Agile Release Planning
Agile release planning sets the schedule of a release: how many iterations it holds and which features are available at the end of each one. A release is a set of features that go live together. The PMBOK Guide lists the technique among the tools of the Develop Schedule process. It sits between the product roadmap and the iteration plan.
Goal
The release plan sets the number and length of the iterations, the size of the team, the features available at the end of each iteration and the go-live date. According to the PMBOK Guide, this schedule typically covers three to six months. The product owner and the team use it to fix the scope and the dates of a releasable product. They take account of business goals, dependencies, impediments and available resources.
The plan answers the question the sponsor asks as soon as a backlog exists: which features will be live by which date? It counts in features because a feature delivers the value the customer expects. The business therefore reads the schedule in its own terms.
Usage
When to use it
- A go-live date to announce: the plan states which features will be ready at the end of which iteration.
- Agile HERMES project: the release plan fits into the schedule of the project management plan.
- Dependency on another team or a supplier: the plan fixes the iteration in which each expected delivery must be ready.
- Budget justified release by release: the cost of one iteration multiplied by the number of iterations gives the cost of the release.
When not to use it
- Product direction still open: set the vision and the product roadmap first.
- Continuous flow without iterations: forecast dates from the throughput that a cumulative flow diagram measures.
- Traditional HERMES project delivered in steps: divide the work into implementation units and plan them all in the Concept phase.
Description
The planning levels
Each plan details the next slice of the plan above it. The vision states the outcome the product aims for. The product roadmap lays out the themes and the releases across quarters. The release plan distributes the features of a release among its iterations. The iteration plan breaks the features of the coming iteration into user stories estimated in points, then into tasks. The PMBOK Guide traces this chain in its figure 5-1. It notes that many agile teams estimate in points rather than hours because a team compares two items better than it predicts a duration.
The Agile Extension maps the same levels to its planning horizons: the release plan belongs to the Initiative horizon and the iteration plan to the Delivery horizon. The Scrum Guide names the Product Goal and Sprint Planning. A Scrum team that announces release dates adds the technique to the framework. The team produces the release plan and the iteration plan in a planning workshop.
Building the plan
- Bring together the product owner, the team and the stakeholders involved in the dependencies. Take from the roadmap the release goal, its candidate features and the target date.
- Set the iteration length and derive from it the number of iterations up to the target date. This length is a timebox: when the work overruns, the team cuts scope and keeps the date.
- Order the backlog by value and estimate each feature in points by relative estimation.
- Take the velocity measured over recent iterations. A new team forecasts it: the team plans a first iteration in tasks. The points it commits to deliver in that iteration become its forecast velocity. The team replaces this forecast with the measurement once it has delivered its first iterations.
- Fill the iterations in backlog order up to the capacity: the velocity multiplied by the number of iterations. Whatever exceeds it moves to the next release. The release line marks the boundary between the two releases. Story mapping draws it on the map. If the scope is fixed, divide the total points by the velocity and round up. The result gives the number of iterations and therefore the date.
- Check the plan against the dependencies and the known absences, then have the product owner approve it.
Planning in rolling waves
The release plan applies the rolling wave planning that the PMBOK Guide describes: the team plans near-term work in detail and later work only in outline. The coming iteration holds stories and tasks. The later iterations hold features. The later releases hold only themes from the roadmap. Rolling wave estimation applies the same principle to estimating.
The Agile Extension treats each plan as a hypothesis that the delivered iterations confirm or correct. At the end of each iteration, the team plots the delivered work on a release burnup. It recalculates the remaining capacity from the measured velocity and moves the release line. The team draws one release line at the lowest velocity of recent iterations and another at the highest. The first shows what the release will contain. The second shows what it can contain.
The pitfalls
A team that breaks the whole release into stories at the start writes detail that is stale before the team reaches it. A product owner who presents the plan as a scope commitment promises too much. The date holds, but the content at the end of the release follows the velocity. The business must know this from the first presentation. Management that sets velocity as a target gets inflated estimates. The plan then rests on a false velocity.
Release or implementation unit in HERMES
HERMES 2022 divides delivery into steps in two ways.
| Release (agile approach) | Implementation unit (traditional approach) | |
|---|---|---|
| Phases | Execution divided into releases 1 to n | Implementation and Deployment repeated for each unit |
| Planning | Master plan before the execution release, then the next release in detail at the end of each release | All units planned in the Concept phase |
| Approval | Decision on release, mandatory if the project management plan prescribes it | Project steering releases each unit before it starts |
| End | Operation activated at the time the release plan sets | Product or system in productive use |
In an agile HERMES project, the release plan is part of the project management plan. The project manager keeps this plan up to date on the principle of rolling planning. The development team plans the detail of the iterations on its own. At the management level, planning covers coordination only. It resumes in the Closure phase.
