Two charts of the same release over nine sprints. On the left, the burnup: the scope line rises from 40 to 48 points at the start of sprint 5. The line of completed work climbs from 0 to 36 points by sprint 6. Two dotted forecast lines start from that point. The average slope of 6 points reaches the scope line at the end of sprint 8. The low slope of 5 points reaches it during sprint 9. On the right, the burndown of the same data: the remaining work falls from 40 to 16 points, rises to 17 in sprint 5 and then falls to 12 in sprint 6. The ideal diagonal reaches zero at sprint 7. The two dotted forecasts reach zero at the end of sprint 8 and during sprint 9.

Burndown and velocity

The burndown and the burnup are progress charts for work delivered in iterations. The burndown plots the work remaining against time. The burnup plots the work done under the line of total scope. Velocity is the amount of work a team finishes in one iteration. The team counts it in story points or as an item count. On the chart, velocity is the slope of the line of completed work. At Sprint Planning and in the Product Owner's projections, velocity is the basis of the forecast. It does not measure the team's performance.

Goal

A burndown is a chart that plots the work remaining on the vertical axis and time on the horizontal axis. Both charts answer the question that any schedule control asks: at this rate, when will the committed work be done? The PMBOK Guide places them in Monitor and Control Schedule. This process compares the work delivered and accepted with the work planned for the time elapsed. The burndown comes from the Scrum community and not from the Scrum Guide: the Agile Alliance glossary traces its first description to Ken Schwaber in 2000.

Velocity is the rate that feeds this forecast. It adds up the estimates of the items finished in an iteration. The work remaining divided by the average velocity of the last iterations gives the number of iterations still needed. At Sprint Planning, this figure helps the team decide how much work it takes on. For the release, it helps the Product Owner announce a date. The deliverable is the chart updated at the end of every iteration and the forecast drawn from it.

Usage

When to use it

  • Work delivered in fixed-length iterations: the end of each iteration yields a measurement comparable with the previous one.
  • Sprint Planning: the team selects work on the basis of the velocity of the last sprints.
  • A release date to announce: velocity forecasts the number of iterations remaining.
  • Scope that changes during the release: the burnup plots the addition and the completed work on two lines.
  • Day-by-day tracking of a sprint: the iteration burndown compares the remaining work with the ideal diagonal.
  • HERMES project with agile development: HERMES includes the burndown chart in the project status report.

When not to use it

  • Continuous flow without iterations: throughput and work in progress are tracked on a cumulative flow diagram.
  • Evaluating or comparing teams: velocity distorts as soon as it is used to judge teams. Measure the delivered result with metrics and KPIs.
  • Control against a cost baseline: the chart ignores the francs spent. Use earned value management.

Description

The elements of the chart

The unit of work is the unit of the backlog estimates. Teams use an item count or story points set by relative estimation. The team keeps the unit constant over the whole release. A unit that changes makes the measurements incomparable.

The interval is the iteration. Scrum calls it a sprint. On an iteration burndown, the interval becomes the day.

Completed work counts only the items that meet the Definition of Done. An item three-quarters finished counts as zero. This rule stops partial work from inflating the sprint's measurement and pushing the problem onto the next sprint.

On the burndown, the ideal line joins the work committed at the start to zero at the end date. On an iteration burndown, this start is the work committed at Sprint Planning. The actual line plots the remaining work observed. A trend line extends the actual line and forecasts the completion date.

On the burnup, the scope line plots the total work at the top of the chart. The line of completed work starts at zero and climbs towards it. The forecast is the point where the two lines meet.

Sprint burndown
Remaining work on day 6 against 30 committed points
Sprint burndown: Remaining work on day 6 against 30 committed points051015202530012345678910DayPoints remainingTodayExpected gap: about 8 pointsActualIdealTrend Sprint burndown: Remaining work on day 6 against 30 committed points051015202530012345678910DayPoints remainingTodayActualIdealTrend
Expected gap: about 8 points
The trend line extends the remaining work observed. On day 10, it leaves about 8 points unfinished. The team knows this gap four days before the end of the sprint.

