process is followed and documented. The user representative, the business analyst and project support contribute to the change request. Under the traditional approach, the project manager enters each request in the change status list, has it analysed and submits it to the decision maker. The decision maker approves or rejects it. The project manager then plans the approved changes, has them implemented and reviews them. Where needed, the project manager adapts the project management plan.
The change request describes the change, the procedure for making it and the proposed solution. HERMES treats it as a requirement: it specifies the change to be made in detail.
| Group | Fields |
|---|---|
| Identification | Change request number, requester, date of request |
| Justification | Reason for change |
| Solution | Proposed solution |
| Impact assessment | Effort, costs, deadline, risks |
The change status list records all the changes dealt with and shows the status of each. Under the traditional approach, each row also names the decision maker and the person responsible for the change. Under the agile approach, the list documents only the most significant changes.
Predictive approach, adaptive approach and HERMES
In an adaptive approach, the PMBOK Guide replaces the formal request with backlog management. A stakeholder's proposal becomes a product backlog item. The team analyses its impact to give it a priority. No formal approval takes place: a low priority defers the change. The person responsible for the backlog rejects the change by leaving the item out or removing it. This role most often falls to the product owner.
| Predictive (PMBOK) | Adaptive (PMBOK) | Traditional (HERMES) | Agile (HERMES) | |
|---|---|---|---|---|
| Trigger | Approved baseline | A stakeholder's proposal | Any change in content outside the initiation phase | A change that affects the objectives, the budget or the time frame of the project |
| Form | Written change request | Product backlog item | Change request | Traditional change request |
| Analysis | Typically the impact on schedule and costs | Impact analysed to set the priority | Impact assessment: effort, costs, deadline, risks | As in traditional |
| Decision | Approved, deferred or rejected by the designated person or the board | Deferred by a low priority. Rejected when the person responsible for the backlog leaves the item out or removes it | Approved or rejected | As in traditional |
| Record | Change log | Product backlog | Change status list | Change status list of the most significant changes |
Pitfalls
Oral request carried out. A developer adds a field requested in a meeting. The log has no trace of it. The cost shows up in the final account with no request number and no decision to cover it.
Decision without figures. The board approves a request whose effect on the schedule nobody has estimated. Two weeks later it finds that the request pushes back the go-live. In the log, its row carries a decision and no estimated impact.
Silent refusal. The board rejects or defers a request and does not tell the requester. The requester submits it again or goes around the board. The log then receives a second request on the same subject.
Project waiting on the board's decision. The team stops the work affected by a request that awaits a decision. In the log, the request stays "pending" from one meeting to the next.
Board approval taken as final. The team starts the work as soon as the board approves and before the sponsor signs. The project manager first checks whether a customer or sponsor approval is still due.
Disproportionate formality. A four-page form to correct a label pushes the team to bypass the process. Minor corrections stop appearing in the log.
AI considerations
A language model drafts a structured request from meeting minutes or an email. It extracts the reason, the proposed solution and the requester, then fills in the fields of the organisation's template. It flags the fields left empty and checks that the request puts figures on its costs and deadlines. Before a board meeting it summarises the change log: pending requests, deferred requests whose date is near, requests that affect the same deliverable. It drafts the notices to requesters from the recorded decision.
Only the people who know the work estimate the impact. A model produces a plausible figure with no basis. The board then risks deciding on that figure. The decision belongs to the person or the board that the plan designates. Requests often contain contract amounts and supplier names. They therefore go only to an AI tool that the organisation has authorised.
Examples
At one meeting, the board decides on four requests about replacing a cantonal office's permit management software. Each decision goes into the log. The board notifies the requester of the deferred request and the requester of the rejected one.
| No. | Requester | Subject | Estimated impact | Decision | Next step |
|---|---|---|---|---|---|
| CR-07 | Legal department | Add the "legal basis" field to the permit form | 6 days, CHF 7'200, no delay | Approved | Plan and cost baseline updated. Passed to the delivery team |
| CR-08 | Head of operations | Migrate the 2005 to 2014 files in addition to the last ten years | 25 days, CHF 30'000, go-live 4 weeks later | Deferred to release 2 | Requester notified of the review date |
| CR-09 | Supplier | Replace the signature module with the supplier's own product | 12 days, CHF 14'400, no delay | Rejected: the current module meets the requirement | Requester notified of the reason |
| CR-10 | Front desk | Interface with the cantonal register of residents | Not estimated | More information: back to analysis | Reviewed at the next meeting |
Only one of the four requests changes the plan. The head of operations knows when the request will come back. The supplier knows why the board rejected its request.
Visualisations
One figure follows the request from submission to the recorded decision. It shows the four outcomes and the documents that pass from one step to the next. The content of the HERMES request, the comparison of the approaches and the completed log are tables.
Cost
| Phase | Level | Justification |
|---|---|---|
| Preparation | Medium | The change management plan names the decision maker, establishes the board if one is needed and sets its authority. The project manager writes it with the sponsor when the baseline is approved. |
| Execution | Medium | Each request costs an impact analysis and a presentation to the decision maker. The analysis takes from a few hours to several days depending on the size of the request. The board meets at the frequency that the plan sets. |
| Documentation | Low | A request of one to two pages and one log row per change. The project manager updates the plan and the affected documents after each approval. |
Tooling
The PMBOK Guide allows manual or automated change control tools. They record the requests and track their assessment and approval. They then distribute the decisions to the stakeholders.
A spreadsheet is enough for the log of a medium-sized project. It holds one row per request and one column per status. A filter prepares the list for the board meeting. HERMES publishes its templates for the change request and the change status list on the page of each outcome.
A ticketing tool (Jira, ServiceNow, Redmine) fits when the requests run into dozens. Its workflow reproduces the states of the process. The tool notifies the requester when the decision maker defers or rejects the request. A versioned document space (SharePoint, Confluence) keeps each version of the plan and of the baselines with the request that changed it.
Sources
- A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition, Project Management Institute: §2.1.6.8 Assess and Implement Changes for the process, its inputs, tools and outputs (figure 2-10), the example flow (figure 2-11), the predictive approach (§2.1.6.8.1) and the adaptive approach (§2.1.6.8.2); Section 4 Inputs and Outputs, entries "Approved change requests", "Change log", "Change management plan" and "Change requests"; Section 5 Tools and Techniques, entries "Backlog management" and "Change control tools"; Glossary, entries "change control" and "change control board (CCB)".
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project management: task Manage changes for the purpose, the activities and the absence of formal change management in the initiation phase; outcome Change request for its content and the agile threshold; outcome Change status list for its content under the traditional and the agile approach.