Bid documents (RFI, RFP, RFQ)
Bid documents are the documents in which a buyer asks potential suppliers for information, a proposal or a price. The PMBOK Guide distinguishes three. The request for information (RFI) sounds out the market. The request for proposal (RFP) asks for a solution to a complex scope. The request for quote (RFQ) asks for a price for a solution available on the market. In the bid process, the buyer writes and distributes the documents. The buyer answers the bidders' questions, then receives the offers on the set date. In Switzerland, HERMES calls what the contracting authority publishes to solicit offers the tender documentation.
Goal
According to the PMBOK Guide (§X4.5), the buyer develops and publicises the documents. The buyer then holds a bidder conference and selects a bidder.
The technique settles one question: what must the buyer obtain? It delivers the chosen document, the register of questions and answers and the offers received by the deadline. The vendor assessment compares these offers and prepares the choice.
HERMES 2022 does not use the acronyms RFI, RFP and RFQ. It places the call for tenders in the Procurement module, under the tasks Prepare call for tenders and Issue call for tenders. The module covers the open and selective procedures. For a public buyer, the estimated contract value sets the procedure. The procurement analysis determines it before the team writes the tender documentation. A private buyer chooses its document without these constraints.
Usage
When to use it
- Unfamiliar market: an RFI identifies the solutions and the suppliers before the buyer writes the specifications.
- Complex need with no settled solution: an RFP lets the supplier propose the solution.
- Standard product available on the market: an RFQ makes the suppliers compete on price.
- Public purchase in an open or selective procedure: the project writes the HERMES tender documentation and publishes it on simap.ch.
- Invitation procedure: the same documentation goes to the bidders that the contracting authority invites.
- Several suppliers to choose between: shared documentation and shared answers make the offers comparable.
When not to use it
- Received offers awaiting comparison: run a vendor assessment.
- Public purchase with no procedure chosen yet: run a procurement analysis.
- Only one possible supplier: prepare the negotiation.
Description
Choosing the document
| Document | The buyer seeks | The PMBOK Guide provides for it when | The supplier submits |
|---|---|---|---|
| RFI (request for information) | Information on the market | The buyer wants to know the market before sending the documents to selected suppliers | A description of its solutions and capabilities |
| RFP (request for proposal) | A solution | The scope is complex or complicated and the supplier must provide the solution | An offer that describes the solution, its cost and its implementation |
| RFQ (request for quote) | A price | Price decides and the solution exists on the market | A price for what the buyer has described |
The RFI comes before the documents that solicit offers. The buyer issues it before sending the bid documents to selected suppliers (PMBOK §X4.5). US federal law specifies its role: an agency can issue an RFI when it has no present intention to award a contract and seeks price, delivery or capability information for planning (FAR 15.201). This rule does not apply in Switzerland. In Switzerland, a public contracting authority can consult suppliers through a market clarification before the call for tenders. The procurement analysis describes this clarification and its effect on prior involvement. The contracting authority publishes its results in the tender documents (art. 14 para. 3 PPA).
The RFP describes the need, the objectives and the requirements. It leaves the solution to the bidder. The offers then differ in substance. To make them comparable, the buyer imposes the structure of the offer and publishes the criteria that will decide between them.
In an RFQ the buyer itself describes what it buys: the item reference, the quantity and the delivery date. The bidders respond with a price.
The PMBOK Guide mentions other documents specific to certain industries.
The tender documentation
According to HERMES 2022 (outcome 4.4.1.8), the documentation comprises all the information that the contracting authority publishes for a call for tenders.
| Part | What it sets |
|---|---|
| Specifications | The background and the reason for the purchase. The current situation: organisation, strengths and weaknesses, quantities and frequency, volume and price. The target situation: objectives and requirements, mandatory and optional criteria, scope, price range, deadlines, structure of the offer and administrative details. |
| List of criteria | The eligibility criteria and the award criteria, their weighting and the points. |
| Draft contract | The type of contract that the procurement strategy selected (PMBOK §X4.4). |
| General terms and conditions | The terms and conditions of the core organisation. |
| Tender notice | The notice that the contracting authority publishes on simap.ch in the open and selective procedures (art. 48 para. 1 PPA). |
| Results of the market clarification | What the contracting authority learned from the suppliers it consulted before the call for tenders. It publishes these results in the tender documents (art. 14 para. 3 PPA). |
| Questions and answers | The bidders' questions and the contracting authority's answers, when the public call for tenders provides for questions. All bidders receive them. |
Writing the specifications makes the buyer settle what it needs. The bidder learns from them what the buyer wants. According to HERMES, the specifications also force the bidder to take a position on every relevant issue and to submit an offer in the required structure. They incorporate the solution requirements and the organisational requirements when other modules have produced them.