Burndown or burnup

BurndownBurnup
Vertical axisWork remainingWork done and total scope
LinesActual, ideal, trendDone, scope, forecast
Scope additionAbsorbed into the actual line, which rises as if the team were going backwardsVisible: the scope line steps up
Period trackedOne sprint followed day by dayOne release followed sprint by sprint

The burndown has only one line of work. Its remaining work mixes two flows: the work the team finishes and the work the Product Owner adds. The Agile Alliance glossary notes that the burndown shows no change of scope. The burnup separates the two flows onto two lines. Over a release of several sprints, scope almost always changes: the burnup is the right chart there. Neither chart says which items were finished: the backlog carries that information.

Building the chart

  1. Set the unit. Choose story points or an item count, then keep that unit for the whole release.
  2. Set the interval. A release burnup is measured per sprint. An iteration burndown is measured per day.
  3. Count at the end of each interval. Only the items that meet the Definition of Done enter the total.
  4. Plot the points. On a burndown, the remaining work with the ideal diagonal. On a burnup, the cumulative completed work with the scope line. Record each addition or removal of scope on that line at the date the Product Owner decides it.
  5. Read the slope. The chart shows velocity: the increase in completed work from one iteration to the next.
  6. Forecast. The work remaining divided by the average velocity of the last three iterations gives the number of iterations remaining. Martin Fowler uses this average of the last three periods. Round the result up to the next whole iteration. The lowest and the highest of the three give a range.
  7. Use the slope and the forecast. At Sprint Planning as the basis of the sprint forecast. In the Product Owner's release projection. In the status report for the stakeholders.
  8. React to a drift. Look for the cause of a flattening slope and adapt the plan. Never set a target for the number.

An average alone implies more precision than three measurements support. A team that delivered 5, 7 and 6 points announces 6 points per sprint within a range of 5 to 7. When the commitment is firm, the Product Owner communicates the date that the low slope gives.

A new team has no slope yet. Its first three sprints give the first range. A date announced before then remains a guess.

Velocity is the basis of the forecast

The Sprint Planning section of the Scrum Guide states that the Developers forecast with more confidence when they know their past performance, their upcoming capacity and their Definition of Done. Velocity puts a number on that past performance.

At Sprint Planning, velocity bounds the selection: a team that finishes 6 points per sprint does not take on 12. For the release, the Product Owner derives a date from it. In Martin Fowler's example, a team delivers an average of 26 points per two-week iteration. A release of 330 points takes it about 13 iterations.

Upcoming capacity adjusts the forecast. When a planned absence removes a fifth of the team's days, the team takes on about a fifth less than its average.

Both uses require a reliable measurement. The Product Owner commits to a date with the stakeholders on the strength of the slope. If the slope is wrong, the date is wrong too.

Velocity does not measure performance

Velocity is a dangerous indicator. It is a planning tool. As soon as people read it as a performance measure, it stops being reliable.

The PMBOK Guide defines velocity as a measure of the team's productivity rate. On this point, the PMBOK Guide is wrong. Velocity adds up estimates that the team set itself. Martin Fowler writes: "Using velocity as a productivity measure kills agility." He adds that each team has its own basis of measurement and that no standard story point exists. The Agile Alliance glossary treats velocity as a measurement taken after the fact. There it is neither a budget nor a forecast. The glossary sees the phrase "setting velocity" as a basic misunderstanding. Velocity cannot be compared from one team to another.

The PMBOK Guide itself describes the mechanism among its measurement pitfalls. It names the Hawthorne effect there: measuring something changes the behaviour of the people measured. The example it gives almost describes velocity: "measuring only a project team's output of deliverables can encourage the project team to focus on creating a large volume of deliverables".

An imposed velocity destroys the indicator

In practice, the mechanism shows every time management sets a velocity target or asks for velocity to rise from sprint to sprint. The target does not make the team deliver faster. It inflates its estimates: the item that was worth 3 points is now worth 5. Velocity rises from the next sprint while the work delivered stays the same. The team had estimated the remaining work on the old scale. Divided by an inflated velocity, it gives a date that is too early. Nobody sees the error before the missed deadline.

