The bid process from left to right. It starts from the work order and a high-level estimate. The buyer then chooses the document. The RFI asks the market what it offers. For a private buyer or in an invitation procedure, its responses give a short list of suppliers. An RFP or an RFQ then goes to them. In an open or selective procedure, the RFI only informs the specifications. The RFP asks for a solution. The RFQ asks for a price. The tender documentation brings together the specifications, the list of criteria and the draft contract. The buyer publishes it on simap.ch or invites bidders. It answers the questions once for all bidders. The offers arrive on the set date. The offers then go to the vendor assessment.

Bid documents (RFI, RFP, RFQ)

Bid documents are the documents in which a buyer asks potential suppliers for information, a proposal or a price. The PMBOK Guide distinguishes three. The request for information (RFI) sounds out the market. The request for proposal (RFP) asks for a solution to a complex scope. The request for quote (RFQ) asks for a price for a solution available on the market. In the bid process, the buyer writes and distributes the documents. The buyer answers the bidders' questions, then receives the offers on the set date. In Switzerland, HERMES calls what the contracting authority publishes to solicit offers the tender documentation.

Goal

According to the PMBOK Guide (§X4.5), the buyer develops and publicises the documents. The buyer then holds a bidder conference and selects a bidder.

The technique settles one question: what must the buyer obtain? It delivers the chosen document, the register of questions and answers and the offers received by the deadline. The vendor assessment compares these offers and prepares the choice.

HERMES 2022 does not use the acronyms RFI, RFP and RFQ. It places the call for tenders in the Procurement module, under the tasks Prepare call for tenders and Issue call for tenders. The module covers the open and selective procedures. For a public buyer, the estimated contract value sets the procedure. The procurement analysis determines it before the team writes the tender documentation. A private buyer chooses its document without these constraints.

Usage

When to use it

  • Unfamiliar market: an RFI identifies the solutions and the suppliers before the buyer writes the specifications.
  • Complex need with no settled solution: an RFP lets the supplier propose the solution.
  • Standard product available on the market: an RFQ makes the suppliers compete on price.
  • Public purchase in an open or selective procedure: the project writes the HERMES tender documentation and publishes it on simap.ch.
  • Invitation procedure: the same documentation goes to the bidders that the contracting authority invites.
  • Several suppliers to choose between: shared documentation and shared answers make the offers comparable.

When not to use it

Description

Choosing the document

The three bid documents of the PMBOK Guide (§X4.5)
DocumentThe buyer seeksThe PMBOK Guide provides for it whenThe supplier submits
RFI (request for information)Information on the marketThe buyer wants to know the market before sending the documents to selected suppliersA description of its solutions and capabilities
RFP (request for proposal)A solutionThe scope is complex or complicated and the supplier must provide the solutionAn offer that describes the solution, its cost and its implementation
RFQ (request for quote)A pricePrice decides and the solution exists on the marketA price for what the buyer has described

The RFI comes before the documents that solicit offers. The buyer issues it before sending the bid documents to selected suppliers (PMBOK §X4.5). US federal law specifies its role: an agency can issue an RFI when it has no present intention to award a contract and seeks price, delivery or capability information for planning (FAR 15.201). This rule does not apply in Switzerland. In Switzerland, a public contracting authority can consult suppliers through a market clarification before the call for tenders. The procurement analysis describes this clarification and its effect on prior involvement. The contracting authority publishes its results in the tender documents (art. 14 para. 3 PPA).

The RFP describes the need, the objectives and the requirements. It leaves the solution to the bidder. The offers then differ in substance. To make them comparable, the buyer imposes the structure of the offer and publishes the criteria that will decide between them.

In an RFQ the buyer itself describes what it buys: the item reference, the quantity and the delivery date. The bidders respond with a price.

The PMBOK Guide mentions other documents specific to certain industries.

The tender documentation

According to HERMES 2022 (outcome 4.4.1.8), the documentation comprises all the information that the contracting authority publishes for a call for tenders.

The parts of the tender documentation according to HERMES 2022 (outcome 4.4.1.8)
PartWhat it sets
SpecificationsThe background and the reason for the purchase. The current situation: organisation, strengths and weaknesses, quantities and frequency, volume and price. The target situation: objectives and requirements, mandatory and optional criteria, scope, price range, deadlines, structure of the offer and administrative details.
List of criteriaThe eligibility criteria and the award criteria, their weighting and the points.
Draft contractThe type of contract that the procurement strategy selected (PMBOK §X4.4).
General terms and conditionsThe terms and conditions of the core organisation.
Tender noticeThe notice that the contracting authority publishes on simap.ch in the open and selective procedures (art. 48 para. 1 PPA).
Results of the market clarificationWhat the contracting authority learned from the suppliers it consulted before the call for tenders. It publishes these results in the tender documents (art. 14 para. 3 PPA).
Questions and answersThe bidders' questions and the contracting authority's answers, when the public call for tenders provides for questions. All bidders receive them.

