Diagram of the auditor's position. On the left, the reference framework brings together the policies, processes, procedures and plans of the organisation and the project. In the centre, the project boundary encloses the quality process, the procurement process with its contracts and the risk management process. The project deliverables are grey inside the boundary. No arrow reaches them. The auditor is placed outside the boundary, since the auditor usually stands outside the project. An arrow runs from the auditor to each process: quality audit, procurement audit, risk audit. An arrow runs from the reference framework to the auditor. The findings leave the auditor in two groups: good practices and nonconformities.

Audits

An audit is a structured and independent process that determines whether project activities comply with the policies, processes and procedures of the organisation and the project. The PMBOK Guide gives this definition and describes quality, procurement and risk audits. The auditor examines the project's processes. The content of the deliverables belongs to quality control. The audit identifies good practices and nonconformities. Its findings feed quality reports, change requests and the organisation's lessons learned.

Goal

An audit checks that project activities follow the policies, processes and procedures that the organisation and the project have set for themselves. The PMBOK Guide lists it among the tools of the Manage Quality Assurance process (§2.1.6.5). This process turns the project management plan into activities that build in the organisation's standards, regulations and policies. It runs for the whole project.

According to the PMBOK, quality assurance gives confidence that a future output will meet the requirements. It improves the effectiveness and efficiency of the processes. It also checks that the project is governed as planned.

The deliverable of an audit is a findings report. Each finding relates an activity to the written rule that it complies with or breaches. The Manage Quality Assurance process draws quality reports and change requests from it. HERMES records the findings in the review report. The project manager uses the report to correct the project's processes. The project sponsor learns from it whether the project follows its rules.

The word audit also names a strategy technique. The resource audit takes stock of what an organisation owns and looks for a competitive advantage in it. It does not check compliance.

Usage

When to use

  • A policy, regulation or standard to comply with: show the sponsor or a supervisory body that the project works by its rules.
  • A quality management plan in force: conduct the quality audits that it provides for, scheduled or random.
  • A sponsor who wants independent assurance: give the audit of project management to a body that does not report to the project manager.
  • A contract with a supplier: examine the contracts and the procurement process; write the audit clause before signature.
  • A risk management plan that sets a frequency: check at that interval that the risk management process works.
  • Approved corrective actions: confirm that they have been implemented.
  • Good practices to spread: identify what works in a project and add it to the organisation's lessons learned.

When not to use

  • Judging the content of a deliverable: the audit checks the process; submit the document to a review or an inspection.
  • Checking that the solution meets the requirements: that is the job of testing and of user acceptance testing (UAT).

Description

The object of the audit: the process

The PMBOK separates quality assurance from quality control. Quality assurance concerns the effective use of the project's processes. Its related concepts are regulation, compliance and audit. Quality control concerns the production of deliverables that meet their specifications and thresholds. Its related concepts are product design, testing and defects. The audit belongs to quality assurance.

Quality assurance and quality control according to the PMBOK Guide.
Quality assuranceQuality control
ObjectThe project's processesThe project's deliverables
QuestionDoes the project work by its rules?Does the deliverable meet its specification?
Related conceptsRegulation, compliance, auditsProduct design, testing, defects

HERMES draws the line elsewhere. Checking covers the content and form of documents and compliance with the agreed processes. Testing verifies that the solution meets the requirements. The audit is one of the forms of checking that the task "Perform quality assurance" names.

Reference framework
Policies
Processes and procedures
Project plans
Independent auditor
Internal audit, PMO or external auditor
Project
Quality auditQuality process
Procurement auditProcurement process and contracts
Risk auditRisk management process
Deliverables
Findings
Good practices
Nonconformities
The auditor usually stands outside the project. The auditor compares the project's activities with the written policies, processes and procedures. The quality audit, the procurement audit and the risk audit each examine one process. The content of the deliverables belongs to quality control.

The independence of the auditor

The auditor is not accountable for the process under examination: the definition calls for an independent process. A person from the project can therefore audit a process they do not run. For the quality audit, the PMBOK names a team that is usually external to the project: the organisation's internal audit function, the project management office (PMO) or an auditor from outside the organisation.

The project management team, an external entity or both carry out the quality assurance tasks. In a predictive project, quality assurance is usually formal. In an agile or adaptive project, it is formal or informal depending on the context.

In HERMES, the project manager is responsible for the task "Perform quality assurance". Depending on the size of the project and its risks, the project sponsor gives quality and risk management to a dedicated body that reports to the sponsor directly. This body holds the role of quality and risk manager. The organisation that provides it takes no other role in the project and guarantees the independence of its mandate. Among other things, the quality and risk manager assesses whether the project complies with the directives of the core organisation. The quality and risk manager hands the project sponsor the QA and risk report, which gives an independent view of the project.