The process
Start from the decision to buy. The PMBOK Guide starts the flow with the work order (SOW, statement of work) and high-level estimates (Figure X4-1). The work order describes what the supplier must deliver. The high-level estimate gives a benchmark for the prices when they arrive. Upstream, the make-or-buy analysis has established that the purchase is justified. In a HERMES project, the procurement analysis has set the procedure, the procurement plan and the person who answers the questions.
Choose the document. One purchase can chain two documents. A private buyer or a contracting authority in an invitation procedure sounds out the market with an RFI. It then sends an RFP or an RFQ to the suppliers it selects. In the open procedure, any bidder can submit an offer. In the selective procedure, the contracting authority admits bidders according to their eligibility. In these two procedures the RFI only informs the specifications.
Write the documentation. In the HERMES task Prepare call for tenders (5.4.3.5), the project produces the specifications, the list of criteria, the draft contract and the tender notice from the procurement analysis. The task also lists the protection needs analysis among its prerequisites. The protection requirements go into the specifications. For example, the protection needs analysis sets requirement E-17: hosting in Switzerland. The list of criteria contains all the eligibility criteria, the technical specifications, the award criteria and the evaluation model. The controlling and compliance bodies then check the documentation.
The PMBOK Guide recommends including the evaluation method in the bid documents so that bidders know how the buyer will evaluate them (§X4.6). The PPA requires the federal contracting authority to state the award criteria and their weighting in the call for tenders or in the tender documents (art. 29 para. 3). For a contract that concerns solutions, proposed solutions or procedures, it can publish the criteria without their weighting. The AIMP/IVöB 2019 sets the same rule for the cantons and the municipalities. The vendor assessment builds the criteria and their weights.
Decide and publish. In HERMES, the project sponsor decides on the call for tenders (task 5.4.1.1). The sponsor checks the documentation against the tender checklist and coordinates the decision with the core organisation. The Tender milestone is reached when the project sponsor has made this decision. In the open and selective procedures, the project then publishes the documentation on simap.ch (task 5.4.3.4, art. 48 para. 1 PPA). In an invitation procedure, the project sends it to the invited bidders. A call for tenders for supplies or services appears in principle in at least two official languages (art. 48 para. 5).
Answer the questions. Once the documents are distributed, the buyer generally holds a bidder conference. At the conference the buyer answers the questions and clarifies the documentation. The PMBOK Guide's glossary gives its purpose: all bidders share a clear and common understanding of the procurement before they prepare their offer. The PMBOK Guide also calls it a vendor conference or a pre-bid conference.
In HERMES, the buyer records the answers to the bidders' questions. It makes them available to all interested parties in neutralised form. The neutralised form removes the name of the bidder that asked the question and any detail that points to it.
Receive the offers. The bidders prepare their offer and submit it by the date that the documents set. HERMES calls this outcome the Offer (4.4.1.4). It describes the service or the product, its commercial terms and the way it will be delivered. It follows the structure that the contracting authority imposed. The procurement analysis gives the minimum submission deadlines that the PPA sets. For a public contract, the contracting authority draws up a report on the opening of the offers when the submission deadline expires (HERMES outcome 4.4.1.5). The offers then go to the vendor assessment.
Pitfalls
Confusing the two meanings of RFI. The PMBOK Guide also uses the acronym for the questions that bidders ask during the call for tenders (§X4.2). A team that speaks of an "RFI" therefore says which of the two it means: the market consultation before the documentation or a question about the published documentation.
Prescribing the solution in an RFP. Specifications that describe the expected solution rule out the solutions that the bidders know. The buyer then pays the cost of an RFP to receive RFQ responses.
Issuing an RFQ for a complex scope. Price decides only between offers for the same goods or services. For a complex procurement, the PMBOK Guide advises against least cost as a selection method because it can harm quality (§X4.6).
Leaving the structure of the offer open. Each bidder then answers in its own order and in its own terms. The evaluators look for the same information in a different place in each offer. HERMES sets the structure of the offer in the specifications to obtain a uniform reference basis.
Answering a single bidder. A buyer who answers one bidder by telephone gives it information that the others lack. The others then prepare their offer on different documentation. Every answer goes through the shared register.
Having a supplier consulted through the RFI write the specifications. The contracting authority excludes a bidder that took part in preparing the procedure when the advantage gained cannot be offset and the exclusion does not jeopardise competition (art. 14 para. 1 PPA). The procurement analysis describes how the contracting authority offsets this advantage.