Writing the specifications makes the buyer settle what it needs. The bidder learns from them what the buyer wants. According to HERMES, the specifications also force the bidder to take a position on every relevant issue and to submit an offer in the required structure. They incorporate the solution requirements and the organisational requirements when other modules have produced them.

The process

Work order and high-level estimate
Choice of document
RFI: what does the market offer?
Informs the specifications
Short list of suppliers
Private buyer or invitation procedure: to the selected suppliers
RFP: propose a solution
RFQ: give a price
Tender documentation: specifications, list of criteria, draft contract
Publication on simap.ch (open or selective procedure) or invitation
Bidder A
Bidder B
Bidder C
Questions and answers: one answer for all
Shared answer
Offers received on the set date
Vendor assessment
The buyer chooses the document after the work order. A private buyer or a contracting authority in an invitation procedure then sends an RFP or an RFQ to the suppliers it selects after the RFI. In an open or selective procedure, the RFI only informs the specifications. Every question receives a shared answer. The offers received go to the vendor assessment.

Start from the decision to buy. The PMBOK Guide starts the flow with the work order (SOW, statement of work) and high-level estimates (Figure X4-1). The work order describes what the supplier must deliver. The high-level estimate gives a benchmark for the prices when they arrive. Upstream, the make-or-buy analysis has established that the purchase is justified. In a HERMES project, the procurement analysis has set the procedure, the procurement plan and the person who answers the questions.

Choose the document. One purchase can chain two documents. A private buyer or a contracting authority in an invitation procedure sounds out the market with an RFI. It then sends an RFP or an RFQ to the suppliers it selects. In the open procedure, any bidder can submit an offer. In the selective procedure, the contracting authority admits bidders according to their eligibility. In these two procedures the RFI only informs the specifications.

Write the documentation. In the HERMES task Prepare call for tenders (5.4.3.5), the project produces the specifications, the list of criteria, the draft contract and the tender notice from the procurement analysis. The task also lists the protection needs analysis among its prerequisites. The protection requirements go into the specifications. For example, the protection needs analysis sets requirement E-17: hosting in Switzerland. The list of criteria contains all the eligibility criteria, the technical specifications, the award criteria and the evaluation model. The controlling and compliance bodies then check the documentation.

The PMBOK Guide recommends including the evaluation method in the bid documents so that bidders know how the buyer will evaluate them (§X4.6). The PPA requires the federal contracting authority to state the award criteria and their weighting in the call for tenders or in the tender documents (art. 29 para. 3). For a contract that concerns solutions, proposed solutions or procedures, it can publish the criteria without their weighting. The AIMP/IVöB 2019 sets the same rule for the cantons and the municipalities. The vendor assessment builds the criteria and their weights.

Decide and publish. In HERMES, the project sponsor decides on the call for tenders (task 5.4.1.1). The sponsor checks the documentation against the tender checklist and coordinates the decision with the core organisation. The Tender milestone is reached when the project sponsor has made this decision. In the open and selective procedures, the project then publishes the documentation on simap.ch (task 5.4.3.4, art. 48 para. 1 PPA). In an invitation procedure, the project sends it to the invited bidders. A call for tenders for supplies or services appears in principle in at least two official languages (art. 48 para. 5).

Answer the questions. Once the documents are distributed, the buyer generally holds a bidder conference. At the conference the buyer answers the questions and clarifies the documentation. The PMBOK Guide's glossary gives its purpose: all bidders share a clear and common understanding of the procurement before they prepare their offer. The PMBOK Guide also calls it a vendor conference or a pre-bid conference.

In HERMES, the buyer records the answers to the bidders' questions. It makes them available to all interested parties in neutralised form. The neutralised form removes the name of the bidder that asked the question and any detail that points to it.

Receive the offers. The bidders prepare their offer and submit it by the date that the documents set. HERMES calls this outcome the Offer (4.4.1.4). It describes the service or the product, its commercial terms and the way it will be delivered. It follows the structure that the contracting authority imposed. The procurement analysis gives the minimum submission deadlines that the PPA sets. For a public contract, the contracting authority draws up a report on the opening of the offers when the submission deadline expires (HERMES outcome 4.4.1.5). The offers then go to the vendor assessment.