The quality audit

The quality audit examines the project's processes. It is scheduled or random. The PMBOK counts among its objectives:

  • identify all good practices being applied;
  • identify all nonconformities, deviations and gaps;
  • share the good practices of similar projects in the organisation or the industry;
  • offer help in a positive manner to improve the application of processes and the productivity of the team;
  • add the contribution of each audit to the organisation's lessons learned repository;
  • confirm the implementation of approved change requests, corrective actions, defect repairs and preventive actions.

Some of these objectives concern what works: identifying good practices, sharing them and adding the contribution of the audit to the lessons learned. When the team corrects the gaps found, the cost of quality falls and the sponsor or the customer accepts the product more readily. The cost of quality counts the audit among the appraisal costs.

The procurement audit

The procurement audit examines the project's procurement process: the contracts and the contracting processes. It checks that they are complete, accurate and effective. The contract describes the rights and obligations that relate to audits. The auditor communicates the observations to the project managers of the buyer and the seller. Both adjust the project if necessary.

The risk audit

The risk audit examines the effectiveness of the risk management process. The project manager sees to it that these audits take place at the frequency that the risk management plan sets. The team holds the audit during a regular status meeting, during a risk review meeting or in a separate session. It defines the format and objectives of the audit beforehand. The PMBOK also lists audits among the tools of the Monitor Risks process (§2.7.2.6).

For example, a risk audit asks whether the owners update their risks at the planned interval, whether the team applies the agreed responses and whether the risk register reflects the state of the project.

Object, basis, responsibility and recipients of the findings for each type of audit according to the PMBOK Guide.
TypeObjectBasisResponsibilityRecipients of the findings
Quality auditThe project's processesThe quality management plan; scheduled or random auditTeam usually external to the project: internal audit, PMO or external auditorQuality reports
Procurement auditThe contracts and the contracting processesThe audit rights and obligations in the contractNot specifiedProject managers of the buyer and the seller
Risk auditThe risk management processThe frequency in the risk management plan; format and objectives set before the auditProject manager: oversees the audit frequencyNot specified

Audit, review, inspection

The PMBOK notes that inspections are sometimes called reviews, peer reviews, audits or walkthroughs. In some application areas these terms have a narrow meaning. An inspection examines a work product to determine whether it conforms to documented standards. An audit examines project activities against the project's policies, processes and procedures.

A review submits a work product to people other than its author. The reviewers look for defects or for consensus. The audit judges from an independent position how the team worked. The reviewers go over the content of a specification. The quality audit then checks that this review took place as the project management plan provides.

Conducting an audit

The PMBOK defines the audit, its types and its objectives. Each step restates a provision of the PMBOK or of HERMES. Their order follows the course of an audit.

  1. Choose the type according to what is audited. The project's processes call for a quality audit. The contracts and the procurement process call for a procurement audit. Risk management calls for a risk audit.
  2. Write the audit into the plans. The quality management plan describes the quality assurance actions. It provides for scheduled or random audits. The risk management plan sets the frequency of risk audits. The contract sets the audit rights. In HERMES, the project management plan contains the review plan. The work order provides for the reviews.
  3. Define the format and objectives before the audit. The PMBOK sets this rule for the risk audit. HERMES likewise records the review procedure in the work order. The work order tells the auditor and the sponsor what the audit covers. The sponsor reads the report against these objectives.
  4. Appoint an independent auditor. The internal audit function, the PMO or an external auditor usually conducts the quality audit. The risk audit is the exception: the team can hold it during a regular status meeting. The quality auditor is internal or external to the organisation.
  5. Compare the activities with the reference framework. The auditor sets the project's activities against the policies, processes and procedures. The auditor identifies good practices, nonconformities, deviations and gaps.
  6. Record and report. The findings go into the quality reports. HERMES records them in the review report. The procurement audit sends its observations to the project managers of the buyer and the seller.
  7. Open the change requests. The auditor or the project manager opens a change request for each nonconformity: a corrective action, a defect repair or a preventive action. The next audit confirms the implementation of what the project approved.
  8. Add the lessons to the organisation's repository. The good practices found serve later projects. You will find the procedure under Lessons Learned.
  9. Evaluate quality assurance. In HERMES, the task "Perform quality assurance" includes the activity "Evaluate the fitness for purpose of quality assurance and make adjustments if necessary". The project manager judges whether the project's quality assurance serves its purpose and adjusts it if needed.
Plans: frequency, audit rights
Format and objectives
Audit: compare with the reference framework
Findings
Good practices
Organisation's lessons learned
Nonconformities
Change request
Correction approved and implemented
Next audit: confirm the correction
Quality report · Review report (HERMES)
A nonconformity becomes a change request. The next audit confirms the approved correction. A good practice joins the organisation's lessons learned.

