Activity model of a municipal library's lending service. The root definition sits above the diagram. The planning activities lead to the enabling activities: acquire and catalogue the documents, recruit and train the staff and run the digital lending platform. The opening hours and the enabling activities lead to lending books and media to residents. Lending leads to taking back the returned documents. A frame surrounds these eight operations and holds the monitoring and control activities: define the criteria, monitor the operations and take control action. A control arrow returns to the operations.

Business Activity Modelling

Business activity modelling establishes what a system must do to achieve a declared purpose. The model lists activities named by a verb. It links them by their logical dependencies and adds activities that monitor and correct the operations. The technique comes from Peter Checkland's Soft Systems Methodology. Each model starts from one root definition. That sentence states the transformation the system performs under a declared worldview. The analyst builds one model per selected viewpoint and uses it to question the real situation: does this activity exist, who carries it out, how is it judged? The answers feed the debate on change and the gap analysis.

Goal

Business activity modelling lists the activities a system must carry out to achieve the transformation its root definition states. It gives a group that disagrees about the system's purpose a shared object to discuss before anyone describes a process. Soft Systems Methodology (SSM) calls this deliverable a purposeful activity model or a conceptual model. The BCS Business Analysis Practice syllabus calls it a business activity model (BAM).

Each model expresses the one worldview that its root definition declares. Checkland and Poulter conclude that an activity model never describes the real world. It supplies questions to ask about the real situation. The answers structure the debate on what to change. The participants look for changes that are arguably desirable given the models. These changes must also be culturally feasible for the people concerned.

In business analysis the BCS syllabus pairs the activity model with the target operating model (TOM) and with gap analysis to build a view of the target state. The deliverable is one model per selected worldview. Each model carries its root definition and its performance criteria.

Usage

When to use

  • Contested purpose: build one model per worldview and debate their differences.
  • Root definition in place: turn the statement from CATWOE analysis into activities and dependencies.
  • Defining the target state: build a view of the target state before analysing the gaps.
  • A question that crosses departments: model resource allocation or any activity that the organisation chart splits.
  • No performance monitoring: the questions on criteria show what nobody measures.
  • Before process modelling: establish what must be done before describing how to do it.
  • Poorly documented processes: the model starts from the root definition and needs no description of the current state.

When not to use

Description

The inputs to the model

The PQR formula gives the root definition its shape: do P by Q in order to help achieve R. P answers "what", Q answers "how" and R answers "why". Q carries the transformation process that the model details. The modeller must be able to defend Q as a plausible means of achieving P.

The root definition describes the activity as a transformation in which an entity passes from one state to another. In Checkland and Poulter's example an unpainted fence becomes a painted fence. CATWOE analysis checks that the definition names its beneficiaries or victims, its actors, its worldview, its owner and its constraints. Before drawing anything the analyst sets the performance criteria.

Checkland and Poulter distinguish two kinds of root definition. A primary task definition follows an existing structure: production, marketing or another department. An issue-based definition draws a boundary that cuts across the organisation chart. The allocation of the resources that every department competes for is the typical case. According to the authors, models that mirror the departments limit the team's thinking without the team noticing. Their rule: never work exclusively with either kind.

The elements of the model

An activity is written as a verb followed by its object: "Acquire media", "Lend documents". It says what must be done. How to do it belongs to other models. BCS sums up this rule as "What, not how". Each activity carries a number that the questions and the detailed models cite.

An arrow links two activities when one depends on the other. Checkland and Poulter give the textbook example: nobody can use a raw material before obtaining it. So the arrow runs from "obtain" to "use". It reads "is needed for". A process model also draws who passes what to whom and in what order.

The activities that carry out the transformation form the operations. Checkland and Poulter add a monitoring and control subsystem. One activity defines the performance criteria. A second monitors the operations against these criteria. A third takes control action when monitoring detects a deviation.

The performance criteria

Checkland and Poulter require every model to name its criteria for the "three Es".

  • Efficacy: does the transformation produce the intended outcome?
  • Efficiency: does it achieve that outcome with a minimum of resources?
  • Effectiveness: does it help achieve a higher-level or longer-term aim?

Their example shows that the three are independent. A drug that relieves a headache is efficacious. It is inefficient if it costs too much or acts too slowly. It is ineffective if the headache signalled a more serious complaint. Depending on the situation the analyst adds other criteria such as the elegance or the ethics of the transformation.

The categories of activity

We define the categories into which the BCS syllabus sorts the activities of a BAM.