Pitfalls

Confusing the two meanings of RFI. The PMBOK Guide also uses the acronym for the questions that bidders ask during the call for tenders (§X4.2). A team that speaks of an "RFI" therefore says which of the two it means: the market consultation before the documentation or a question about the published documentation.

Prescribing the solution in an RFP. Specifications that describe the expected solution rule out the solutions that the bidders know. The buyer then pays the cost of an RFP to receive RFQ responses.

Issuing an RFQ for a complex scope. Price decides only between offers for the same goods or services. For a complex procurement, the PMBOK Guide advises against least cost as a selection method because it can harm quality (§X4.6).

Leaving the structure of the offer open. Each bidder then answers in its own order and in its own terms. The evaluators look for the same information in a different place in each offer. HERMES sets the structure of the offer in the specifications to obtain a uniform reference basis.

Answering a single bidder. A buyer who answers one bidder by telephone gives it information that the others lack. The others then prepare their offer on different documentation. Every answer goes through the shared register.

Having a supplier consulted through the RFI write the specifications. The contracting authority excludes a bidder that took part in preparing the procedure when the advantage gained cannot be offset and the exclusion does not jeopardise competition (art. 14 para. 1 PPA). The procurement analysis describes how the contracting authority offsets this advantage.

AI considerations

A language model drafts a first version of the specifications from the solution requirements, the organisational requirements and the Study of the HERMES project. It compares the documentation with the tender checklist and flags an empty section, for example a missing offer structure or a criterion without a weighting. It translates the tender notice into a second official language for review. It groups the questions received by theme, spots duplicates and proposes a neutral wording. It sorts the responses to an RFI and groups the suppliers by type of solution.

The choice between RFI, RFP and RFQ stays with the buyer because it commits the buyer to the course of the procedure and determines what the bidders can offer. A person reviews every answer to the bidders before publication. A published answer changes the documentation for everyone. The estimated value, the budget and the offers received do not go to an AI service that the organisation has not authorised. A bidder that knew the budget would have an advantage over the others. The fixed-budget method is the exception: the request then discloses the budget to all invited suppliers (PMBOK §X4.6). A model that writes the specifications from a supplier's documentation copies that supplier's solution into the tender documentation.

Examples

The register of questions and answers shows how a bidder's question becomes part of the documentation for everyone. In a fictitious case, a federal office publishes the "Records management" call for tenders on simap.ch in an open procedure.

The questions and answers that the contracting authority sent on 12 March to all bidders in the "Records management" call for tenders
No.Question published without the bidder's nameAnswer of the contracting authorityPart of the documentation changed
1Can the configuration be subcontracted?Yes. The offer names each subcontractor and the share of the services it provides.Structure of the offer in the specifications: "Subcontracting" section added
2Do the 48 months of subscription run from the signature of the contract or from go-live?From go-live.Term in the draft contract: start date specified
3What volume of data does the migration cover?About 180'000 records and 2.5 TB of attachments.Current situation in the specifications: volumes added
4Is a solution hosted outside Switzerland acceptable?No. Requirement E-17 of the specifications requires hosting in Switzerland.No other part

The bidder that asked question 4 named its data centre. The register publishes the question without that name. Answer 4 changes no other part. All bidders still receive it.

Visualisations

A diagram shows the bid process from the work order to the offers received. It places the choice of document before the writing of the documentation and routes every question through a shared answer. The three documents, the parts of the documentation and the register of questions are rows and columns. They are therefore tables.

Cost

DimensionLevelRationale
PreparationHigh for an RFPThe specifications, the list of criteria and the draft contract take several weeks for an RFP. An RFQ takes a few days.
ExecutionMediumThe team answers the questions by the deadline, holds the conference and receives the offers.
DocumentationMediumThe register of questions and each version of the documentation remain available to all bidders.

Tooling

simap.ch is the public procurement platform of the Confederation and the cantons. The contracting authority publishes the call for tenders of the open and selective procedures there.

When the organisation provides standard tender documents from its procurement unit, HERMES puts them ahead of any general template.

A word processor with version tracking holds the specifications and the draft contract. A spreadsheet holds the list of criteria and the register of questions and answers. A dedicated mailbox receives all the bidders' questions and keeps a record of each exchange.

E-procurement suites distribute the documentation, collect the questions and the offers and timestamp each exchange. They are worth using when the procedure is formal or the bidders are numerous.

Sources

Benne and Sheats Group Roles