Displayed velocity and work delivered
Velocity target set after sprint 3
Displayed velocity and work delivered: Velocity target set after sprint 3024681012123456SprintPointsVelocity target89106Displayed velocityWork delivered onthe old scaleDisplayed velocity and work delivered: Velocity target set after sprint 3024681012123456SprintPointsVelocity target89106Displayed velocityWork delivered onthe old scale
Remaining: 30 points on the old scale
Average of the last three sprints: 9
30 ÷ 9 = 3.3: 4 sprints
30 ÷ 6 = 5 sprints
After the target, the team inflates its estimates. The displayed velocity rises from 6 to 10 points. The work delivered stays at 6 points on the old scale. For the 30 points remaining, the displayed velocity announces 4 sprints and the work delivered needs 5.

A team that wants to meet the target without inflating its points closes items that do not meet the Definition of Done. Velocity rises and delivered quality falls. Another team works longer days. The eighth principle of the Agile Manifesto rules this route out: it asks for a pace the team can maintain indefinitely.

Some managers come to meetings with an idea picked up from old articles: in their view, a rising velocity proves that the team is improving. Under pressure, a lasting rise most often reflects point inflation. When the team recalibrates its scale, it dates the change on the chart and re-estimates the remaining work on the new scale. From then on it averages only the sprints measured after that date.

The word "velocity" carries the idea from those articles. Outside the team, the word to use is therefore "slope": it describes a rate used for forecasting.

Reading the chart and reacting

When the actual line moves away from the diagonal or the slope flattens, the team looks for the cause. The usual causes are a scope addition, an absence in the team, oversized items that stay open from one sprint to the next or point inflation. The iteration review shows the forecast to the stakeholders and adjusts the backlog. The retrospective deals with the causes that lie in how the team works.

The Scrum Guide points out that these forecasting practices do not replace empiricism. In a complex environment, only what has already happened can ground a forward-looking decision. The team therefore forecasts again at the end of every sprint from the latest measurements.

Progress charts and earned value

Earned value management asks the same question: what share of the planned work is done at this date? It answers in cost units against a performance measurement baseline. The PMBOK Guide applies it to adaptive approaches. Planned value (PV) becomes the total story points of the user stories planned up to the end of the iteration. Earned value (EV) becomes the total story points of the stories completed at that date. Actual cost (AC) comes from the team's hours of work.

The burnup's cumulative completed work is EV in points. PV corresponds to the work planned at each date: the burndown's ideal diagonal or the release plan line that the team adds to the burnup. The scope line carries the total to deliver. Neither chart carries AC. A project that reports on francs spent keeps using earned value management. The burnup is enough when the question is about scope and date.

AI considerations

A language model or a script reads the export of the backlog tool and rebuilds the chart: velocity per sprint, the range of the last three, the forecast and the dates of the scope changes. It also spots point inflation by comparing the average size of finished items from one quarter to the next. It drafts the progress paragraph of the status report. Before it goes out, the Product Owner rereads this paragraph and checks the averages and the forecast against the tool's chart: a language model can get a division wrong.

AI does not decide what counts as done. Only the team applies the Definition of Done. A model that proposes estimates in place of the team changes the unit of measure. Velocity computed from those points no longer continues the team's earlier series. An analysis per person is a design error: an individual velocity becomes a staff appraisal. The Agile Alliance glossary calls the phrase "individual velocity" meaningless. Remove the team members' names from the export before passing it to the model.

Examples

The burnup and the burndown of the same data show the scope addition in different ways.

Burnup and burndown of one release
8 points added at the start of sprint 5
Burnup
Burnup: Scope, Average slope (6), Done and Low slope (5)010203040500123456789SprintPoints+8 points,start of sprint 5Slope: 6 points per sprintScopeAverage slope (6)DoneLow slope (5)
Burndown
Burndown: Remaining, Average slope (6), Ideal and Low slope (5)010203040500123456789SprintPointsRise from 16 to 17RemainingAverage slope (6)IdealLow slope (5)
The burnup plots the scope addition on its own line. The burndown mixes it with the team's work: the remaining work rises from 16 to 17 points in sprint 5 although the team finished 7. The dotted lines of the average slope and the low slope put the end of the release between the end of sprint 8 and the end of sprint 9.
Release of a services portal in two-week sprints. The original plan puts the end of the release at sprint 7. The Product Owner adds 8 points at the start of sprint 5.
SprintDone in the sprintCumulative doneScopeRemaining
Start–04040
1664034
25114029
37184022
46244016
57314817
65364812

At the end of sprint 4, the average slope of the last three sprints is 6 points. The 16 remaining points need 3 sprints: the release lands at the end of sprint 7 as planned. At the end of sprint 6, the slope is still 6 points. The 12 remaining points need 2 sprints. The release moves to the end of sprint 8. The lowest slope of the three (5 points) needs 3. A Product Owner who must commit therefore announces the end of sprint 9.