AI considerations
A language model drafts a first version of the specifications from the solution requirements, the organisational requirements and the Study of the HERMES project. It compares the documentation with the tender checklist and flags an empty section, for example a missing offer structure or a criterion without a weighting. It translates the tender notice into a second official language for review. It groups the questions received by theme, spots duplicates and proposes a neutral wording. It sorts the responses to an RFI and groups the suppliers by type of solution.
The choice between RFI, RFP and RFQ stays with the buyer because it commits the buyer to the course of the procedure and determines what the bidders can offer. A person reviews every answer to the bidders before publication. A published answer changes the documentation for everyone. The estimated value, the budget and the offers received do not go to an AI service that the organisation has not authorised. A bidder that knew the budget would have an advantage over the others. The fixed-budget method is the exception: the request then discloses the budget to all invited suppliers (PMBOK §X4.6). A model that writes the specifications from a supplier's documentation copies that supplier's solution into the tender documentation.
Examples
The register of questions and answers shows how a bidder's question becomes part of the documentation for everyone. In a fictitious case, a federal office publishes the "Records management" call for tenders on simap.ch in an open procedure.
| No. | Question published without the bidder's name | Answer of the contracting authority | Part of the documentation changed |
|---|---|---|---|
| 1 | Can the configuration be subcontracted? | Yes. The offer names each subcontractor and the share of the services it provides. | Structure of the offer in the specifications: "Subcontracting" section added |
| 2 | Do the 48 months of subscription run from the signature of the contract or from go-live? | From go-live. | Term in the draft contract: start date specified |
| 3 | What volume of data does the migration cover? | About 180'000 records and 2.5 TB of attachments. | Current situation in the specifications: volumes added |
| 4 | Is a solution hosted outside Switzerland acceptable? | No. Requirement E-17 of the specifications requires hosting in Switzerland. | No other part |
The bidder that asked question 4 named its data centre. The register publishes the question without that name. Answer 4 changes no other part. All bidders still receive it.
Visualisations
A diagram shows the bid process from the work order to the offers received. It places the choice of document before the writing of the documentation and routes every question through a shared answer. The three documents, the parts of the documentation and the register of questions are rows and columns. They are therefore tables.
Cost
| Dimension | Level | Rationale |
|---|---|---|
| Preparation | High for an RFP | The specifications, the list of criteria and the draft contract take several weeks for an RFP. An RFQ takes a few days. |
| Execution | Medium | The team answers the questions by the deadline, holds the conference and receives the offers. |
| Documentation | Medium | The register of questions and each version of the documentation remain available to all bidders. |
Tooling
simap.ch is the public procurement platform of the Confederation and the cantons. The contracting authority publishes the call for tenders of the open and selective procedures there.
When the organisation provides standard tender documents from its procurement unit, HERMES puts them ahead of any general template.
A word processor with version tracking holds the specifications and the draft contract. A spreadsheet holds the list of criteria and the register of questions and answers. A dedicated mailbox receives all the bidders' questions and keeps a record of each exchange.
E-procurement suites distribute the documentation, collect the questions and the offers and timestamp each exchange. They are worth using when the procedure is formal or the bidders are numerous.
Sources
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th ed., Appendix X4: §X4.5 Bid Process and Documents for the bid process, the three documents and the bidder conference; Figure X4-1 for the flow from the work order to the contract; §X4.2 for the second meaning of RFI; §X4.4 for the type of contract that the procurement strategy sets; §X4.6 for the evaluation method in the documents and the limit of least cost; glossary, entries bid documents and bidder conference.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management reference manual, Procurement module: tasks 5.4.1.1 Decide on call for tenders, 5.4.3.4 Issue call for tenders and 5.4.3.5 Prepare call for tenders; outcomes 4.4.1.4 Offer, 4.4.1.5 Tender report, 4.4.1.8 Tender documentation, 4.4.2.3 Tender checklist and 4.4.4.3 Tender milestone.
- Federal Act on Public Procurement (PPA), SR 172.056.1: art. 14 para. 1 and 3 (prior involvement and market clarification), art. 29 para. 3 (award criteria and weighting in the call for tenders), art. 48 para. 1 and 5 (publication on simap.ch and languages).
- DTAP, Intercantonal Agreement on Public Procurement (AIMP/IVöB) of 15 November 2019: art. 29 para. 3 for the cantons and the municipalities. This paragraph takes over the content of art. 29 para. 3 PPA.
- U.S. General Services Administration, Federal Acquisition Regulation (FAR) 15.201, Exchanges with industry before receipt of proposals.