Pitfalls

The auditor as judge in their own case. A person who audits a process they run loses the independence that the definition calls for. The sponsor or the PMO gives the audit to a person who is not accountable for that process.

The audit that reviews the content of the deliverable. An auditor who corrects a specification is doing a review. The audit finding concerns the rule: did the planned review take place, with which reviewers and which minutes?

The audit seen as a punishment. The audit also aims to offer help in a positive manner and to share good practices. A team that fears the audit hides its deviations. The next audit no longer sees them.

Findings without follow-up. A nonconformity without a change request or an owner stays open. The auditor adds a check of the approved corrections to the scope of the next audit.

An unwritten rule. The auditor compares activities with written rules. An unwritten rule produces only diverging opinions. The project writes it into the plan before the audit.

The forgotten audit clause. Without an audit right written into the contract, the buyer negotiates access to the supplier's records when the need arises.

AI considerations

An AI assistant compares a change log with the directive that governs it. It flags requests without approval, missing minutes and late dates. This sorting replaces the first line-by-line reading. The assistant also drafts a checklist from a written policy. It formats the findings report.

It does not decide whether a finding is a nonconformity. A rule can often be read two ways. The auditor chooses the reading and answers for it. A tool that the audited team configures and feeds also carries the choices of that team. It therefore does not bring the independence that the audit calls for.

Contracts contain confidential prices and terms. Project registers contain personal data. Before putting these documents into an online service, the auditor checks the organisation's policy and the applicable data protection law. A private company or a federal body falls under the FADP. A cantonal administration falls under cantonal law.

Examples

Concept illustrated: the quality audit report relates each activity examined to its reference and gives each nonconformity a follow-up. It also records a good practice that another project shared. The PMO of a canton audits the tax portal redesign project at the end of the Concept phase. The project management plan provides for this audit.

Quality audit report of the tax portal project at the end of the Concept phase.
No.ReferenceFindingClassificationFollow-up
1Cantonal directive on change management: the project committee approves every change to the scope.7 requests out of 7 approved by the committee, with minutes.Good practiceAdded to the lessons learned repository.
2Review plan: each specification passes a review before its release.2 specifications out of 9 released without a review report.NonconformityChange request: review of the 2 specifications before the Phase release milestone. Project manager, 13 November 2026.
3Cantonal directive on data protection: test data is anonymised.The integration environment contains real taxpayer data.NonconformityChange request: anonymise the test data set. Test manager, 30 October 2026.
4Corrective action from the previous audit: the committee minutes go out within 5 working days.4 sets of minutes out of 4 issued on time.Correction confirmedItem closed.
5Practice of the land register project in the same canton.That project keeps a release checklist for each specification.Shared good practiceProposed to the team. Decision by the project manager.

Finding 2 does not judge the content of the two specifications. It establishes that no record of the planned review exists. The change request orders this review.

Visualisations

The diagram of the auditor's position places the auditor opposite the processes under examination and usually outside the project. The findings loop shows the path of a nonconformity up to the audit that confirms its correction. The table of quality assurance and quality control separates the object of the audit from that of quality control. The table of types compares the object, basis, responsibility and recipients of the findings for each audit. The audit report shows the deliverable.

Cost

PhaseLevelRationale
PreparationMediumSet the type, format and objectives. Gather the written reference framework and obtain access to the project's records.
ExecutionMediumCompare each activity with its rule. The duration depends on the number of rules, contracts and records examined.
DocumentationLowA findings report and the change requests that follow from it. In HERMES, the review report.

Tooling

A spreadsheet or a form is enough for the checklist and the findings report. The auditor reads the records where the project keeps them. The minutes sit in a document management system such as SharePoint. The change log sits in a tracking tool such as Jira. The risk audit reads the risk register.

An organisation that audits a portfolio of projects uses a governance, risk and compliance (GRC) tool. It schedules the audits and tracks each finding to closure.

Sources

  • Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition, PMI: the Manage Quality Assurance process, the distinction between quality assurance and quality control and the aims of quality assurance (§2.1.6.5, Figure 2-7); audits among the tools of Monitor Risks (§2.7.2.6, Figure 2-53); the definition of the audit and the quality, procurement and risk audits (section 5, entry Audits); the other names for inspections (section 5, entry Inspections); the audit among the appraisal costs (section 5, entry Cost of quality (CoQ)).
  • Swiss Confederation, HERMES 2022, task Perform quality assurance: checking and testing, reviews and audits as forms of checking, the review plan, the review report; the role Quality and risk manager and its outcome QA and risk report: the independent body that the project sponsor appoints.
  • ISO, ISO 19011, Guidelines for auditing management systems: further reading.