On the burndown, sprint 5 pushes the remaining work up from 16 to 17 points although the team finished 7. Anyone who has only this chart sees a team going backwards.

Visualisations

The figure in Examples plots the same release on a burnup and on a burndown. The two charts share an axis of nine sprints. The burnup separates the scope step at the start of sprint 5 from the slope of completed work. Two dotted lines there extend the average slope and the low slope up to the scope line. The burndown absorbs the step into a rise of its actual line. In Description, a sprint burndown names the ideal line, the actual line and the trend line. Another figure follows an imposed velocity: the displayed velocity rises, the work delivered stays flat and the forecast brings the date forward. The PMBOK Guide also shows a combined burn chart on an information radiator (figure 5-9). Backlog tools plot velocity as bars per sprint with an average line.

Cost

DimensionLevelJustification
PreparationLowAt the start of the release, the team sets the unit and the interval once on an already estimated backlog. Relative estimation covers estimating the backlog. Without an estimated backlog, preparation rises to Medium.
ExecutionLowA backlog tool counts the finished items at the end of every sprint.
DocumentationLowOne chart to update per sprint with the date of each change of scope or of scale.

Tools

Backlog management tools (Jira, Azure DevOps, GitLab and their equivalents) produce the burndown, the burnup and the velocity chart from closed items. Check what the tool counts as done: an item's "closed" status and the team's Definition of Done do not always coincide. Also check that the tool plots scope additions on a separate line.

A spreadsheet is enough for one release: one row per sprint, the data columns and a line chart. It keeps the history of recalibrations and scope changes, which the team dates by hand.

The PMBOK Guide calls an information radiator a visible physical display that informs the rest of the organisation. The team often keeps it up to date by hand. A paper chart posted near the team plays this role. Some of its readers are outside the team: its legend therefore speaks of "slope".

Sources

  • PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., §2.3.2.3 "Monitor and Control Schedule": the burnup, the burndown and velocity among the tools of schedule control, the comparison of work delivered and accepted with work planned, the rate of output per iteration. Section 5, entries "Burndown chart", "Burnup chart", "Iteration burndown chart", "Velocity", "Information radiators" and "Earned value": the definitions, the ideal diagonal and the trend line, planned value and earned value in story points. §2.1.6.7.1 "Measurement Pitfalls": the Hawthorne effect and its example of deliverable volume.
  • Ken Schwaber and Jeff Sutherland, The Scrum Guide, November 2020, section "Sprint Planning": past performance, capacity and the Definition of Done as the bases of the sprint forecast. Section "The Sprint": burn-downs and burn-ups among the forecasting practices, which do not replace empiricism.
  • Swiss Confederation, HERMES 2022, Project Management Reference Manual, outcome 4.4.1.36 "Project status report": the burndown chart in the forecasts of goal achievement. §7.4.4.3 "Steering": in agile development, the comparison of estimated and actual remaining effort through the burndown chart and the publication of the result in the release report.
  • Agile Alliance, Agile Glossary, "Velocity": counting only finished items, the completion forecast and the sizing of the next iteration, velocity as a retrospective measure that is neither a budget nor a forecast, the misunderstanding of "setting velocity", the meaninglessness of an "individual velocity" and the absence of comparison between teams.
  • Agile Alliance, Agile Glossary, "Burndown Chart": the sprint burndown and the product burndown, the absence of scope changes on the chart, the origin with Ken Schwaber in 2000.
  • Martin Fowler, "XpVelocity", 17 May 2013: velocity as the calibration of a plan, the average of the last three periods ("Yesterday's Weather"), the example of 330 points at 26 points per iteration, the rejection of velocity as a productivity measure and the absence of a standard story point.
  • "Principles behind the Agile Manifesto": the eighth principle on a constant pace that the team can maintain indefinitely.