  • Planning: set what the other activities aim at, for example a policy, a volume or a service level.
  • Enabling: obtain, maintain and renew what the doing activities consume: staff, equipment, information, premises.
  • Doing: carry out the transformation itself. This category holds few activities and often only one.
  • Monitoring: measure the other activities against the performance criteria.
  • Controlling: decide on and launch control action when monitoring detects a deviation.

We place planning, enabling and doing in Checkland and Poulter's operations. Monitoring and controlling join the definition of the criteria in their monitoring and control subsystem. Planning sets what the operations aim at: a policy or a volume. Defining the criteria sets how the team judges the transformation: efficacy, efficiency and effectiveness. Checkland and Poulter aim for "the magical number 7 ± 2" activities in the operational part of the model. They accept breaking that rule when necessary.

Monitoring and control
Operations7 ± 2 activities
Planning
Enabling
Doing
Define the criteria (efficacy, efficiency, effectiveness)
Monitor
Take control action
Planning, enabling and doing make up the operations. The monitoring and control subsystem surrounds them.

Building the model

Checkland and Poulter give a sequence that a modeller follows or consults when stuck. We insert a step that sorts the activities into the BCS categories.

  1. Assemble the inputs
    The PQR formula, the root definition, the CATWOE grid and the performance criteria fit on one page.
  2. Write the activities in three groups
    Those that concern the entity to be transformed, those that carry out the transformation and those that deal with the transformed entity. For the fence: prepare the fence, paint it and judge whether it improves the property.
  3. Sort each activity into its category
    Planning, enabling or doing. An empty category signals a missing activity: lending without an activity that supplies the documents does not hold up.
  4. Link the activities by dependency arrows
    "Paint the fence" depends on "Obtain the brush", "Obtain the paint" and "Prepare the fence".
  5. Add monitoring and control
    Define the criteria, monitor the operations and take control action. These activities take the same form in every model.
  6. Check the model against its inputs
    Does every element of the root definition lead to something in the model? Can every activity be linked back to the root definition or to the CATWOE grid? Two yeses make the model defensible.

Checkland and Poulter write "defensible" rather than "correct". Two competent practitioners derive slightly different models from the same root definition because each reads its words differently. When two models drawn from the same root definition differ, the team compares how each author reads the words of the definition.

The modeller expands an activity that is too broad in a lower-level model. That activity becomes the source of a root definition and a model of its own. The activities of the new model take its number: activity 6 expands into 6.1, 6.2, 6.3. Across more than a hundred studies the authors never needed to go more than two levels below the parent model.

The most frequent error, according to Checkland and Poulter, is to lose sight of the root definition and model a real-world version of the activity. Their example comes from a medium-sized manufacturing company. Its distribution manager kept slipping into the working methods of his own department. The model that results reproduces the situation. A team that compares this model with the situation compares the situation with itself. No question arises. An activity that names a software product, a form or a department signals this drift.

Questioning the real situation

Checkland and Poulter warn against the word "comparison". It turns dangerous once the discussion lists the shortcomings of the situation against "perfect" models. A model rests on a pure worldview. It does not claim to describe what the organisation should be. The questions address the activities, the dependencies and the performance criteria.

The informal approach suits a setting whose culture rules out a detailed presentation of the method. The facilitator puts the models up on flip charts on the wall and refers to them during the discussion about improving the situation. According to the authors the formal approach is probably the most common. The team fills in a matrix with the activities and dependencies of the model as rows and the questions as columns. In the scenario approach the analyst writes an account of an action carried out according to the model and sets it against an account of a real action of the same kind. A chemical company ran every plant start-up as if it were the first. The authors set the story drawn from a generic plant start-up model against the stories of past start-ups.

The matrix must not turn into mechanical drudgery. Checkland and Poulter recommend glancing quickly over many activities and questions. The team dwells on those that catch attention or stir emotion. Groups usually struggle with the criteria question: what would show that this activity is efficacious, efficient and effective? That difficulty draws attention to monitoring, which organisations often neglect.

Consensus or accommodation?

BCS starts from one BAM per stakeholder perspective. The analyst then derives a consensus BAM from them: a single model that all stakeholders find agreeable. It shows what the business activity should look like. The syllabus treats it as part of stakeholder buy-in and engagement.

Checkland and Poulter aim for an accommodation: a version of the situation that people with different worldviews can live with. For them consensus is a special and rare case of accommodation. A team can use the consensus BAM as a view of the target state as long as it treats that BAM as one model among others. The consensus BAM then expresses the worldview the group agrees to share. The team uses it to question the situation.