AI considerations
An assistant connected to the backlog tool flags the features that are larger than one iteration (for the insured persons' portal: the pension certificate at 34 points, the retirement pension simulation at 40 and the early withdrawal request at 45). It proposes a split that the team then estimates. It recalculates the plan at 24, 30 and 36 points per iteration and shows which features cross the release line. It picks out from the story text the dependencies that nobody has recorded. It drafts the release report that HERMES requires at the close of each release.
The points remain the relative judgement of the people who will do the work: the assistant does not produce them. The product owner chooses what goes into the release by weighing value against the date. A backlog can contain customer data or describe known flaws in the system. The team gives it only to a tool that the organisation has approved.
Examples
A pension fund opens a portal for its insured persons. The team delivers in two-week iterations with a measured velocity of 30 points. Release 1 has six iterations.
| Order | Feature | Points | Cumulative | Available at the end of iteration | Available at 27 points from iteration 3 |
|---|---|---|---|---|---|
| 1 | Login and insured person's profile | 21 | 21 | 1 | 1 |
| 2 | Online pension certificate | 34 | 55 | 2 | 2 |
| 3 | Retirement pension simulation | 40 | 95 | 4 | 4 |
| 4 | Buy-in simulation for contribution years | 30 | 125 | 5 | 5 |
| 5 | Notice of a change of address or civil status | 20 | 145 | 5 | 6 |
| 6 | Secure messaging | 30 | 175 | 6 | release 2 |
| Release line: 6 iterations × 30 points = 180 points | |||||
| 7 | Early withdrawal request for home ownership | 45 | 220 | release 2 | release 2 |
The cumulative total decides what enters the release. With the early withdrawal request, the total reaches 220 points and exceeds the capacity of 180 by 40 points: the feature moves to release 2. If the measured velocity falls to 27 points from iteration 3, the capacity becomes 2 × 30 + 4 × 27 = 168 points. Secure messaging then moves to release 2 as well.
Visualisations
The planning levels are drawn as stacked tiers, from the longest horizon at the top to the shortest at the bottom. The release plan reads as a table: one row per feature in backlog order. The release burnup plots the cumulative work delivered per iteration against the total scope. The point where the delivered-work curve extended along its slope meets the total line gives the probable date.
Cost
| Phase | Level | Rationale |
|---|---|---|
| Preparation | Medium | An ordered and estimated backlog, a measured or forecast velocity. |
| Execution | Low | Half a day per release with the team and the product owner. One update at the end of each iteration. |
| Documentation | Low | A table or a view in the backlog tool. |
Tools
A spreadsheet is enough for one team: one row per feature, a points column, a cumulative column and a formula that divides the cumulative total by the velocity and rounds up. Jira and Azure DevOps attach items to a version or an iteration and chart the progress of the release. For the planning session, the team works on a wall board or an online whiteboard with one column per iteration.
Sources
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 8th edition, §2.3.2.2 (figure 2-22), section 5 (entries Agile release planning with figure 5-1 and Rolling wave planning): the place of the technique among the tools of the Develop Schedule process, its definition, the horizon of three to six months, the schedule expressed in features, the chain from the vision to the iteration plan, points as the common unit, near-term work planned in detail and later work in outline.
- IIBA, Agile Extension to the BABOK Guide v2, §3.3.3 Adaptive Planning, §7.8 Planning Workshops, Appendix A Glossary (release planning): the plan treated as a hypothesis, the release and iteration levels mapped to the Initiative and Delivery horizons, the content of the release plan.
- Swiss Confederation, Federal Chancellery, HERMES 2022, Project Management Reference Manual, 4.4.1.34 Project management plan, 5.4.3.36 Draw up project management plan, 5.4.3.40 Prepare release closure, 7.4.5.4 Planning in agile solution development, 7.4.6 Implementation units under traditional approach: the release plan in the project management plan, the decision on release, rolling planning, the release report, the autonomous planning of the iterations, the implementation units.
- Ken Schwaber and Jeff Sutherland, The Scrum Guide (November 2020), sections "Product Goal" and "Sprint Planning": the two planning levels that the framework names.