The activity model and its neighbours

TechniqueQuestion askedStarting point
Business activity modellingWhat must a system do to achieve a declared purpose?A root definition and the worldview it declares
Functional decompositionWhat parts make up this scope?A scope or a function to break down
Business capability analysisWhat can the organisation do and at what level?The organisation as it stands and its strategy
Process modellingWho does what, in what order, with which exchanges?Actual or planned work
Each technique starts from a different object. The activity model starts from a declared worldview.

AI considerations

A language model helps to get from the root definition to a first draft. From the PQR sentence and the CATWOE grid it proposes activities in verb-and-object form. It sorts them into the categories and suggests dependencies. It can also review the model. It flags an activity that names a tool or a department and so describes a way of doing things. It spots the element of the root definition that nothing in the model picks up. It drafts rival root definitions for the same situation, which the analyst checks with the people concerned.

The language model draws its proposals from typical cases. It therefore drifts towards the most frequent error: modelling a real-world version of the activity. For each proposed activity the analyst checks which word of the root definition it traces back to. The dependencies need the same care, since the tool infers them from the usual order of tasks. Questioning the situation remains human work. It deals with what people do, believe and feel. Root definitions and workshop notes name people and departments. An analyst who submits them to an external tool transfers personal data. For a company that transfer falls under the Federal Act on Data Protection (FADP). For a cantonal or municipal administration it falls under the cantonal data protection act.

Examples

A municipal library reviews its lending service.

Root definition: a municipal system that the library team runs to lend books and media to residents (P) at the counter and online (Q) in order to widen access to reading in the municipality (R). The municipality's worldview: lending is a public service that gives access to reading.

A municipal system that the library team runs to lend books and media to residents (P) at the counter and online (Q) in order to widen access to reading in the municipality (R).
Monitoring and control
Operations7 ± 2 activities
1PlanningSet the collection policy→ 3, 6
2PlanningSet opening hours and staffing→ 5, 7
3EnablingAcquire books and media→ 4
4EnablingCatalogue the documents→ 7
5EnablingRecruit and train staff→ 7
6EnablingRun the digital lending platform→ 7
7DoingLend books and media to residents→ 8
8EnablingTake back and reshelve returned documents
1 to 8 → 10
9Define the criteriaEfficacy: documents lent per resident per yearEfficiency: cost per loan in CHFEffectiveness: share of residents who borrowed in the year→ 10
10Monitor operations 1 to 8→ 11
11Take control action→ 1 to 8
The activity model that the municipality derives from its root definition. Each arrow links an activity to the one that depends on it.

The effectiveness criterion measures R. A rising number of loans may come from the same readers, while the root definition aims at wider access.

The workshop then uses the model to question the real library. Extract from the matrix:

Model elementDoes it exist?Who, how?How is it judged?Question for the debate
1 Set the collection policyPartlyThe head librarian chooses purchases as titles come out. No document sets the policy.Acquisition budget spentWho sets the policy: the library or the municipality?
6 Run the digital lending platformYesAn external provider under contract with the municipal IT departmentThe provider tracks the availability of the platform.Can the library correct an activity it does not run?
Dependency 4 → 7: lending presupposes cataloguingNoNew titles go out on loan before they are catalogued.No criterionShould the library lend new titles before cataloguing them?
10 Monitor the operations (effectiveness criterion)NoThe annual report counts loans. It does not count borrowers.Loans per yearDoes lending widen access or serve the same readers more often?
The matrix puts the activities and dependencies of the model in rows and the questions in columns. The last row shows monitoring that nobody organised.

Visualisations

The structure diagram places planning, enabling and doing within the operations. The monitoring and control subsystem surrounds them. The library model applies this structure to one root definition: its numbered activities, its dependency arrows and its criteria.

The team fills in the matrix in a workshop and keeps it as a record of the questions asked. The "Question for the debate" column becomes the agenda of the debate on change.

Cost

PhaseLevelJustification
PreparationMediumWrite one root definition per selected worldview with its CATWOE grid and its criteria. Get each one accepted before any drawing starts.
ExecutionMediumEach model takes one session to build. Questioning the situation takes one workshop with the stakeholders per selected model.
DocumentationLowOne page per model: root definition, numbered activities, dependencies, criteria. The completed matrix keeps a record of the questions.

Tooling

A flip chart or a whiteboard is enough. The team writes the activities on sticky notes and draws the arrows in marker. It moves the notes while the dependencies are still changing. The flip chart then goes up on the wall to question the situation in the informal approach.

For remote work a collaborative whiteboard (Miro, Mural, FigJam) carries the same layout and keeps the model editable between sessions. A diagramming tool (draw.io, Visio, Lucidchart) suits the version for circulation. The questioning matrix fits in a spreadsheet: one row per activity or dependency, one column per question.

Sources